China, People's Republic of: Harbin Water Supply

Sovereign Project | 33177-013

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Harbin Water Supply
Project Number 33177-013
Country China, People's Republic of
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1995-PRC: Harbin Water Supply
Ordinary capital resources US$ 100.00 million
Loan: Harbin Water Supply
Fortis Bank S.A./N.V. US$ 179.60 million
Strategic Agendas
Drivers of Change
Sector / Subsector For classification - For classification
Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Harbin City
Safeguard Categories
Environment A
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Sangay Penjor
Responsible ADB Department East Asia Department
Responsible ADB Division Urban and Social Sectors Division, EARD
Executing Agencies
Harbin Municipal GovernmentMr. Liu YurunXQWANG@PUBLIC.HR.HL.CN, CELL: 13009725456233 Youyi Road, Daoli District
Harbin, Heilongjing Province
China 150018
Timetable
Concept Clearance 26 Mar 1999
Fact Finding 14 Jun 2002 to 29 Jun 2002
MRM 23 Aug 2002
Approval 11 Mar 2003
Last Review Mission -
PDS Creation Date 05 Jun 2006
Last PDS Update 15 Apr 2010

Loan

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 299.50 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 119.90 Cumulative Disbursements
Cofinancing 179.60 - 0.00 0.00 %

Loan 1995-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
11 Mar 2003 28 Aug 2003 07 Jan 2004 30 Jun 2008 28 Feb 2009 24 Mar 2009
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 399.50 Cumulative Contract Awards
ADB 100.00 11 Mar 2003 98.65 0.00 100%
Counterpart 119.90 Cumulative Disbursements
Cofinancing 179.60 11 Mar 2003 98.65 0.00 100%
Title Document Type Document Date
Harbin Water Supply Project Project/Program Completion Reports Jun 2009
Harbin Water Supply Project Reports and Recommendations of the President Feb 2003

Safeguard Documents

See also: Safeguards

Evaluation Documents

See also: Independent Evaluation
Title Document Type Document Date
People's Republic of China: Harbin Water Supply Project [Loan 1995-PRC] Project Performance Evaluation Reports Dec 2010
People's Republic of China: Harbin Water Supply Project Validations of Project Completion Reports Feb 2010

The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.