Tajikistan: Dushanbe-Kyrgyz Border Road Rehabilitation Project, Phase II (TAJ)

Sovereign Project | 38236-022 Status:

Summary

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Dushanbe-Kyrgyz Border Road Rehabilitation Project, Phase II (TAJ)
Project Number 38236-022
Country Tajikistan
Project Status
Project Type / Modality of Assistance Grant
Loan
Source of Funding / Amount
Grant 0023-TAJ: Dushanbe-Kyrgyz Border Road Rehabilitation Project, Phase II (Supplementary)
Asian Development Fund US$ 500,000.00
Grant 0154-TAJ: Dushanbe-Kyrgyz Border Road Rehabilitation Project, Phase II (Supplementary)
Asian Development Fund US$ 20.00 million
Loan 2196-TAJ: Dushanbe-Kyrgyz Border Road Rehabilitation Project, Phase II (Supplementary)
Asian Development Fund US$ 29.50 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change Governance and capacity development
Sector / Subsector

Transport - Road transport (non-urban)

Gender Equity and Mainstreaming Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome All the work at km 95-217 were completed by October 2012, and the section is fully open to traffic. Maintenance goods were installed by June 2013 at the Karamyk border and other designated areas and are well utilized by the executing agency (Ministry of Transport) for realizing smooth traffic. ADB fielded the project completion review mission in February/March 2013.
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)

Rehabilitated 72.9 km of the section at km 140-217.

Rehabilitated 27 km of the section at km 95-140 (12 km at km 95-107 and 15 km in total at km 112-140).

Constructed emergency bypass in 2011.

All the equipment were procured, delivered and assembled at the designated sites, in accordance with the requirement in the contract. The entire works were completed in June 2013.

Geographical Location Obigarm-Nimich, Karamyk border section,Republic of Tajikistan

Summary of Environmental and Social Aspects

Environmental Aspects During implementation, semi-annual safeguard monitoring reports were submitted in accordance with the Grant Agreement and the Project Administration Manual (PAM). The construction supervision consultant closely monitored the contractors' full compliance with their site-specific environmental management plans, and the contractors met with the requirement of submitting regular safeguard monitoring reports.
Involuntary Resettlement Throughout the project, no land acquisition and resettlement activity was involved. Nonetheless, the construction supervision consultant monitored closely any impact from social safeguard perspectives during implementation.
Indigenous Peoples Not applicable.
Stakeholder Communication, Participation, and Consultation
During Project Design Due diligence was carried out during preparation and implementation-covering technical, social, and safeguards issues. In parallel to L2196-TAJ's implementation, nongovernment organizations and potential affected local communities were engaged during the project processing as needed.
During Project Implementation Due diligence works were carried out during implementation in technical, social and safeguard terms.

Business Opportunities

Consulting Services Construction supervision consultants are engaged in accordance with ADB's Guidelines on the Use of Consultants (2007, as amended from time to time) by varying the existing contracts under L2196 and G0085. The Government of Tajikistan engages audit service consultants under coordination with Tajikistan Resident Mission (block audit).
Procurement MOT procured contractors for civil works in accordance with ADB's Procurement Guidelines (2007, as amended from time to time). International and national competitive bidding was applied, as well as varying the existing contracts. This will ensure continuity, and adherence to existing implementation schedules. The same arrangement is applied to the procurement of goods.

Responsible Staff

Responsible ADB Officer Rika Idei
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Transport and Communications Division, CWRD
Executing Agencies
Ministry of Health
Mr.Ruziev
16 Shevchenko St.
Dushanbe
Tajikistan
Ministry of Transport
Mr. Shokulov Ismonkul Salimovich, Executive Director for Project Implementation Unit for Roads Rehabilitation
piurr@tojikiston.com
14, Aini Street Dushanbe 734042 Tajikistan

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
PDS Creation Date 19 Mar 2008
Last PDS Update 08 Sep 2013

Grant 0023-TAJ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
17 Nov 2005 14 Feb 2006 13 Mar 2006 31 Dec 2009 - 19 Jan 2010
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 0.50 Cumulative Contract Awards
ADB 0.50 17 Nov 2005 0.49 0.00 98%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 17 Nov 2005 0.49 0.00 98%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory Satisfactory Satisfactory - Satisfactory

Grant 0154-TAJ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
24 Jul 2009 07 Aug 2009 03 Sep 2009 31 Dec 2012 30 Jun 2013 30 Aug 2013
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 25.00 Cumulative Contract Awards
ADB 20.00 24 Jul 2009 20.00 0.00 100%
Counterpart 5.00 Cumulative Disbursements
Cofinancing 0.00 24 Jul 2009 20.00 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory Satisfactory Satisfactory - Satisfactory

Loan 2196-TAJ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
17 Nov 2005 14 Feb 2006 13 Mar 2006 31 Dec 2009 30 Sep 2010 16 Nov 2010
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 29.50 Cumulative Contract Awards
ADB 29.50 17 Nov 2005 30.88 0.00 99%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 17 Nov 2005 31.21 0.00 100%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - Satisfactory Satisfactory Satisfactory - Satisfactory

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

Title Document Type Document Date
Tajikistan: Dushanbe–Kyrgyz Border Road Rehabilitation Project, Phase II Validations of Project Completion Reports Dec 2014

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.