Bangladesh: Emergency Flood Damage Rehabilitation Project

Sovereign Project | 38625-013

Summary

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Emergency Flood Damage Rehabilitation Project
Project Number 38625-013
Country Bangladesh
Project Status Closed
Project Type / Modality of Assistance Loan
Technical Assistance
Source of Funding / Amount
Grant 0038-BAN: Emergency Flood Damage Rehabilitation Project
Netherlands Fund (with LoA) US$ 13.00 million
Grant 0039-BAN: Emergency Flood Damage Rehabilitation Project
Sweden (Sida) (w/ LoA) US$ 14.70 million
Loan 2156-BAN: Emergency Flood Damage Rehabilitation Project
Asian Development Fund US$ 152.30 million
Loan: Emergency Flood Damage Rehabilitation Project
Swedish International Dev. Cooperation Agency US$ 14.70 million
TA 4561-BAN: Support for Financial Management and Monitoring
Technical Assistance Special Fund US$ 150,000.00
Strategic Agendas
Drivers of Change
Sector / Subsector For classification - For classification
Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Central and Northern region of Bangladesh
Safeguard Categories
Environment B
Involuntary Resettlement B
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Hans Carlsson
Responsible ADB Department South Asia Department
Responsible ADB Division Bangladesh Resident Mission
Executing Agencies
Local Government Engineering DepartmentM.Wahidur Rahman and M.Abdul Gaffarwahid@LGED.ORG, agaffar@lged.orgLGED Bhaban (L-2), Agargaon, Dhaka
Bangladesh Railway (BR)Habib AhmedJBRLPCON@CITECHCO.NETRail Bhaban, Abdul Gani Road, Dhaka-1000
Roads and Highways DepartmentA.K.M.Rezaul Haquesutradharp@rhd.gob.bdSarak Bhaban, Ramna, Dhaka
Ministry of Local Gov't,Rural Dev't,&Co-operativesRural Development and Cooperatives
Room 632, Bldg 7
Block-B, Dhaka-1207, Bangladesh
Bangladesh Water Development BoardM.Humayun Kabirefdrp2004@yahoo.com6/1, Block-A (1st Floor, East), Lalmatia, Dhaka-1207
Timetable
Concept Clearance 16 Jan 2005
Fact Finding 12 Sep 2004 to 27 Sep 2004
MRM 24 Nov 2004
Approval 20 Jan 2005
Last Review Mission -
PDS Creation Date 31 Jan 2007
Last PDS Update 16 Jul 2008

Grant 0038-BAN

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
15 Nov 2005 27 Apr 2006 02 May 2006 31 Jul 2007 - 13 Dec 2007
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 13.00 Cumulative Contract Awards
ADB 0.00 15 Nov 2005 0.00 10.75 83%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 13.00 15 Nov 2005 0.00 10.75 83%

Grant 0039-BAN

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
15 Nov 2005 27 Apr 2006 02 May 2006 31 Jul 2007 - 13 Dec 2007
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 14.70 Cumulative Contract Awards
ADB 0.00 15 Nov 2005 0.00 14.70 100%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 14.70 15 Nov 2005 0.00 14.70 100%

Loan

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 74.81 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 60.11 Cumulative Disbursements
Cofinancing 14.70 - 0.00 0.00 %

Loan 2156-BAN

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
20 Jan 2005 02 Feb 2005 02 May 2005 31 Jul 2007 - 13 Dec 2007
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 227.05 Cumulative Contract Awards
ADB 152.30 20 Jan 2005 136.85 0.00 100%
Counterpart 60.05 Cumulative Disbursements
Cofinancing 14.70 20 Jan 2005 136.85 0.00 100%

TA 4561-BAN

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
20 Jan 2005 - 20 Jan 2005 14 Feb 2007 31 Aug 2007 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
150,000.00 0.00 0.00 0.00 0.00 0.00 150,000.00 20 Jan 2005 122,576.94

TA 4562-BAN

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
20 Jan 2005 23 Apr 2005 23 Apr 2005 14 Aug 2005 30 Sep 2007 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
0.00 0.00 62,500.00 0.00 0.00 0.00 62,500.00 20 Jan 2005 184,226.81
Title Document Type Document Date
Emergency Flood Damage Rehabilitation Project Project/Program Completion Reports Jun 2008
Emergency Flood Damage Rehabilitation Project Reports and Recommendations of the President Jan 2005

Safeguard Documents

See also: Safeguards

No documents found.

Evaluation Documents

See also: Independent Evaluation
Title Document Type Document Date
Bangladesh: Emergency Flood Damage Rehabilitation Project Validations of Project Completion Reports Dec 2009

The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.