Solomon Islands: Emergency Assistance Project

Sovereign Project | 41105-012

Summary

The Project will rehabilitate essential infrastructure that was damaged by the earthquake and tsunami in Choiseul and Western provinces, including (i) approximately 35 km of rural and town roads, along with about 19 bridges and 35 culverts, (ii) about 4 wharves and 1 jetty, and (iii) the Gizo town water supply and sanitation system. These estimates are subject to detailed damage assessments and cost estimates.

Latest Project Documents

Project Results

 

51

kilometers of roads built or upgraded

 

3,560

average daily vehicle-kilometers using roads built or upgraded in the first full year of operation


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Emergency Assistance Project
Project Number 41105-012
Country Solomon Islands
Project Status Closed
Project Type / Modality of Assistance Grant
Technical Assistance
Source of Funding / Amount
Grant 0078-SOL: Emergency Assistance Project
Asian Development Fund US$ 4.95 million
TA 4944-SOL: Strengthening Disaster Recovery Planning and Coordination (piggybacked to Grant-Emergency Assistance Project)
Technical Assistance Special Fund US$ 800,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change
Sector / Subsector Agriculture, natural resources and rural development - Rural water supply services
Transport - Water transport (non-urban)
Gender Equity and Mainstreaming
Description The Project will rehabilitate essential infrastructure that was damaged by the earthquake and tsunami in Choiseul and Western provinces, including (i) approximately 35 km of rural and town roads, along with about 19 bridges and 35 culverts, (ii) about 4 wharves and 1 jetty, and (iii) the Gizo town water supply and sanitation system. These estimates are subject to detailed damage assessments and cost estimates.
Project Rationale and Linkage to Country/Regional Strategy ADB's country strategy and program update identifies the development of transportation infrastructure and services as one of the 2 main areas for ADB assistance. Through other projects and TA, ADB is also addressing cross-sectoral infrastructure issues and technical capacity building. Existing and proposed projects will be prioritized and sequenced as appropriate to respond to emergency, complement activities, and maximize benefits.
Impact Normal economic and social activities and accessibility resumed in affected areas
Project Outcome
Description of Outcome

Access to markets for agricultural and fisheries products, social services, and tourism areas via land transport restored

Access to markets for agricultural and fisheries products, social services, and tourism areas via sea

transport restored

Risks to public health caused by unreliable and unsafe town water system reduced

Effective disaster recovery coordination Reduced vulnerability of infrastructure to hazards

Progress Toward Outcome The Project is complete and assessed as successful. The Project Completion Report is under preparation and will be circulated by 2011.
Implementation Progress
Description of Project Outputs

Provincial and secondary roads rehabilitated to restore full accessibility

Water landings rehabilitated to restore access to interisland shipping

Gizo town water system restored to normal functionality

Maintenance on rehabilitated infrastructure conducted through community participation and labor based methods

Disaster recovery processes prepared

Status of Implementation Progress (Outputs, Activities, and Issues)

Under evaluation.

20 replacement bridges and 2 existing bridges rehabilitated.

46 new watercrossings.

4 new wharves, 2 foot bridges and 1 jetty have been reconstructed.

Under evaluation.

7 community contracts underway.

Under evaluation.

Geographical Location Western and Choiseul Provinces
Safeguard Categories
Environment B
Involuntary Resettlement C
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Business Opportunities
Consulting Services International and domestic consulting services will be required for (i) engineering design and preparation of bidding documents; (ii) construction supervision; (iii) project management; (iv) socioeconomic monitoring and evaluation; and (v) financial management. The Project will fund 8 person-months of international consulting services and 48 person-months of national consulting services. Consulting services will be engaged in accordance with ADB's Guidelines on the Use of Consultants.
Procurement Procurement under the Project, including for ADB and Government-financed packages, will follow ADB's Procurement Guidelines, with the flexible interpretation permitted for emergency assistance provided in accordance with ADB Disaster and Emergency Assistance Policy (2004) to ensure maximum expediency in implementing the recovery program. Major civil works will be procured using international and national competitive bidding procedures. Minor civil works will be procured using national competitive bidding, shopping, and community procurement procedures.
Responsible ADB Officer David Ling
Responsible ADB Department Pacific Department
Responsible ADB Division Pacific Liaison and Coordination Office in Sydney, Australia
Executing Agencies
Ministry of Infrastructure Development Mr. John Taarupsmid@pmc.gov.sbMinistry of Infrastructure Development
Timetable
Concept Clearance 26 Apr 2007
Fact Finding 14 May 2007 to 25 May 2007
MRM 11 Jun 2007
Approval 27 Jun 2007
Last Review Mission -
PDS Creation Date 21 May 2007
Last PDS Update 05 Sep 2011

Grant 0078-SOL

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
27 Jun 2007 11 Sep 2007 01 Oct 2007 31 Dec 2009 30 Jun 2011 06 Aug 2013
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 5.75 Cumulative Contract Awards
ADB 4.95 27 Jun 2007 NaN 7.78 97%
Counterpart 0.80 Cumulative Disbursements
Cofinancing 0.00 27 Jun 2007 NaN 7.78 97%

TA 4944-SOL

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
27 Jun 2007 18 Jul 2007 18 Jul 2007 31 Dec 2009 30 May 2010 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
800,000.00 0.00 150,000.00 0.00 0.00 0.00 950,000.00 27 Jun 2007 743,018.18
Title Document Type Document Date
Emergency Assistance Project Project/Program Completion Reports Oct 2011
Strengthening Disaster Recovery Planning and Coordination TA Completion Reports Sep 2010
Emergency Assistance Project Grant Change in Scope, Amount, and Implementation Arrangements Jul 2009
Amendment to the Grant Agreement for Emergency Assistance Project between Solomon Islands and Asian Development Bank dated 7 July 2008 Grant Agreement Jul 2008
Rehabilitation and Reconstruction Program for Disaster-affected Areas Documents Produced Under Grant/Loans/TA Nov 2007
Grant Agreement for Emergency Assistance Project between Solomon Islands and Asian Development Bank dated 11 September 2007 Grant Agreement Sep 2007
Emergency Assistance Project Design and Monitoring Frameworks Jun 2007
Emergency Assistance Project Initial Poverty and Social Analysis Jun 2007
Proposed Asian Development Fund Grant Solomon Islands: Emergency Assistance Project Procurement Plans Jun 2007
Emergency Assistance Project Reports and Recommendations of the President Jun 2007

Safeguard Documents

See also: Safeguards

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.