Tuvalu: Maritime Training Project (supplementary loan)

Sovereign Project | 32407-023 Status:

Summary

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents

None currently available.


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Maritime Training Project (supplementary loan)
Project Number 32407-023
Country Tuvalu
Project Status
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2088-TUV: Maritime Training Project (supplementary loan)
Asian Development Fund US$ 1.97 million
Strategic Agendas Inclusive economic growth
Drivers of Change
Sector / Subsector

Education - Technical and vocational education and training

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome The project has been physically completed to assist TMTI to maintain its IMO recognition.
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues) All works under the project and the associated Technical assistance has been delivered. The physical works under the loan were completed in March 2010. The loan account is now financially closed
Geographical Location Amatuku Islet, Funafuti atoll, Tuvalu

Summary of Environmental and Social Aspects

Environmental Aspects

This initial environmental examination has determined that the proposed upgrading of TMTI and extension of shipping services offices can be constructed and operated with no significant negative environmental and social impacts, and that environmental and social benefits should result from proper operation of the facilities. This Project can be classified as Category B (relatively small scale), not requiring an environmental impact assessment. Subject to the implementation of specified mitigation measures, the Project should be able to proceed

without any significant negative effects.

Involuntary Resettlement No resettlement issues
Indigenous Peoples No issues
Stakeholder Communication, Participation, and Consultation
During Project Design Stakeholder consultations held during design of the original TMTI Loan 1921-TUV .
During Project Implementation Ongoing stakeholder consultations maintained during during project implementation towards reaching project completion.

Business Opportunities

Consulting Services Approximately 7 person-months of international consulting services were required for the project management unit and were estimated at US$177,000. Approximately 1.5 additional person-months of consulting services will be required to cover the extended period of construction supervision and necessary changes to some of the designs.
Procurement Goods and services financed by ADB under the Project will be procured in accordance with ADB's Guidelines for Procurement. The civil works have been tendered under international competitive bidding. Materials and equipment valued below $50,000 will be procured under direct purchase procedures. Funds from the supplementary loan will be used to finance part of the shortfall of the civil works contract. The received bids from the shortlisted firms for this ICB were all more than 100% above the appraisal estimates. The civil works contract will be offered for partial award to the lowest substantive responsive bidder for negotiations.

Responsible Staff

Responsible ADB Officer Alain Goffeau
Responsible ADB Department Pacific Department
Responsible ADB Division Pacific Subregional Office in Suva, Fiji
Executing Agencies
Ministry of Education and Sports
Minute Taupo
mtaupo@tuvalu.tv
Funafuti, Tuvalu

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
PDS Creation Date 15 Nov 2006
Last PDS Update 02 Sep 2011

Loan 2088-TUV

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
03 Aug 2004 13 Aug 2004 13 Jan 2005 30 Jun 2006 31 Mar 2010 25 May 2011
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 2.02 Cumulative Contract Awards
ADB 1.97 03 Aug 2004 2.02 0.00 99%
Counterpart 0.05 Cumulative Disbursements
Cofinancing 0.00 03 Aug 2004 2.05 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating Partly satisfactory Satisfactory - Partly satisfactory - Satisfactory
Title Document Type Document Date
Maritime Training Project Project/Program Completion Reports Sep 2011
Maritime Training Project (Supplementary) Reports and Recommendations of the President Jul 2004

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

Title Document Type Document Date
Tuvalu: Maritime Training Project Validations of Project Completion Reports Dec 2013

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.