The objective of the project is to prepare the Southern Road Corridor Improvement Project so that it is suitable for ADB financing. The scope of the project is to undertake a feasibility study and preliminary design of the project, as well as safeguard documents in accordance with ADB requirements.

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Southern Road Corridor Improvement Project (Alyat-Astara Road)
Project Number 39176-012
Country Azerbaijan
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 4684-AZE: Southern Road Corridor Improvement Project (Alyat-Astara Road)
Japan Special Fund US$ 700,000.00
TA 4684-AZE: Southern Road Corridor Improvement Project
Technical Assistance Special Fund US$ 430,000.00
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change
Sector / Subsector Transport - Road transport (non-urban)
Gender Equity and Mainstreaming No gender elements
Description The objective of the project is to prepare the Southern Road Corridor Improvement Project so that it is suitable for ADB financing. The scope of the project is to undertake a feasibility study and preliminary design of the project, as well as safeguard documents in accordance with ADB requirements.
Project Rationale and Linkage to Country/Regional Strategy The project belongs to one of the strategically selected areas for ADB assistance in Azerbaijan and is in line with the poverty reduction strategy outlined in the State Program on Poverty Reduction and Economic Development that include, among others, improvement of road infrastructure.
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location Southern Azerbaijan
Safeguard Categories
Environment A
Involuntary Resettlement A
Indigenous Peoples B
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Business Opportunities
Consulting Services The TA will require 74 person-months of consultant's input, comprising 21 person-months of international consultants and 53 person-months of domestic consultants. The international consultants will include (i) transport economist/team leader, (ii) highway engineer, (iii) pavement specialist, (iv) institutional specialist, (v) road maintenance/road safety specialist, (vi) bridge engineer, (vii) poverty/social development specialist, (viii) resettlement specialist, and (ix) environmental specialist. This will be supported by domestic staff in the same areas. The consultants will be engaged using ADB's quality and cost-based selection procedures, and according to the ADB's Guidelines on the Use of Consultants.
Responsible ADB Officer Shakeel Ahmad Khan
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Transport and Communications Division, CWRD
Executing Agencies
AzerRoadService Open Joint-Stock CompanyMr. Javid Gurbanovinfo@piu-ahp.az72/4 U. Hajibeyov Street 370066 Baku
Timetable
Concept Clearance -
Fact Finding 13 Jun 2005 to 16 Jun 2005
MRM -
Approval 03 Nov 2005
Last Review Mission -
PDS Creation Date 03 Apr 2006
Last PDS Update 14 Feb 2008

TA 4684-AZE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
03 Nov 2005 17 May 2006 17 May 2006 30 Jun 2006 31 Dec 2007 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
1,130,000.00 0.00 0.00 0.00 0.00 0.00 1,130,000.00 03 Nov 2005 1,109,059.61

Safeguard Documents

See also: Safeguards

No documents found.

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.