Nepal: Strengthening Land Administration Services

Sovereign Project | 40544-012

Summary

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Strengthening Land Administration Services
Project Number 40544-012
Country Nepal
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 4969-NEP: Strengthening Land Administration Services
Technical Assistance Special Fund US$ 350,000.00
Strategic Agendas
Drivers of Change
Sector / Subsector For classification - For classification
Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Govinda P. Gewali
Responsible ADB Department South Asia Department
Responsible ADB Division Nepal Resident Mission
Executing Agencies
Ministry of Land Reform and ManagementSinga Durbar
Kathmandu, Nepal
Timetable
Concept Clearance 16 May 2007
Fact Finding 11 Jun 2007 to 26 Jun 2007
MRM -
Approval 26 Sep 2007
Last Review Mission -
PDS Creation Date 05 Jun 2007
Last PDS Update 20 Jan 2009

TA 4969-NEP

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
26 Sep 2007 04 Nov 2007 04 Nov 2007 31 Dec 2008 - -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
350,000.00 0.00 50,000.00 0.00 0.00 0.00 400,000.00 26 Sep 2007 262,091.18
Title Document Type Document Date
Strengthening Land Administration Services TA Completion Reports Jun 2009
Strengthening Land Administration Services Technical Assistance Reports Sep 2007

Safeguard Documents

See also: Safeguards

No documents found.

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.