Pakistan: National Trade Corridor Highway Investment Program, Tranche 2

Sovereign Project | 40075-033

Summary

The Project 2 (E35: Hasanabdal-Havellian Expressway) is part of national trade corridor. It will connect existing M1 at Hasanabadal to Havellian, and will further extend to Abbotabad and Mansehra to North. The Project is almost parallel with existing N5 which is being urbanized in many sections. Due to high traffic volume and deteriorated road condition, E35 is becoming necessary in order to improve the sub regional connectivity within Pakistan, and to China, Afghanistan and other central Asian countries.

Latest Project Documents

Consulting Notices

See also: CMS

No notices are currently available for this project.

Procurement Notices

See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name National Trade Corridor Highway Investment Program, Tranche 2
Project Number 40075-033
Country Pakistan
Project Status Approved
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3121-PAK: National Trade Corridor Highway Investment Program, Tranche 2
Ordinary capital resources US$ 200.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change Governance and capacity development
Sector / Subsector Transport - Road transport (non-urban)
Gender Equity and Mainstreaming No gender elements
Description The Project 2 (E35: Hasanabdal-Havellian Expressway) is part of national trade corridor. It will connect existing M1 at Hasanabadal to Havellian, and will further extend to Abbotabad and Mansehra to North. The Project is almost parallel with existing N5 which is being urbanized in many sections. Due to high traffic volume and deteriorated road condition, E35 is becoming necessary in order to improve the sub regional connectivity within Pakistan, and to China, Afghanistan and other central Asian countries.
Project Rationale and Linkage to Country/Regional Strategy

The proposed Project 2 is part of the Central Asia Regional Economic Cooperation (CAREC). It will be PAK Investment Project 119 under corridor 5 of updated CAREC. It will improve regional connectivity through improving linkages with the neighboring countries and developing inter-provincial linkages to improve sub-regional connectivity. The proposed project 2 will construct a north-south access controlled expressway system to link the northern area of the country to existing expressway network and lead to better connectivity within Pakistan, to China and Afghanistan and other central Asian countries.

The Project 2 is part of the famous Karakoram Highway (KKH), which connects Kashgar of China to Abbottabad of Pakistan and extends to meet the Grand Trunk Road at Hassanabad, and it is also a part of ancient Silk Road. The Project is in line with the Country Partnership Strategy for 2009-2013 and is consistent with ADB's continuous supports on the NTCIP.

Impact Efficiency gain for road traffic operation along the National Trade Corridor
Project Outcome
Description of Outcome Improved regional network for movement of goods and people along E35 expressway
Progress Toward Outcome 2 Civil works contracts have been signed for the construction of 39 km road.
Implementation Progress
Description of Project Outputs

Expressway connecting Hassanabdal and Sarai Saleh constructed and operational

NHA's institutional capacity in social safeguards improved

Status of Implementation Progress (Outputs, Activities, and Issues)

2 Civil works contracts have been signed for the construction of 39 km road, and contractors have been mobilized.

Social safeguards implementation is complied with the ADB's Safeguards Policy Statement.

Recruitment of Social Safeguards Management Consultant (SSMC) has been completed.

Geographical Location Punjab/Khyber Pakhtunkhwa
Safeguard Categories
Environment A
Involuntary Resettlement A
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects

Tranche 2 is a new alignment through areas that are sparsely populated, therefore an Environment Category A project; there are no protected areas in the vicinity with no significant or thick vegetation.

The environmental impacts identified are largely concentrated in the construction phase, due to the sheer scale of the project, appropriate and specific mitigation measures.

Involuntary Resettlement Project 2 is classified category A for the purposes of social safeguards including involuntary resettlement. About 9,000 households will be affected by the project , and the impacts vary from household to household, and primarily involve the acquisition of portions of agricultural land. Some residential lands will be affected, however all households will be able to relocate either on remaining land, or land within close proximity to the affected lands. The LARF has been updated, endorsed by NHA, cleared by ADB and has been disclosed/uploaded to the ADB and NHA websites. Three LARPs have been prepared in accordance with the approved updated LARF, the Land Acquisition Act of 1894 and ADB SPS, 2009. The resettlement planning was informed by a detailed independent land assessment study to ensure prices proposed for compensation approximate full replacement cost as required by SPS 2009.
Indigenous Peoples There will no indigenous people in the project affected area.
Stakeholder Communication, Participation, and Consultation
During Project Design The consultation process will continue to share the latest development interventions in the project and take responses from the APs.
During Project Implementation The consultation process will continue during project implementation.
Business Opportunities
Consulting Services All consulting services financed under Tranche 2 will be procured in accordance with the Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers (2010, as amended from time to time).
Procurement Procurement of all civil works, equipment and goods will be undertaken in accordance with ADB's Procurement Guidelines (2010, as amended from time to time).
Responsible ADB Officer Pawan Karki
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Pakistan Resident Mission
Executing Agencies
National Highway AuthorityRoom No. 110, 1st Floor,
NC Building, Sector G-9/1
Islamabad, Pakistan
Timetable
Concept Clearance 28 Jul 2007
Fact Finding -
MRM 25 Nov 2013
Approval 01 Apr 2014
Last Review Mission -
PDS Creation Date 31 Jul 2009
Last PDS Update 25 Mar 2015

Loan

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 0.00 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 - 0.00 0.00 %

Loan 3121-PAK

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
01 Apr 2014 17 Sep 2014 11 Nov 2014 31 Dec 2017 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 238.00 Cumulative Contract Awards
ADB 200.00 01 Apr 2014 129.66 0.00 65%
Counterpart 38.00 Cumulative Disbursements
Cofinancing 0.00 01 Apr 2014 16.24 0.00 8%

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.