India: MFF - Rural Roads Sector II Investment Program - Tranche 5

Sovereign Project | 37066-063 Status: Closed

Summary

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name MFF - Rural Roads Sector II Investment Program - Tranche 5
Project Number 37066-063
Country India
Project Status Closed
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2651-IND: MFF - Rural Roads Sector II Investment Program - Tranche 5
Ordinary capital resources US$ 203.81 million
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector

Transport - Road transport (non-urban)

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome

As of 30 June 2014, a total of 1,487 habitations have been connected with breakdown as follows: i) Orissa - 347; ii) Madhya Pradesh - 825; iii) West Bengal - 164, and iv) Chattisgarh - 151.

All activities completed.

Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)

As of 30 June 2014, 4,136 km completed with breakdown as follows: Chhattisgarh - 310 km, Orissa - 1,157 km, Madhya Pradesh - 2,246 km, and West Bengal - 423 km.

Target is fully achieved.

Geographical Location

Safeguard Categories

Environment B
Involuntary Resettlement C
Indigenous Peoples C

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Business Opportunities

Consulting Services The Project has no provision for financing consulting services. The services of TSC will continue to be financed under Project 4 loan proceeds and will include conducting safeguard due diligence, impact monitoring, preparation of project completion reports and other services for all projects under the MFF according to the terms of reference.
Procurement Under the advance contracting and retroactive financing provisions of the Facility Financing Agreement, Madhya Pradesh started advance procurement action under proposed Project 5 in November 2009 and by March 2010 subcontracts amounting to more than $58 million were awarded. Orissa started advance procurement action in February 2009, and by March 2010 subcontracts amounting to mover than $70 million were awarded packages exceeded more than $17 million. Procurement of civil works followed national competitive bidding procedure using the PMGSY standard bidding documents and procedures with the agreed ADB-financing specific adjustments in the areas of eligibility, anticorruption, social and environmental safeguards.

Responsible Staff

Responsible ADB Officer Ashok Srivastava
Responsible ADB Department South Asia Department
Responsible ADB Division India Resident Mission
Executing Agencies
Ministry of Rural Development
Krishi Bhawan
New Delhi 110001
India

Timetable

Concept Clearance -
Fact Finding -
MRM 06 Mar 2010
Approval -
Last Review Mission -
Last PDS Update 23 Mar 2015

Loan 2651-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
06 Jul 2010 02 Aug 2010 29 Oct 2010 30 Jun 2013 30 Jun 2014 01 Jan 2015
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 203.81 Cumulative Contract Awards
ADB 203.81 06 Jul 2010 192.26 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 06 Jul 2010 192.26 0.00 100%

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.