41614-033: MFF - Assam Power Sector Enhancement Investment Program - Tranche 2 | Asian Development Bank

India: MFF - Assam Power Sector Enhancement Investment Program - Tranche 2

Sovereign (Public) Project | 41614-033 Status: Active

ADB is helping India's Assam state expand its electricity transmission and distribution capacity, and increase access in remote communities. The second tranche of the multitranche facility will finance construction of 220 kV and 132 kV power transmission lines, two 220/132 kV substations, and six 132/33 kV substations. It also includes extension and augmentation of 11 substations.

 
Project Name MFF - Assam Power Sector Enhancement Investment Program - Tranche 2
Project Number 41614-033
Country India
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2677-IND: MFF - Assam Power Sector Enhancement Investment Program - Tranche 2
Ordinary capital resources US$ 66.90 million
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Private sector development
Sector / Subsector

Energy / Electricity transmission and distribution

Gender Equity and Mainstreaming
Description

The Transmission and Distribution Sector Investment Program (the Investment Program) includes the following components and costs: (i) access to power (transmission) and energy efficiency enhancement (transmission loss reduction), $561.6 million (73.5%); (ii) access to power (distribution) and energy efficiency enhancement (distribution loss reduction) and distribution franchising, $150 million (19.6%); (iii) distributed decentralized generation, $50 million (6.5%). The Investment Program includes $3.4 million for a capacity development program to meet the increasing management capacity requirements including technical assistance (TA). The physical investments will address current unserved energy demand and provide additional capacity to meet forecast demand growth.

The MFF is expected to be utilized in three tranches. Tranche 1 will finance a set of projects for (i) transmission of power for capacity addition in transmission lines of 220 kilovolts (kV) (180 kilometers [km]) and 132 kV (82 km), and capacity addition of transformation through construction of 1 new 220/132 kV substation and 5 new 132/33 kV substations; and (ii) extension and augmentation of 2 existing substations. The tranche will include capacity development.

Tranche 2 is expected to finance a set of projects for

(i) transmission of power for capacity addition in transmission lines of 220 kV (185 km) and 132 kV (160 km), and capacity addition of transformation through construction of 2 new 220/132 kV substations and 6 new 132/33 kV substations; and (ii) extension and augmentation of 11 substations.

Tranche 3 is expected to finance a set of projects for (i) access to power in distribution, (ii) energy efficiency enhancement: distribution loss reduction, and (iii) distribution franchising. This component includes construction of new distribution substations and lines to enable the rollout of relevant franchising models.

Project Rationale and Linkage to Country/Regional Strategy

The Investment Program will (i) strengthen power transmission capacity to deliver reliable and affordable electricity, (ii) improve access to electricity in distribution through grid electricity and off-grid renewable and conventional energy-based electricity, (iii) enhance efficiency and quality of power supply, (iv) ensure financial health of the power sector through continued reform, and (v) promote private sector participation. The Investment Program includes a capacity development program component to meet the increasing management capacity requirements.

The MFF is particularly well suited for the Investment Program because (i) its aim is to support GOA's long-term objectives, as stated in the T&D road map; (ii) the performance of ongoing projects under the MFF can guide the provision of subsequent loans, thereby offering proper incentives for implementation; and (iii) the MFF can offer the flexibility required for the Investment Program to support participation of the utilities at different stages of readiness.

Impact A sustainable state power sector with increased transmission and distribution capacity to support inclusive economic growth
Project Outcome
Description of Outcome Enhanced quality and expanded service delivery of electricity in Assam through improved technical, commercial, and financial performance and capability of the power sector utilities
Progress Toward Outcome Loan 2677. All works under this loans are complete except: (i) Kamakhya and Sonapur substations, which are at an advanced stages of construction; and (ii) construction of 220 kV D/C LILO of Samaguri-Sarusajai line at Sonapur and 132 kV D/C LILO of Chandrapur-Kahilipara line at Sonapur. The project is delayed due to ROW problems, which are being monitoring closely for early resolution. ADB sought GoA intervention in resolving the ROW issues. EA and GoA assured the ADB that all out efforts are being made to resolve the ROW issues and expect the remaining works to be completed by the current loan closing date of 31 March 2018.
Implementation Progress
Description of Project Outputs

Access to power: Constructed new transmission lines and substations, and other transmission system improvement activities

Energy efficiency enhancement : Extended and augmented transmission substations, refurbished existing substations, reactive compensation, introduction of new technologies to reduce loss

Status of Implementation Progress (Outputs, Activities, and Issues) Overall implementation of the Loan 2677 is satisfactory and is rated "on track. All procurement packages have been contracted and disbursement of funds is ongoing. The Loan closing date is 31 March 2018 and substantial Physical progress has been achieved, and the loan expected to close within the existing closing date, without any further extension.
Geographical Location Barpeta, Cachar, Dhuburi, Dibrugarh, Goalpara, Golaghat, Hailakandi, Jorhat, Kamrup, Karimganj, Kokrajhar, Lakhimpur, Marigaon, Nagaon, Nalbari, Sibsagar, Sonitpur, Tinsukia
Safeguard Categories
Environment B
Involuntary Resettlement B
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects Being Complied.
Involuntary Resettlement Being Complied.
Indigenous Peoples Being Complied.
Stakeholder Communication, Participation, and Consultation
During Project Design Complied.
During Project Implementation Consultations will continue during the entire project cycle according to a stakeholder participation plan.
Business Opportunities
Consulting Services Consulting services will be required to provide ASEB and the implementing agencies with assistance for project implementation, including design, construction supervision, and management of the projects under each loan of the MFF; as well as ASEB's processing work and PFR preparation for future loans. Consulting services will be provided for evaluation, monitoring, and reporting purposes. Consultants will be selected and engaged in accordance with ADB's Guidelines on the Use of Consultants (2007, as amended from time to time) in accordance with the procurement plan.
Procurement Goods, equipment, and civil works to be financed under the MFF will be procured in accordance with ADB Procurement Guidelines (2007, as amended from time to time) and the related procurement plan.
Responsible ADB Officer Banerjee, Jyotirmoy
Responsible ADB Department South Asia Department
Responsible ADB Division India Resident Mission
Executing Agencies
Assam Electricity Grid Corporation Ltd
[email protected]
Assam State Electricity Board ,
4th Floor Bijuleen Bhawan Paltan Bazar,
Guwahati-781001
Timetable
Concept Clearance -
Fact Finding -
MRM -
Approval 05 Oct 2010
Last Review Mission -
PDS Creation Date 30 Jul 2010
Last PDS Update 27 Sep 2017

Loan 2677-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
05 Oct 2010 17 Jan 2011 01 Apr 2011 30 Nov 2013 31 Mar 2018 -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 66.90 Cumulative Contract Awards
ADB 66.90 05 Oct 2010 65.37 0.00 98%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 05 Oct 2010 60.52 0.00 90%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Assam Power Sector Enhancement Investment Program - Tranche 2: Environmental Monitoring Report (January-June 2017) Environmental and Social Monitoring Reports Dec 2017
Assam Power Sector Enhancement Investment Program - Tranches 1 and 2: Initial Environmental Examination Initial Environmental Examination Oct 2017
MFF - Assam Power Sector Enhancement Investment Program - Tranche 2: 132kV S/C of Agia-Matia Line Resettlement Plan Resettlement Plans Oct 2017
MFF - Assam Power Sector Enhancement Investment Program - Tranche 2: 132kV Hailakandi LILO Resettlement Plan Resettlement Plans Oct 2017
Assam Power Sector Enhancement Investment Program - Tranche 2: 132 kV SC LILO of Jorhat-Bokakhat Line Resettlement Plan Resettlement Plans Sep 2017
Assam Power Sector Enhancement Investment Program - Tranche 2: 220 kV Sonabil LILO Resettlement Plan Resettlement Planning Documents Sep 2017
MFF - Assam Power Sector Enhancement Investment Program - Tranche 2: 132kV Bordubi LILO Resettlement Plan Resettlement Plans Sep 2017
Assam Power Sector Enhancement Investment Program - Tranche 2: Depota-Gohpur Line Updated Resettlement Plan Resettlement Plans Jul 2017
Assam Power Sector Enhancement Investment Program - Tranche 2: Environmental Monitoring Report (January-June 2016) Environmental Monitoring Reports May 2017
Assam Power Sector Enhancement Investment Program - Tranche 2: Environmental Monitoring Report (July-December 2016) Environmental Monitoring Reports May 2017
Assam Power Sector Enhancement Investment Program - Tranche 2: Social Monitoring Report (July-December 2016) Social Monitoring Reports Mar 2017
Assam Power Sector Enhancement Investment Program - Tranche 2: Environmental Monitoring Report (July-December 2015) Environmental Monitoring Reports Mar 2017
Assam Power Sector Enhancement Investment Program - Tranche 2: Social Monitoring Report (January-June 2016) Social Monitoring Reports Dec 2016
Assam Power Sector Enhancement Investment Program - Tranche 2: Social Monitoring Report (January-June 2015) Social Monitoring Reports Oct 2016
Assam Power Sector Enhancement Investment Program - Tranche 2: Social Monitoring Report (July-December 2015) Social Monitoring Reports Oct 2016
Assam Power Sector Enhancement Investment Program - Tranche 2: Environmental Monitoring Report (January-June 2015) Environmental Monitoring Reports May 2016
Assam Power Sector Enhancement Investment Program - Tranche 2: 220 kV Mariani-Namrup Transmission Line Initial Environmental Examination (Addendum) Initial Environmental Examination May 2016
Assam Power Sector Enhancement Investment Program - Tranche 2: Social Monitoring Report (July-December 2014) Social Monitoring Reports Jan 2015
Assam Power Sector Enhancement Investment Program - Tranche 2: Environmental Monitoring Report (July-December 2014) Environmental Monitoring Reports Jan 2015
Assam Power Sector Enhancement Investment Program - Tranche 2: Environmental Monitoring Report (January-June 2014) Environmental Monitoring Reports Jul 2014
Assam Power Sector Enhancement Investment Program - Tranche 2: Social Monitoring Report (January-June 2014) Social Monitoring Reports Jul 2014
Assam Power Sector Enhancement Investment Program - Tranche 2: Environmental Monitoring Report (January-June 2013) Environmental Monitoring Reports Apr 2014
Assam Power Sector Enhancement Investment Program - Tranche 2: Social Monitoring Report (January-June 2013) Social Monitoring Reports Apr 2014
Assam Power Sector Enhancement Investment Program - Tranche 2: Environmental Monitoring Report (July-December 2013) Environmental Monitoring Reports Apr 2014
Assam Power Sector Enhancement Investment Program - Tranche 2: Social Monitoring Report (July-December 2013) Social Monitoring Reports Apr 2014
Assam Power Sector Enhancement Investment Program - Tranche 2 Initial Environmental Examination Aug 2010
Assam Power Sector Enhancement Investment Program Resettlement Plans May 2010

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.