Tajikistan: Power Rehabilitation Project

Sovereign Project | 32513-013

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Power Rehabilitation Project
Project Number 32513-013
Country Tajikistan
Project Status Closed
Project Type / Modality of Assistance Loan
Technical Assistance
Source of Funding / Amount
Loan 1817-TAJ: Power Rehabilitation Project
Asian Development Fund US$ 34.00 million
Loan: Power Rehabilitation Project
Islamic Development Bank US$ 9.30 million
Swiss Development Corporation US$ 6.00 million
TA 3600-TAJ: Improving Barki Tajik's Billing and Collection System
Japan Special Fund US$ 500,000.00
Strategic Agendas
Drivers of Change
Sector / Subsector For classification - For classification
Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Tajikistan
Safeguard Categories
Environment B
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer S. Vivekananda
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Energy Division, CWRD
Executing Agencies
Barki TajikMr. Samiev64 Somoni Street
Dushanbe 734026
Tajikistan
Timetable
Concept Clearance 18 Feb 1999
Fact Finding 10 Apr 2000 to 25 Apr 2000
MRM 19 Jul 2000
Approval 20 Dec 2000
Last Review Mission -
PDS Creation Date 05 Dec 2006
Last PDS Update 08 Jan 2009

Loan

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 28.89 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 13.59 Cumulative Disbursements
Cofinancing 15.30 - 0.00 0.00 %

Loan 1817-TAJ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
20 Dec 2000 26 Feb 2001 24 Aug 2001 30 Jun 2006 31 Dec 2008 23 Apr 2009
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 62.80 Cumulative Contract Awards
ADB 34.00 20 Dec 2000 39.95 0.00 100%
Counterpart 13.50 Cumulative Disbursements
Cofinancing 15.30 20 Dec 2000 39.95 0.00 100%

TA 3600-TAJ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
20 Dec 2000 15 Feb 2001 15 Feb 2001 31 Jan 2002 31 Mar 2004 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
500,000.00 0.00 88,000.00 0.00 0.00 0.00 588,000.00 20 Dec 2000 467,878.88
Title Document Type Document Date
Таджикистан: Проект по реабилитации энергетического сектора Project/Program Completion Reports Apr 2010
Power Rehabilitation Project Project/Program Completion Reports Dec 2009
Power Rehabilitation Project Reports and Recommendations of the President Nov 2000

Safeguard Documents

See also: Safeguards

No documents found.

Evaluation Documents

See also: Independent Evaluation
Title Document Type Document Date
Tajikistan: Power Rehabilitation Project Validations of Project Completion Reports Apr 2011

The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.