Bangladesh: Railway Sector Investment Program (Tranche 4)

Sovereign Project | 32234-063 Status: Proposed

Summary

The fourth PFR was received on 17 February 2015. The government requested for a loan of $50 million OCR to finance completion of balance works on subprojects financed under tranches 1 and tranche 2. Bangladesh Railway has submitted project progress reports and an updated economic and financial analysis. No additional contract awards are planned under tranche 4. As not all reform conditions were achieved, policy dialogue was continued and sufficient progress with approval of the two main reform actions by the Prime Minister of Bangladesh was achieved in December 2015 to resume processing of tranche 4.

Latest Project Documents

None currently available.

Consulting Notices

See also: CMS

No notices are currently available for this project.

Procurement Notices

See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents

None currently available.


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Railway Sector Investment Program (Tranche 4)
Project Number 32234-063
Country Bangladesh
Project Status Proposed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan: MFF - Railway Sector Investment Program (Subproject 4)
Ordinary capital resources US$ 50.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Private sector development
Sector / Subsector

Transport - Rail transport (non-urban)

Gender Equity and Mainstreaming No gender elements
Description The fourth PFR was received on 17 February 2015. The government requested for a loan of $50 million OCR to finance completion of balance works on subprojects financed under tranches 1 and tranche 2. Bangladesh Railway has submitted project progress reports and an updated economic and financial analysis. No additional contract awards are planned under tranche 4. As not all reform conditions were achieved, policy dialogue was continued and sufficient progress with approval of the two main reform actions by the Prime Minister of Bangladesh was achieved in December 2015 to resume processing of tranche 4.
Project Rationale and Linkage to Country/Regional Strategy A multitranche financing facility (MFF) was approved on 10 October 2006 to improve the performance of the railway sector and to increase the capacity of the existing rail network to handle traffic demand necessary to sustain Bangladesh's economic growth. The MFF consists in financing four subprojects, out of which three are ongoing: (i) the construction of the 64 km Tongi Bhairab Bazar Double Line Project and the implementation of sector policy reforms designed to make Bangladesh Railway, more commercially focused (Tranche 1); (ii) the rehabilitation of yards, extension of loops and upgrading of signaling at different stations in the Darsana Ishurdi Sirajganj Bazar section (Tranche 2); and (iii) the procurement of 150 passenger carriages (Tranche 3). The proposed subproject (Tranche 4) will consist in funding the financing gap of Tranches 1 and 2. Most of the civil works have been completed as of December 2015.
Impact Efficient and safe railway transport in Bangladesh
Outcome Capacity in the Dhaka-Chittagong and Dhaka-Ishurdi-Darsana-Khulna/India corridor improved
Outputs

Infrastructure improvements commissioned

Equipment commissioned

Construction supervision services provided

Geographical Location
Safeguard Categories
Environment C
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects TBD
Involuntary Resettlement TBD
Indigenous Peoples TBD
Stakeholder Communication, Participation, and Consultation
During Project Design TBD
During Project Implementation TBD
Business Opportunities
Consulting Services No additional consultant recruitments are expected under this loan.
Procurement No additional contract awards are expected under this loan.
Responsible ADB Officer Markus Roesner
Responsible ADB Department South Asia Department
Responsible ADB Division Transport and Communications Division, SARD
Executing Agencies
Bangladesh Railway (BR)
Railway Div., Ministry of Communication
Rail Bhavan, Abdul Gani Road
Dhaka, Bangladesh
Timetable
Concept Clearance -
Fact Finding -
MRM 19 Feb 2016
Approval 31 Mar 2016
Last Review Mission -
Last PDS Update 15 Sep 2015

None currently available.

Safeguard Documents

See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents

See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.