Viet Nam: Multitranche Financing Facility Mong Duong 1Thermal Power Project

Sovereign Project | 39595-013 Status: Active

Summary

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Multitranche Financing Facility Mong Duong 1Thermal Power Project
Project Number 39595-013
Country Viet Nam
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
MFF Facility Concept 0013-VIE: Multitranche Financing Facility Mong Duong 1Thermal Power Project
Ordinary capital resources US$ 930.71 million
Loan: Multitranche Financing Facility Mong Duong 1Thermal Power Project
Korea Exim Bank US$ 510.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Private sector development
Sector / Subsector

Energy - Conventional energy generation

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location

Safeguard Categories

Environment A
Involuntary Resettlement A
Indigenous Peoples C

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Business Opportunities

Consulting Services Consulting services will be required for (i) reviewing technical designs; (ii) preparation of bid document for the engineering, procurement and construction (EPC) contract; (iii) supervision of site preparation; (iv) monitoring implementation of the resettlement plan; (v) implementation of the environmental management plan; (vi) socioeconomic impact assessment of the health situation; (vii) project performance monitoring; and (viii) supervision of the EPC contractor. The consultants will be selected and engaged by EVN in accordance with ADB's Guidelines on the Use of Consultants by Asian Development Bank and Its Borrowers. Services will be provided through consulting firms following international competition using the quality-and cost-based selection (QCBS) method. Individual experts may be recruited based on bio data submitted in response to specific terms of reference for the assignment. Two recruitments of consulting services will be undertaken for the Project. The first recruitment of consultants will be to assist in the preparation of bid documents for selection of the EPC contractor, negotiations and award of EPC contract; preparation of civil works bid documents, bidding, award of contract and supervision of civil works; assist in the implementation of resettlement plans; and implementation and supervision of environmental management plans. This recruitment will undertake during the implementation of the first loan. The second recruitment of consultants will be to assist EVN in the overall management of the Project, supervision of the EPC contract and civil works contracts. This recruitment will be undertaken prior to approval of the second loan. The total consulting inputs will be 820 person months comprising 556 person months of international consultancy services and 264 person months of national consultancy services.
Procurement Equipment and materials to be financed under the MFF will be procured in accordance with ADB's Procurement Guidelines. International competitive bidding (ICB) will be used for the engineering, procurement and construction (EPC) contract of the power plant and common facilities, for supply contracts estimated to cost the equivalent of or more than $1.0 million, and for civil works contracts valued at more than $3 million. National competitive bidding (NCB)/Limited international bidding will be used for supply contracts valued at less than $1 million. Civil works contracts estimated at less than $3.0 million will be procured following NCB procedures acceptable to ADB. Miscellaneous goods and civil works contracts valued at less than $100,000 will be procured using shopping procedures. Contract packages will be prepared to ensure maximum competition under ICB. Similar contractual arrangements and specifications will be applied to other subprojects.

Responsible Staff

Responsible ADB Officer Aruna Wanniachchi Kankanamalage
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Energy Division, SERD
Executing Agencies
Viet Nam Electricity
MR. TRAN VAN DUOC, Vice Pres., Thermal Power Proj.
69 Dinh Tien Hoang Street Hanoi, Viet Nam

Timetable

Concept Clearance 29 Sep 2005
Fact Finding 20 Jun 2006 to 03 Jul 2006
MRM 15 Aug 2006
Approval -
Last Review Mission -
Last PDS Update 04 Oct 2010

MFF Facility Concept 0013-VIE

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 1,099.60 Cumulative Contract Awards
ADB 930.71 - 0.00 0.00 %
Counterpart 168.89 Cumulative Disbursements
Cofinancing 0.00 - 0.00 0.00 %

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.