Bangladesh: Road Network Improvement and Maintenance

Sovereign Project | 32223-013 Status:

Summary

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents

None currently available.

Project Results

  •  

    153

    kilometers of road that have been built or upgraded

  •  

    485,940

    average daily vehicle-kilometers using roads built or upgraded in the first full year of operation

The results data reported above are limited to ADB's core sectors, as defined under Strategy 2020 and tracked through indicators in the ADB Results Framework. For definitions of results indicators, please see the ADB Results Framework Indicators Definition.


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Road Network Improvement and Maintenance
Project Number 32223-013
Country Bangladesh
Project Status
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1920-BAN: Road Network Improvement and Maintenance
Asian Development Fund US$ 65.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Private sector development
Sector / Subsector

Transport - Road transport (non-urban)

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome Loan closed on 30 June 2011 and accounts was closed on 19 December 2011. BRM has engaged one staff consultants and the consultant has submitted the draft PCR to ADB which is under review by ADB. Its parelal loan No. 8204-BAN(OFID) was closed on 30 June 2011 and its loan account was closed effective 19 July 2012.
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)

Status of implementation as of 31 December 2011 were as follows:

1. Progress of five road improvement contracts (RIC) are: RIC-1=46%, RIC-2=100%, RIC-3=26%, RIC-4=100% and RIC-5=100%.

2. Progress of four Periodic Road Maintenance contracts were as follows:

PRMC-1=100%, PRMC-2=100%, PRMC-3=100% & PRMC-4=100%.

3. Progress of one performanve based routine road maintenance cootract was 100%.

4. Progress of one road safety contract was 50%.

5. Supervision consultants work completed

6. Loan has been closed on 30 June 2011. The loan account was closed on 19 December 2011.

Geographical Location Northwest and the center-north regions in Bangladesh.

Summary of Environmental and Social Aspects

Environmental Aspects

The six roads will have no significant environmental impact because the Project will be executed only on the existing roads, none of which are in environmentally sensitive areas. The environmental impacts associated with the construction stage will include (i) disruption of traffic in the construction area; (ii) increased air pollution due to increasing dust and other volatile

chemical substance from asphalt plants; (iii) noise and vibration; (iv) disruption of the water system due to cut-and-fill and other earthworks; and (v) potential landslides associated with elevating some part of the road. All these impacts will occur only during the construction period. Mitigation measures will be adopted to minimize the impacts: (i) reroute the traffic with clear signs; (ii) maintain optimum moisture content during handling of soil, spray water to minimize dust, and maintain a safe distance between the asphalt plant and public facilities including education facilities; (iii) strictly control the construction works that create noise and vibration by prohibiting night work in the residential areas; (iv) provide for pumping of stagnant water and an adequate drainage system; and (v) stabilize road embankment side slopes, restrict construction in flood areas to only the dry season, and avoid road widening at pond sites. All these mitigation requirements will be included in the contract documents for the contractor. Clearly, all the impacts are temporary and manageable. The environmental impact associated with the operation of the Project is mainly on traffic safety; therefore, adequate traffic signs and physical

barriers to reduce motorist speed will be installed. The other important environmental impact that will not concentrate in the road areas is borrow pits excavation. In this context, strictly borrow pits operation will be adopted (e.g. restrict borrow pits in the fertile agriculture lands and areas prone to erosion and landslide, restore and rehabilitate former borrow pit areas).

Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Business Opportunities

Consulting Services Consulting services for supervising civil works for the road improvement and the periodic road maintenance components have been completed. An international consulting firm undertook supervision in association with domestic consultants. In addition to contract supervision, the consultants performed (i) design formance-based road maintenance and implement supervision maintenance; (ii) assess safety for existing roads, develop a black spot improvement plan, and procure and supervise civil works; and (iii) make a feasibility study for privatizing of RHDs maintenance equipment and workshops. Consulting services also be required for preparing a detailed design for the proposed Road Network Improvement and Maintenance Project II. The consultants were recruited in accordance with ADBs Guidelines on the Use of Consultants and other arrangements satisfactory to ADB for engaging domestic consultants.
Procurement Civil works contract packages were awarded in accordance with ADBs Guidelines. International competitive bidding procedures were followed for road improvement contracts, and national competitive bidding procedures were followed for the ADB-financed road maintenance contracts.

Responsible Staff

Responsible ADB Officer ADB Disclosure
Responsible ADB Department South Asia Department
Responsible ADB Division Bangladesh Resident Mission
Executing Agencies
Bangladesh Road Transport Authority
Mr. Syed Iftekhar Hossain
Alenbari, Old Airport Road, Tejgaon, Dhaka, Bangladesh
Roads and Highways Department
Mr. Md. Sohrab Uddin Miah
pdrnimp1@yahoo.com, ahp_1968@yahoo.com
Sarak Bhaban, Ramna, Dhaka-1000, Bangladesh

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
PDS Creation Date 01 Feb 2007
Last PDS Update 25 Jul 2012

Loan 1920-BAN

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
10 Oct 2002 03 Feb 2003 27 Oct 2003 31 Dec 2007 30 Jun 2011 19 Dec 2011
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 112.90 Cumulative Contract Awards
ADB 65.00 10 Oct 2002 34.29 0.00 98%
Counterpart 47.90 Cumulative Disbursements
Cofinancing 0.00 10 Oct 2002 34.93 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Satisfactory Satisfactory Satisfactory Satisfactory - Satisfactory

Loan 8204-BAN

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
25 Sep 2002 04 Feb 2003 15 Apr 2003 31 Dec 2007 30 Jun 2011 30 Jun 2012
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 0.00 Cumulative Contract Awards
ADB 0.00 25 Sep 2002 0.00 4.03 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 25 Sep 2002 0.00 4.03 100%
Title Document Type Document Date
Road Network Improvement and Maintenance Project: Project Completion Report Project/Program Completion Reports Mar 2013
Road Network Improvement and Maintenance Project Reports and Recommendations of the President Sep 2002

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.