China, People's Republic of: Gansu Clean Energy Development Project

Sovereign Project | 34476-013

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Gansu Clean Energy Development Project
Project Number 34476-013
Country China, People's Republic of
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2032-PRC: Gansu Clean Energy Development Project
Ordinary capital resources US$ 35.00 million
Loan: Gansu Clean Energy Development Project
Bank of China US$ 38.00 million
Strategic Agendas
Drivers of Change
Sector / Subsector For classification - For classification
Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Gansu Province (Zhangye)
Safeguard Categories
Environment A
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer P. Abeygunawardena
Responsible ADB Department East Asia Department
Responsible ADB Division PRC Resident Mission
Executing Agencies
Gansu Provincial GovernmentMme. Zhang Xiaopingn.a.No. 696 Donggang West Road, Chengguan District, Lanzhou, Gansu, PRC,730000
Timetable
Concept Clearance 13 Jul 2000
Fact Finding 15 Jan 2003 to 24 Jan 2003
MRM 13 May 2003
Approval 05 Dec 2003
Last Review Mission -
PDS Creation Date 23 Jun 2006
Last PDS Update 10 Jun 2008

Loan

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 52.00 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 14.00 Cumulative Disbursements
Cofinancing 38.00 - 0.00 0.00 %

Loan 2032-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
05 Dec 2003 27 Apr 2004 04 Aug 2004 30 Apr 2008 - 02 Sep 2008
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 87.00 Cumulative Contract Awards
ADB 35.00 05 Dec 2003 34.04 0.00 100%
Counterpart 14.00 Cumulative Disbursements
Cofinancing 38.00 05 Dec 2003 34.04 0.00 100%
Title Document Type Document Date
Gansu Clean Energy Development Project: Project Completion Report Project/Program Completion Reports Aug 2009
Gansu Clean Energy Development Project: Report and Recommendation of the President Reports and Recommendations of the President Nov 2003

Safeguard Documents

See also: Safeguards
Title Document Type Document Date
Gansu Clean Energy Development Project: Land Acquisition and Resettlement Plan Resettlement Plans Dec 2003
Gansu Clean Energy Development Project Environmental Assessment and Measures Apr 2003

Evaluation Documents

See also: Independent Evaluation
Title Document Type Document Date
People’s Republic of China: Gansu Clean Energy Development Project Project Performance Evaluation Reports Dec 2013
People's Republic of China: Gansu Clean Energy Development Project [Loan 2032-PRC] Validations of Project Completion Reports Dec 2010

The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.