Lao People's Democratic Republic: Nam Ngum River Basin Development Sector Project

Sovereign Project | 33356-013 Status: Closed

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Nam Ngum River Basin Development Sector Project
Project Number 33356-013
Country Lao People's Democratic Republic
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1933-LAO: Nam Ngum River Basin Development Sector Project
Asian Development Fund US$ 15.00 million
Loan: Nam Ngum River Basin Development Sector Project
Agence Francaise de Developpement US$ 3.80 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector

Agriculture, natural resources and rural development - Water-based natural resources management

Gender Equity and Mainstreaming Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome

Department of Water Resources, under Water Resources & Environment Administration's (WREA), was established to build on technical IWRM capacities. Following completion of Component 1A, support to WREA's IWRM program has been taken up under the ADB/AusAID-financed TA "Updating the National Water Policy and Strategy Project" and its supplementary financing.

Extension activities were conducted to facilitate improved performance of (i) cropping systems; (ii) livestock and fisheries systems; and (iii) forest systems. This was achieved through participatory planning processes and better management of land, forests, water and natural resources at the village, khet (village cluster), district and provincial levels.

Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)

Instead of strengthening WRCCS, the Government reorganized IWRM institutional arrangements at the central and provincial levels by creating WREA. Under Component 1, the Project successfully carried out and supported the creation and organization of WREA.

Progress is underway on the establishment and strengthening of the NNRBC. The decree for the general establishment of river basin committees was approved in 2010. With this decree, river basin committees are initially expected to be formed for Nam Ngum and Nam Theun-Nam Kading river basins, as well as other priority basins.

Activities have been achieved under Component 2. Department of Energy (DoE) (formerly Hydropower Office) expressed its satisfaction on the training and awareness of a core modeling team, and corresponding capacity to operate MORDOR (Hydrological modeling) and PARSIFAL models. DoE plans to mainly use these models to carry out studies of optimization of hydropower production.

Under Component 3, activities being undertaken under the IWMU within the Department of Planning of MAF include the preparation of watershed baseline data profiles, of management and development strategies and plans, and working closely with the village, district and provincial planning process. Capacity-building activities include workshops and on-the-job training. Maps and databases relating to various aspects of the watersheds are held by the IWMU.

Extension activities were conducted in 22 subwatersheds within NNRB (in Xiengkhouang, Luang Prabang and Vientiane provinces and Vientiane Capital). The Project targeted 316 villages (160 in Vientiane and 95 in Xieng Khouang). Extension made steady progress to attain the Project's targets to increase rice yield, livestock performance and to increase income of 10,000 households. Attainment of Project targets were also done through provision of loans (VDF), extension of technical assistance by Khet Extension Service Centers, capacity building and infrastructures and through demonstration areas.

Geographical Location Covers the Nam Ngum River Basin in central Lao PDR, with an area of about 16,906 km2, in north-central LAO.

Safeguard Categories

Environment B
Involuntary Resettlement C
Indigenous Peoples

Summary of Environmental and Social Aspects

Environmental Aspects The initial environmental examination (IEE) indicates that the environmental impacts arising from the Project's construction and operation activities will be minor and can be minimized to acceptable levels using mitigation measures. An EMP has been prepared to ensure that all applicable national and provincial environmental laws, regulations, standards, and ADB environmental requirements are met during project implementation. The IEE study reports have been completed for 19 sub watersheds. All IEE reports have been produced, certified by STEA, and submitted to ADB for approval.
Involuntary Resettlement No resettlement was done during implementation of the Project.
Indigenous Peoples Ethnic groups are among the poorest and most vulnerable communities in the country. They suffer from social exclusion due to a variety of factors. The Project was designed to ensure their full participation in all relevant activities. They were mobilized and organized for culturally appropriate extension training, and livelihood development programs. Participatory rural assessments were carried out in association with Lao Front for National Contstruction, Lao Women's Union and non-government organizations. About 15% of the extension staff belonged to the ethnic groups.
Stakeholder Communication, Participation, and Consultation
During Project Design Consultations with key stakeholders were undertaken during project formulation and processing.
During Project Implementation Consultations with key stakeholders were undertaken during project implementation.

Business Opportunities

Consulting Services

The consulting consortium was mobilized on 20 July 2004. The contract is a single contract divided into two packages, financed by AFD and ADB. The contract originally provided for a total of 158 person months (pm) international and 146 pm national consultants. ADB financed one package of 48 PM of international and 42 PM of domestic consultants. All consultants work followed a consolidated work plan and reported to the single team leader engaged under the ADB package. Amendments have been made to the ADB and AFD funded inputs with a no-cost implication. A total of 171.95 PM of international inputs and 178.76 domestic inputs were provided under the consulting consortium's contract to all Project components.

In addition to the consulting firm, a total of 293.2 pm (101 pm international and 192.2 national) have been provided from ADB funding. The individual consultants were engaged for activities under Component 3 (Watershed Management).

Procurement Procurement of items for Component 1 (IWRM) was funded under the AFD grant, Component 2 (Reservoir Management and River Basin Modeling) was shared between ADB and AFD, and Component 3 was funded under the ADB loan. The procurement of goods were done in several lots during the implementation period and in accordance with ADB procurement guidelines. The Project included all procurement projections in the Annual Workplan and Budget which was approved by ADB annually.

Responsible Staff

Responsible ADB Officer Christopher Wensley
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Environment, Natural Resources & Agriculture Division, SERD
Executing Agencies
Ministry of Agriculture and Forestry
Mr. Sisovath Phandanouvong
nnrblao@gmail.com
2nd Floor Wooden House, Ministry of Agriculture & Forestry, Patouxay Square, Vientiane, Lao PDR

Timetable

Concept Clearance 14 Nov 2000
Fact Finding 22 May 2002 to 04 Jun 2002
MRM 18 Jul 2002
Approval 11 Nov 2002
Last Review Mission -
PDS Creation Date 23 Jan 2007
Last PDS Update 23 Feb 2011

Loan 1933-LAO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
11 Nov 2002 07 Feb 2003 11 Feb 2004 31 Mar 2009 30 Sep 2011 11 May 2011
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 23.00 Cumulative Contract Awards
ADB 15.00 11 Nov 2002 16.93 0.00 97%
Counterpart 4.20 Cumulative Disbursements
Cofinancing 3.80 11 Nov 2002 17.39 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory Satisfactory Satisfactory - Satisfactory
Title Document Type Document Date
Nam Ngum River Basin Development Sector Project: Project Completion Report Project/Program Completion Reports Jun 2016
Nam Ngum River Basin Development Sector Project Reports and Recommendations of the President Oct 2002

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.