39928-014: SOUTH SUMATRA TO WEST JAVA PHASE II GAS PIPELINE PROJECT

Project Data Sheet (PDS): Details


Description

The Project, with a capacity of 460 Million Standard Cubic Feet Per Day (MMSCFD), is expected to transport natural gas from the Corridor Block Field operated by ConocoPhilips. The Project consists of 661 km of 36" /32" diameter pipeline from Grissik, South Sumatra to Rawa Maju, West Java.

Objectives and Scope

The Project, with a capacity of 460 Million Standard Cubic Feet Per Day (MMSCFD), is expected to transport natural gas from the Corridor Block Field operated by ConocoPhilips. The Project consists of 661 km of 36" /32" diameter pipeline from Grissik, South Sumatra to Rawa Maju, West Java.

Project Rationale and Linkage to Country/Regional Strategy

ADB's Country Strategy and Program for Indonesia (2006-2009) confirms policies of improvements in the environment (air quality), good governance and private sector development; these are all areas that PGN's corporate strategies and activities, including this Project, support.

Safeguard Categories

Environment: B
Involuntary Resettlement: A
Indigenous Peoples: C

Summary of Environmental and Social Aspects

The Project will not pass through environmentally sensitive areas and will not have significant impacts on wildlife and forests. During construction the Project will create transient disturbances to environmental quality over a short period only. During operation the Project will not pollute the environment. The onshore pipeline alignment was chosen because it minimizes the number of structures and persons affected. To date, all affected persons have chosen to accept cash compensation rather than replacement of land for land; therefore, no actual resettlement is required. Land acquisition is expected to be completed in mid-December 2006. The project area will not pass through any communities of indigenous peoples.

Stakeholder Participation and Consultation

PGN has carried out extensive consultation with the Project's stakeholders since the early stage of the AMDAL process in 1999 including public meetings held in regencies and sub-districts along the entire project area.

Project Sponsor

PT Perusahaan Gas Negara (PGN)



Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

Project Data Sheets (PDS)

Timetable

Concept Clearance
02 Sep 2005

Due Diligence Mission
20 Mar 2006 to 18 May 2006

Investment Committee Meeting
03 Jul 2006

Approval
10 Aug 2006