China, People's Republic of: Central Yunnan Roads Development Project

Sovereign Project | 36455-013 Status: Closed

Summary

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Central Yunnan Roads Development Project
Project Number 36455-013
Country China, People's Republic of
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2448-PRC: Central Yunnan Roads Development Project
Ordinary capital resources US$ 200.00 million
Loan: Central Yunnan Roads Development Project
Industrial and Commercial Bank of China US$ 211.50 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change Governance and capacity development
Sector / Subsector

Transport - Road transport (non-urban)

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome Construction is ongoing satisfactorily and about 85% completed
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)

construction ongoing

ongoing

ongoing

To be assessed at project completion

To be assessed at project completion

To be assessed at project implementation.

servcices of consulting firm ongoing

survey ongoing

Geographical Location Yunnan Province

Safeguard Categories

Environment A
Involuntary Resettlement A
Indigenous Peoples A

Summary of Environmental and Social Aspects

Environmental Aspects

This is an environmental category A project. The environmental impact assessment (EIA) for the expressway was prepared by YPCD and approved by the Ministry of Environmental Protection in April 2007. A major environmental issue is erosion control. A soil erosion prevention plan was prepared and approved by the Ministry of Water Resources in December

2006. A summary initial environmental examination for the local roads was conducted during project preparation, which concluded that this component would not require an EIA, given that the civil works are for pavement, drainage installation, and slope protections. On the basis of the EIA, social erosion prevention plan and the field survey, a summary EIA has been prepared and endorsed by YPCD, circulated to ADB's Board of Directors, and made public through ADB's website on 3 May 2007. The EIA and summary EIA assessed the environmental impact of the Project and prescribed environmental protection and mitigation measures costing CNY57.6 million. To ensure that all the potential adverse environmental impacts of the project are mitigated, YPCD will implement the environmental management plan as specified in the EIA and summary EIA. The EMP will be incorporated in the bidding documents and contracts for civil works; it will be monitored and reported on to ADB semiannually.

Involuntary Resettlement This is an involuntary resettlement category A project. YPCD has prepared a resettlement plan for the expressway and a short resettlement plan for the seven local roads. The land use pre-examination was approved by the Ministry of Land and Resources on 24 January 2008. By Novembere 2012, the project land acquisition and resettlement actives commenced in July 2009 and resettlement activities were still ongoing, particularly for construction of concentrated resettlement sites. So far a total of 6,264 mu of land were permanently acquired. The number of people affected by land acquisition was 22,144. A total of 266,300 m2 of buildings were demolished. The number of people affected by house demolition was 3,299. Land acquisition and resettlement impacts were minimized by aligning the expressway away from towns, village centers, and paddy lands, where possible; the urban section will be elevated to reduce impacts and disturbance. The seven local roads for upgrading include roads only require resurfacing within the existing alignment, so no resettlement will be necessary, but the short resettlement plan will provide the basis for due diligence.
Indigenous Peoples This is an indigenous peoples category A project. Ethnic minorities in the project area comprise 25% of the beneficiaries. Mitigation measures will address potential social risks, including resettlement, environmental disturbance, and transmissible diseases; these risks are mainly focused along the project expressway corridor. Enhancement measures (such as local roads, local road safety, small business development, tourism promotion, and skills training) have been targeted in poor counties in the project area, which have high concentrations of ethnic minorities and poverty villages, especially the Miao and Lisu nationalities. Special measures will be targeted at women.
Stakeholder Communication, Participation, and Consultation
During Project Design Over 2,430 people were interviewed during the preparation of the feasibility study, environmental assessment, social assessment, resettlement planning and EMDP consultations. For the assessments on environment, resettlement, and ethnic minorities, consultations were held with representatives of affected counties, townships and villages. Both rural people and urban people were familiar with the project and public support for it was high. The consultation and participation process has influenced the Project design and alignment, and the formulation of the Environmental Management Plan (EMP), RP and EMDP. To ensure equal benefit from the project, the poor, ethnic minority groups and other vulnerable groups, such as women, were separately consulted. Their needs and comments were considered in the design of project components, such as local road improvement and safety enhancement program.
During Project Implementation Stakeholder participation and consultations are ongoing.

Business Opportunities

Consulting Services The Project will finance 36 person-months of international consulting services, including 15 person-months for the team leader of the international consultants; 6 person-months each for (i) bridge, and (ii) tunnel specialists; and 3 person-months each for (i) road safety, (ii) highway design, and (iii) ITS specialists. A program for overseas training, including 85 person-months, will be included in the Project. A consulting firm will be engaged based on a full technical proposal through the quality- and cost-based selection (80% quality and 20% cost) procedures in accordance with ADB's Guidelines on the Use of Consultants (2007, as amended from time to time). The Project will also provide $100,000 to finance a local road traffic safety strategy study. Given the very small contract values and the intensive relevant experience of the national firm proposed by YPCD in the areas of the study, the firm will be selected using the single source selection method in accordance with ADB's Guidelines on the Use of Consultants. In addition, YPCD will engage and entirely finance 5,500 person-months of national consultants. The national consultants, not financed by ADB, will be recruited in accordance with government procedures acceptable to ADB. The chief supervision engineer will be responsible for overall project supervision, assisted by two deputies, one of whom will be the team leader of the international consultants.
Procurement

All ADB-financed procurement will follow ADB's Procurement Guidelines (2007, as amended from time to time). The expressway works will be divided into 18 packages, 15 of which will be financed by ADB and procured under international competitive bidding procedures. ADB-financed equipment will be procured under international competitive bidding procedures. All other packages, including equipment for tolling, telecommunication, traffic monitoring and lighting; landscaping works, buildings, and ancillary facilities will be financed by the Government and procured under national competitive bidding (NCB) procedures. Various thresholds for procurement and the contract packages are set out in the procurement plan.

All road safety enhancement works estimated to cost $200,000 or more will be procured through NCB procedures in accordance with the PRC Tendering and Bidding Law, 1999, including clarifications agreed with ADB. All local road safety enhancement contracts expected to cost less than $200,000 will be procured using shopping procedures. Given the nature of the local road safety enhancement works, force account may be employed for works valued at less than $100,000 when size and location make it unsuitable to adopt shopping procedures (this may include work such as warning posters and signs on local roads, minor poster painting works, and other small and remote scattered works).

Responsible Staff

Responsible ADB Officer Chenglong Chu
Responsible ADB Department East Asia Department
Responsible ADB Division PRC Resident Mission
Executing Agencies
Yunnan Provincial Department of Transport
Mr. Yang Yubao
No. 1 Huang Cheng Xi Road
Kunning, Yunnan
Harbin,People's Republic of China

Timetable

Concept Clearance 31 Aug 2006
Fact Finding 22 Jan 2007 to 30 Jan 2007
MRM 16 May 2007
Approval -
Last Review Mission -
PDS Creation Date 25 Jul 2007
Last PDS Update 11 Sep 2014

Loan 2448-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
25 Sep 2008 27 Mar 2009 31 Aug 2009 30 Jun 2013 31 Mar 2014 08 Jul 2014
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 745.00 Cumulative Contract Awards
ADB 200.00 25 Sep 2008 200.00 0.00 100%
Counterpart 333.50 Cumulative Disbursements
Cofinancing 211.50 25 Sep 2008 200.00 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - - - - - Satisfactory

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Central Yunnan Roads Development Project: Social Monitoring Report (October 2014) Social Monitoring Reports Oct 2014
Central Yunnan Roads Development Project: Social Monitoring Report (September 2014) Social Monitoring Reports Sep 2014
滇中道路發展項目:環境監測報告(1月至2013年12月) Environmental Monitoring Reports Jan 2014
Central Yunnan Roads Development Project: Social Monitoring Report (July 2013) Social Monitoring Reports Jul 2013
Central Yunnan Roads Development Project: Social Monitoring Report (June 2013) Social Monitoring Reports Jun 2013
Central Yunnan Roads Development Project: Environmental Monitoring Report (July-December 2012) Environmental Monitoring Reports Mar 2013
Central Yunnan Roads Development Project: Wuding-Kunming Expressway Social Monitoring Reports Oct 2012
滇中道路發展項目:環境監測報告(2012年1月 - 6月) Environmental Monitoring Reports Jul 2012
Central Yunnan Roads Development Project: Environmental Monitoring Report (July-December 2011) Environmental Monitoring Reports Jan 2012
Central Yunnan Roads Development Project: Environmental Monitoring Report (January-June 2011) Environmental Monitoring Reports Jul 2011
Central Yunnan Roads Development Project: Wuding-Kunming Expressway Social Monitoring Reports Jun 2011
Central Yunnan Roads Development Project: Wuding-Kunming Expressway Resettlement Plans Feb 2011
Central Yunnan Roads Development Project: Wuding-Kunming Expressway Social Monitoring Reports Feb 2011
滇中道路發展項目:環境監測報告(2010年7月) Environmental Monitoring Reports Jan 2011
Central Yunnan Roads Development Project: Environmental Monitoring Report (January-June 2010) Environmental Monitoring Reports Aug 2010
Central Yunnan Roads Development Project Indigenous Peoples Plans/Indigenous Peoples Development Plans May 2007
Central Yunnan Roads Development Project Environmental Assessment and Measures Apr 2007

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.