China, People's Republic of: Zhangbei Wind Power Project

Nonsovereign Project | 41926-014 Status: Approved


Zhangbei Wind Power Project

Latest Project Documents

Consulting Notices

See also: CMS

No notices are currently available for this project.

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Zhangbei Wind Power Project
Project Number 41926-014
Country China, People's Republic of
Approval Number 7297
Type or Modality of Assistance
7297 Loan US$ 34.30 million Approved
Strategic Agendas Inclusive economic growth
Drivers of Change Private sector development
Sector / Subsector

Energy - Renewable energy generation - wind

Gender Equity and Mainstreaming
Responsible ADB Department East Asia Department
Responsible ADB Division Energy Division, EARD
Responsible ADB Officer ADB Disclosure
Project Sponsor(s)
Description Zhangbei Wind Power Project
Objectives and Scope
Linkage to Country/Regional Strategy The Asian Development Bank (ADB) promotes inclusive, efficient, equitable, and sustainable economic growth to eliminate poverty across the Asia and Pacific region. In its long-term strategic framework 2008 2020 (Strategy 2020), ADB identified energy as one of five core operational areas and achieving environmental sustainability as one of three strategic development priorities. ADB s operational focus for the energy sector hinges on addressing energy security and climate change by improving energy efficiency and enlarging the use of indigenous clean and renewable energy. ADB s country partnership strategy for the PRC (2008 2010) concentrates on achieving balanced and sustainable growth with more efficient uses of resources and more stringent protection of the environment.
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
Timetable for assistance design, processing and implementation
Concept Clearance -
Due Diligence 21 Nov 2008
Credit Committee Meeting -
Approval 10 Mar 2009
PDS Creation Date 05 Feb 2009
Last PDS Update 05 Feb 2009
Title Document Type Document Date
Zhangbei Wind Power Project Reports and Recommendations of the President Feb 2009

Safeguard Documents

See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Zhangbei Wind Power Project Summary Initial Environmental Examination Feb 2009

Evaluation Documents

See also: Independent Evaluation

None currently available.

Related Publications

None currently available.

The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.