Economic development of rural areas through provision of reliable and environmentally clean energy. The TA will prepare a loan project for developing 5 small hydropower plants on existing irrigation canals and dams.

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Rural Renewable Energy Development
Project Number 39598-012
Country Uzbekistan
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 4709-UZB: Rural Renewable Energy Development
A.T.F. - Finnida Grant US$ 300,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Partnerships
Sector / Subsector Energy - Renewable energy generation - small hydro
Gender Equity and Mainstreaming No gender elements
Description Economic development of rural areas through provision of reliable and environmentally clean energy. The TA will prepare a loan project for developing 5 small hydropower plants on existing irrigation canals and dams.
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement B
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Business Opportunities
Consulting Services

The total input of international and domestic consultants will be 9 and 24 person-months, respectively.

The following international experts will be required:

(i) Hydropower development specialist (2 person-months)

(ii) Financial analyst and financial management specialist (2 person-months)

(iii) Economist (1.5 person months)

(iv) Environmental specialist (1 person month)

(v) Procurement specialist (1.5 person months)

(vi) Social/Poverty specialist (1 person month)

The domestic consultants will include (person-months are in parentheses):

(i) Domestic Team Leader (4); (ii) three hydropower experts-hydrologist, hydro-mechanical and electromechanical experts (3 each); (iii) a financial analyst (3); (iv) an economist (2); (v) an environmental specialist (2); (vi) cost estimator and procurement specialist (2); and (vii) social/poverty expert (2)

Responsible ADB Officer Nariman Mannapbekov
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Transport and Communications Division, CWRD
Executing Agencies
Ministry of Agriculture and Water ResourcesMr. Shavkat R. Khamraev, Deputy Minister, MAWR4, Navoi Street Tashkent, 100004 Republic of Uzbekistan
Timetable
Concept Clearance 28 Feb 2005
Fact Finding 11 Oct 2005 to 16 Oct 2005
MRM -
Approval 02 Dec 2005
Last Review Mission -
PDS Creation Date 03 Mar 2006
Last PDS Update 18 Jul 2007

TA 4709-UZB

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
02 Dec 2005 05 Feb 2006 05 Feb 2006 31 Jul 2006 30 Sep 2007 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
0.00 300,000.00 0.00 0.00 0.00 0.00 300,000.00 02 Dec 2005 298,348.73

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.