Tajikistan: Education Sector Reform

Sovereign Project | 37175-013

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Education Sector Reform
Project Number 37175-013
Country Tajikistan
Project Status Closed
Project Type / Modality of Assistance Grant
Loan
Technical Assistance
Source of Funding / Amount
Loan 2053-TAJ: Education Sector Reform
Asian Development Fund US$ 7.50 million
TA 4267-TAJ: Strengthening Planning and Policy Dialogue for Education Sector Reform
Japan Special Fund US$ 300,000.00
Grant 9040-TAJ: School Improvement Project
Japan Fund for Poverty Reduction US$ 2.00 million
Strategic Agendas
Drivers of Change
Sector / Subsector For classification - For classification
Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment C
Involuntary Resettlement
Indigenous Peoples
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Asadullah Sumbal
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Public Management, Financial Sector and Trade Division, CWRD
Executing Agencies
Office of the President*Ms. H. Mavlonova80 Rudaki Avenue
Dunshanbe
Republic of Tajikistan
Timetable
Concept Clearance 30 Jun 2003
Fact Finding 20 Feb 2003 to 06 Mar 2003
MRM 27 May 2003
Approval 17 Dec 2003
Last Review Mission -
PDS Creation Date 12 Dec 2006
Last PDS Update 06 Jan 2010

Grant 9040-TAJ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
13 Jan 2004 08 Apr 2004 08 Apr 2004 31 Dec 2008 - 31 Aug 2009
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 2.00 Cumulative Contract Awards
ADB 0.00 13 Jan 2004 0.00 1.72 86%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 2.00 13 Jan 2004 0.00 1.72 86%

Loan 2053-TAJ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
17 Dec 2003 15 Apr 2004 15 Jul 2004 30 Jun 2009 - 03 Jun 2010
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 9.43 Cumulative Contract Awards
ADB 7.50 17 Dec 2003 7.67 0.00 100%
Counterpart 1.93 Cumulative Disbursements
Cofinancing 0.00 17 Dec 2003 7.67 0.00 100%

TA 4267-TAJ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
17 Dec 2003 08 Apr 2004 08 Apr 2004 31 Jul 2005 30 Jul 2008 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
300,000.00 0.00 0.00 0.00 0.00 0.00 300,000.00 17 Dec 2003 186,784.91
Title Document Type Document Date
Education Sector Reform Project Project/Program Completion Reports Dec 2010
Education Sector Reform Project Reports and Recommendations of the President Nov 2003

Safeguard Documents

See also: Safeguards

No documents found.

Evaluation Documents

See also: Independent Evaluation
Title Document Type Document Date
Tajikistan: Education Sector Reform Project Validations of Project Completion Reports Sep 2013

The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.