India: Himachal Pradesh Clean Energy Development Investment Program - Tranche 4

Sovereign Project | 41627-053 Status: Active

Summary

ADB is helping India construct several run-of-river hydropower plants in Himachal Pradesh. Tranche 4 will fund the turnkey civil works contract for the 450-megawatt Shongtong Karcham Hydroelectric Project located on the Sutlej River in Kinnaur district.  It also includes a data center and disaster recovery center, and personnel training at state-owned Himachal Pradesh Power Corporation Ltd.

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Himachal Pradesh Clean Energy Development Investment Program - Tranche 4
Project Number 41627-053
Country India
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2914-IND: Himachal Pradesh Clean Energy Development Investment Program - Tranche 4
Ordinary capital resources US$ 257.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change
Sector / Subsector

Energy - Large hydropower generation

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome --
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues) HPPCL has achieved an overall implementation progress of about 40%.
Geographical Location

Summary of Environmental and Social Aspects

Environmental Aspects For Tranche 4, the Environmental Impact Assessment (EIA) and Environmental Management Plan (EMP) were disclosed on ADB's website since 28 September 2010. An updated version was posted on 19 December 2011. Consultations were carried out during EIA preparation, including holding meetings and individual interviews involving stakeholders, particularly project affected persons. The environmental assessment process included determining baseline levels for the existing status of physical-chemical, ecological and socio-economic aspects of the environment, followed by identification of potential impacts due to construction and operation activities, and prediction of significant impacts using appropriate simulation models. This was followed by the preparation of an Environmental Management Plan (EMP) outlining measures to minimize adverse impacts during construction and operation phases, including a catchment area treatment plan, fisheries management plan, and muck management plan, including an estimation of cost for implementing the plan and guidelines for monitoring its progress. Expected impacts include impacts on the water, air, noise levels, land and biological environments and have been separated into construction phase impacts and operating phase impacts. Impacts on the water environment stem from sewage from labor camps and effluent from crushers and muck disposal. Operating phase impacts include reservoir water quality, sediments and river flows within the project area. Air impacts predominantly occur during construction and include emissions from construction equipment and increased vehicular movement, and dust emissions from blasting operations and muck disposal. Noise impacts are from construction machinery and vehicles and to a limited degree due to their underground nature, from the blasting operations. Land impacts stem from soil erosion, muck disposal and quarrying operations. Biological impacts on flora and fauna have also been evaluated, as well as socioeconomic impacts from the influx of the labor force.
Involuntary Resettlement Total private land acquisition is 6.3 hectares which will have 141 affected families consisting of 666 affected persons. As an integral part of the safeguards planning, affected persons and local communities were consulted during tranche 4 resettlement plan preparation. The 141 affected families were consulted as part of the census survey in the project area through a household questionnaire survey, and focused group discussions were also conducted in the affected villages. Consultation will continue through the project cycle. A total of 6 residential structures are being affected, of which 2 are purely residential and 4 include small shops. Loss of these structures will not lead to physical displacement since these structures are built on agricultural land and are not used as primary homes. In addition to the structures, a total of 154 trees will be affected which out of which 51 are fruit trees. None of the affected families are to be rendered landless as they are only partially losing their land. Similarly, no squatters or non-titleholders are affected. The resettlement cost estimate for this subproject includes eligible compensation, resettlement assistance and support cost for resettlement plan implementation. All activities related to the land acquisition and resettlement have been planned to ensure that compensation is paid prior to commencement of civil works. Public consultation, monitoring and grievance redress will be undertaken intermittently throughout the project duration. "The resettlement plan for this project is being updated to reflect the final assessment of involuntary resettlement impacts.
Indigenous Peoples As the project has been classified as Indigenous Peoples category C, no separate Indigenous Peoples Plan was prepared. However, the resettlement plan contains specific measures through additional entitlements accorded to scheduled tribes who are considered as vulnerable groups, should any be affected in the future. This is not expected.
Stakeholder Communication, Participation, and Consultation
During Project Design

Public participation and community consultation has been taken up as an integral part of social and environmental assessment process of the project. Consultation was used as a tool to inform and educate stakeholders about the project. The participatory process helped in involving the local people in project activities. Initial Public consultation has been carried out in the subproject areas with the objectives of minimizing probable adverse impacts of the project through alternate design solutions and to achieve speedy implementation of the project through bringing in awareness among the community on the benefits of the project. The consultation process has been going on since 2009 during project design, environment impact assessment study, and fresh rounds of consultations were also conducted during the social impact assessment, land acquisition and resettlement study.

Attempts have been taken to involve the concerned government official in the project preparation. A holistic approach was adopted during the design stage in order to gather the information about the project area and about the other developmental activities which are going on parallel to the proposed plan. These officials represent from local, district and state level.

During Project Implementation Consultations will continue during the entire project cycle according to the stakeholder participation plan.

Business Opportunities

Consulting Services No consulting services are funded by this loan tranche (they were funded via the tranche 1 loan)
Procurement Procurement will be in accordance with ADB's Procurement Guidelines (2010, as amended from time to time). International competitive bidding (ICB) will be used to procure the civil works construction contract. HPPCL has utilized advanced contracting for this contract. The electro-mechanical equipment contract will be funded via parallel cofinancing by KfW. A procurement plan is presented in Annex 4 of the PFR. As this is the 4th tranch in this MFF, the EA is now highly experienced in ADB procurement policies and procedures.

Responsible Staff

Responsible ADB Officer Vallabha Karbar
Responsible ADB Department South Asia Department
Responsible ADB Division India Resident Mission
Executing Agencies
Multipurpose Projects & Power Dept of Govt of HP
HP Secretariat
Shimla-171 002
Himachal Pradesh, India

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
Last PDS Update 23 Feb 2016

Loan 2914-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
02 Oct 2012 19 Nov 2012 17 Jan 2013 30 Jun 2018 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 492.00 Cumulative Contract Awards
ADB 257.00 02 Oct 2012 159.07 0.00 62%
Counterpart 235.00 Cumulative Disbursements
Cofinancing 0.00 02 Oct 2012 47.16 0.00 18%

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
HPCEDIP - Tranche 4: Shongtong-Karchham Hydroelectric Project (450 MW) Environmental Monitoring Report (January-March 2015) Environmental Monitoring Reports Sep 2015
Himachal Pradesh Clean Energy Development Investment Program – Tranche 4: Semi-Annual Environmental Monitoring Report (July-December 2014) Environmental Monitoring Reports Mar 2015
Himachal Pradesh Clean Energy Development Investment Program – Tranche 4: Semi-Annual Environmental Monitoring Report (July-December 2013) Environmental Monitoring Reports Dec 2013
Himachal Pradesh Clean Energy Development Investment Program – Tranche 4: Semi-Annual Environmental Monitoring Report (November 2012-June 2013) Environmental Monitoring Reports Jun 2013
Himachal Pradesh Clean Energy Development Investment Program: Shongtong Karchham Sub Project (Tranche-IV) Resettlement Plans Mar 2012
Himachal Pradesh Clean Energy Development Investment Program - Tranche 4: Shongtong-Karchham Hydroelectric Project (450 MW) - Full Report Environmental Impact Assessments Jun 2011
Himachal Pradesh Clean Energy Development Investment Program - Tranche 4: Shongtong-Karchham Hydroelectric Project (450 MW) Environmental Monitoring Reports Jun 2011
Environmental Management Plan Report: Shongtong-Karcham Hydroelectric Project (402MW) (Tranche 4) (September 2010) Environmental Management Plans Sep 2010
Himachal Pradesh Clean Energy Development Investment Program - Tranche 4: Shongtong-Karcham Hydroelectric Project (402 MW) - Full Report Environmental Impact Assessments Sep 2010

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.