Viet Nam: Provincial Roads Improvement

Sovereign Project | 31367-013 Status: Closed

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Provincial Roads Improvement
Project Number 31367-013
Country Viet Nam
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1888-VIE: Provincial Roads Improvement
Asian Development Fund US$ 70.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Private sector development
Sector / Subsector

Transport - Road transport (non-urban)

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location 18 nothern provinces: Bac Giang, Bac kan, Dien Bien,Ha Giang,Ha Nam,Ha Tay,Hoa Binh,Lai Chau,Lang Son,Lao Cai, Phu Tho, Quang Ninh, Son La, Thai Nguyen,Thanh Hoa,Tuyen Quang,Vinh Phuc, Yen Bai,

Safeguard Categories

Environment B
Involuntary Resettlement
Indigenous Peoples

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Business Opportunities

Consulting Services An international consulting firm will be engaged to provide about 160 person-months of international and 2,000 person-months of domestic consultants to supervise construction, economic evaluation, environmental impact and monitoring, resettlement supervision and monitoring, and a substantial training component for Government officials and domestic consultant personnel involved with the Project. The consultant will also be responsible for engaging and overseeing the work of the PDOT's consulting firm in preparing sub-projects for each proposed provincial road. This involves conducting surveys and preparation of engineering designs, economic evaluation and resettlement plans, as needed.
Procurement Civil works will be implemented through a number of small contracts, each valued between $200,000 and $1,000,000. There will be about 8-20 of these contracts per province, for a total of about 200 contracts. Contracts will be procured using local competitive bidding procedures.

Responsible Staff

Responsible ADB Officer Thang Le
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Viet Nam Resident Mission
Executing Agencies
PMU-5, Ministry of Transport
Mr. Luu Van Dzung
PMU5@hn.vnn.vn
278 Ton Duc Thang Street, Hanoi, Vietnam

Timetable

Concept Clearance 08 Mar 1999
Fact Finding 14 May 2001 to 01 Jun 2001
MRM 20 Sep 2001
Approval -
Last Review Mission -
PDS Creation Date 06 Dec 2006
Last PDS Update 21 Oct 2009

Loan 1888-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
18 Dec 2001 02 Apr 2002 03 Sep 2002 31 Dec 2006 30 Jun 2009 08 Jul 2010
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 70.00 Cumulative Contract Awards
ADB 70.00 18 Dec 2001 73.75 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 18 Dec 2001 73.75 0.00 100%
Title Document Type Document Date
Provincial Roads Improvement Sector Project Project/Program Completion Reports Aug 2011
Provincial Roads Improvement Sector Project Reports and Recommendations of the President Nov 2001

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.