Sri Lanka: Plantation Development

Sovereign Project | 34023-013

Latest Project Documents

Title Document Date
Plantation Development Project Aug 2002

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Plantation Development
Project Number 34023-013
Country Sri Lanka
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 1913-SRI: Plantation Development
Asian Development Fund US$ 20.00 million
Loan 1914-SRI: Plantation Development
Ordinary capital resources US$ 10.00 million
Loan: Plantation Development
Japan Bank for International Cooperation (ODA) US$ 25.00 million
Participating Financial Institutions US$ 8.50 million
Strategic Agendas
Drivers of Change
Sector / Subsector For classification - For classification
Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location The Project area covers 15 districts where the regional plantation companies are located.
Safeguard Categories
Environment B
Involuntary Resettlement C
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Marzia Mongiorgi-Lorenzo
Responsible ADB Department South Asia Department
Responsible ADB Division Environment, Natural Resources & Agriculture Division, SARD
Executing Agencies
Development Finance Corporation of CeylonJayantha NagendranJayantha.Nagendran@dfccbank.com73/5 Galle Road, Colombo 3
Ministry of Plantation Industries (MPI)Raja Premadasarajaprem@sltnet.lk55/75 Vauxhall Lane, Colombo 2
Timetable
Concept Clearance 04 Sep 2000
Fact Finding 21 Mar 2002 to 11 Apr 2002
MRM 22 May 2002
Approval 13 Sep 2002
Last Review Mission -
PDS Creation Date 12 Feb 2007
Last PDS Update 30 Mar 2009

Loan

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 33.50 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 0.00 Cumulative Disbursements
Cofinancing 33.50 - 0.00 0.00 %

Loan 1913-SRI

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
13 Sep 2002 08 Nov 2002 29 Aug 2003 30 Jun 2009 30 Nov 2009 22 Feb 2010
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 53.50 Cumulative Contract Awards
ADB 20.00 13 Sep 2002 9.03 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 33.50 13 Sep 2002 9.03 0.00 100%

Loan 1914-SRI

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
13 Sep 2002 08 Nov 2002 29 Aug 2003 30 Jun 2009 31 Jul 2009 26 Nov 2009
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 10.00 Cumulative Contract Awards
ADB 10.00 13 Sep 2002 4.55 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 13 Sep 2002 4.55 0.00 100%
Title Document Type Document Date
Plantation Development Project Reports and Recommendations of the President Aug 2002

Safeguard Documents

See also: Safeguards

No documents found.

Evaluation Documents

See also: Independent Evaluation
Title Document Type Document Date
Sri Lanka: Plantation Development Project Validations of Project Completion Reports Dec 2011

The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.