Cambodia: Tonle Sap Lowlands Rural Development Project

Sovereign Project | 37287-013 Status: Active

Summary

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Tonle Sap Lowlands Rural Development Project
Project Number 37287-013
Country Cambodia
Project Status Active
Project Type / Modality of Assistance Grant
Loan
Source of Funding / Amount
Grant 0092-CAM: Tonle Sap Lowlands Rural Development Project
Asian Development Fund US$ 9.90 million
Loan 2376-CAM: Tonle Sap Lowlands Rural Development Project
Asian Development Fund US$ 10.10 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector

Agriculture, natural resources and rural development - Agricultural policy, institutional and capacity development - Agricultural production - Irrigation - Rural market infrastructure

Transport - Road transport (non-urban)

Gender Equity and Mainstreaming Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome By the end of December 2014, the overall physical progress was estimated at 95% against the elapsed loan and grant period of 88%. The cumulative contract awards were $9.77 million and $8.63 million, equivalent to 99% and 87% of the total loan and grant amounts, respectively. The cumulative disbursements were $9.36 million and $8.97 million, equivalent to 95% and 91% of the total loan and grant amounts, inclusive of advances to the imprest account, respectively.
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)

149 out of 152 small-scale subprojects have been completed in 40 targeted communes in three provinces. Construction progress for the remaining 3 sub-projects is estimated at 90%.

70 small businesses have been established.

31.3 km of main canals, 55.9 of secondary canals,

19.8 Km tertiary canal, and 697 structures small and large structures have been completed.

49 out of 57 subprojects in three target provinces have been completed. Eight other civil works subprojects are about 98% complete. The total irrigated areas rehabilitated by the project are 13,376 ha, which is 139% of the original target of 9,600 ha.

8 FWUGs have been established and another 14 are being established.

Construction works for 54 sub-projects to rehabilitate 205.91 km of roads have been completed, which is equivalent to 90% of the target of 230 km. Out of the 205.91 km, 84.7 km are road maintenance.

Nine road maintenance committee have been established. Other 21 are being formed.

Selected farmers in 40 communes of three project provinces have been trained to microfinance through self help groups and saving groups. 3,206 beneficiaries utilized local saving-led credit system.

Selected farmers in 40 communes have been sent to on-farm/off-farm trainings. 66% of the participants are women.

More than 30% women of participants have attended the trainings.

Over 200 project staff have been selected and trained

Late submissions of the inception and quarterly reports were observed in 2010, but the EA improved its submissions in 2011, 2012, 2013, and 2014.

Lengthy start-up delay due to complex project design. However, there is no problem for the Project to be completed on time.

Geographical Location Provinces of Kampong Chhang, Kampong Thom, and Pursat

Summary of Environmental and Social Aspects

Environmental Aspects No issue
Involuntary Resettlement No issue
Indigenous Peoples N.A
Stakeholder Communication, Participation, and Consultation
During Project Design No issue
During Project Implementation No issue

Business Opportunities

Consulting Services The Project requires a total of 31 person-months (pm) of international specialists and 204 pm of national specialists for a total of 235 pm to support the implementation and capacity building initiatives. Consultants have been selected and engaged in accordance with ADB's Guidelines on the Use of Consultants. For the project management and implementation consultants, the PMU is responsible for the recruitment of a consulting firm using QCBS. The Project requires (i) international and national consultants to assist the PMU with project management and implementation; (ii) international and national training consultants to prepare and assist in the operation of the capacity building component; (iii) national consultants to assist the provincial agencies with community participation, provincial level planning, subproject identification and the preparation of the environmental assessments, resettlement plans; and (iv) national engineering consultants to prepare detailed engineering designs and supervise construction works.
Procurement All procurement for the Project carried out in compliance with Government's Standard Operating Procedures for Externally Assisted Projects. Procurement activities are mainly undertaken by the executive committee of the Provincial Rural Development Committee. Goods and works financed by ADB are procured in accordance with ADB's Guidelines for Procurement.

Responsible Staff

Responsible ADB Officer Piseth Long
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Cambodia Resident Mission
Executing Agencies
Ministry of Water Resources and Meteorology
H.E. Veng Sakhon
sakhonv@online.com.kh
Ministry of Water Resources and Meteorology, Phnom Penh

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
PDS Creation Date 07 Apr 2006
Last PDS Update 31 Mar 2015

Grant 0092-CAM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
05 Dec 2007 18 Feb 2008 05 Nov 2008 30 Jun 2015 31 Dec 2015 -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 9.90 Cumulative Contract Awards
ADB 9.90 05 Dec 2007 9.90 0.00 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 05 Dec 2007 9.88 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - - - Satisfactory - -

Loan 2376-CAM

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
05 Dec 2007 18 Feb 2008 05 Nov 2008 30 Jun 2015 31 Dec 2015 -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 14.10 Cumulative Contract Awards
ADB 10.10 05 Dec 2007 9.58 0.00 97%
Counterpart 4.00 Cumulative Disbursements
Cofinancing 0.00 05 Dec 2007 9.84 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - - - Satisfactory - -

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.