Viet Nam: Power Transmission Investment Program (MFF)

Sovereign Project | 42039-033 Status: Active

Summary

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents

None currently available.


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Power Transmission Investment Program (MFF)
Project Number 42039-033
Country Viet Nam
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
MFF Facility Concept 0066-VIE: Power Transmission Investment Program (MFF)
Ordinary capital resources US$ 730.00 million
MFF Facility Concept: Power Transmission Investment Program (MFF)
Agence Francaise de Developpement US$ 100.00 million
MFF Facility Concept: Power Transmission Investment Program (MFF)
KfW Bankengruppe US$ 71.01 million
Strategic Agendas Inclusive economic growth
Drivers of Change
Sector / Subsector

Energy - Electricity transmission and distribution

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location

Summary of Environmental and Social Aspects

Environmental Aspects At tranche level
Involuntary Resettlement At tranche level
Indigenous Peoples At tranche level
Stakeholder Communication, Participation, and Consultation
During Project Design Stakeholder participation and consultations were undertaken with the National Power Transmission Corporation, various government ministries at national, provincial and district level. The resettlement and ethnic minority development framework and environmental review framework establishes detailed requirements for consultation with affected people and disclosure during the preparation and implementation of future financing tranches.
During Project Implementation

Business Opportunities

Consulting Services Consultant services financed from ADB's loan proceeds will be recruited according to ADB's Guidelines on the Use of Consultants (2010, as amended from time to time).
Procurement International competitive bidding procedures (ICB) will be used for civil works contracts estimated to cost $5.0 million or more, and supply contracts valued at $500,000 or more. National competitive bidding procedures (NCB) will be used for civil work contracts valued less than $5.0 million, and for supply contracts valued less than $500,000 but more than $100,000. Qualification and eligibility requirements will be specified in the procurement plan and bidding documents. International shopping will be authorized for procurement of goods and works with a contract price equivalent of $100,000 or less. Secondary equipment for expansion of existing 500 kV and 220 kV substations under operation using computerized control system may be procured on the basis of international shopping or through direct contracting, as appropriate.

Responsible Staff

Responsible ADB Officer Daniela Schmidt
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Energy Division, SERD
Executing Agencies
National Power Transmission Corporation
18 Tran Nguyen Han Street,
Hoan Kiem District, Hanoi-Vietnam
Ha Noi

Timetable

Concept Clearance 03 Dec 2010
Fact Finding 09 Aug 2011 to 19 Aug 2011
MRM 20 Sep 2011
Approval -
Last Review Mission -
Last PDS Update 16 Sep 2015

MFF Facility Concept 0066-VIE

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 920.00 Cumulative Contract Awards
ADB 730.00 - 0.00 0.00 %
Counterpart 190.00 Cumulative Disbursements
Cofinancing 0.00 - 0.00 0.00 %
Title Document Type Document Date
Framework Financing Agreement for the Multitranche Financing Facility to the Socialist Republic of Viet Nam for the Power Transmission Investment Program Framework Financing Agreement Jan 2012
Power Transmission Investment Program Facility Administration Manual Nov 2011
Power Transmission Investment Program Reports and Recommendations of the President Nov 2011
Power Transmission Investment Program Summary Poverty Reduction and Social Strategies Nov 2011
Power Transmission Investment Program (MFF) Design and Monitoring Frameworks Sep 2011

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Power Transmission Investment Program (MFF): Initial Environmental Examination for 500 kv/220 kV Pho Noi Substation and Connection Lines Initial Environmental Examination Nov 2011
Power Transmission Investment Program (MFF): Environmental Assessment and Review Framework (as of Board approval) Environmental Assessment and Review Framework Nov 2011
Power Transmission Investment Program (MFF): Initial Environmental Examinations (as of Board approval) Initial Environmental Examination Nov 2011
Power Transmission Investment Program (MFF): Initial Environmental Examination for 220 kV Song May-Uyen Hung Transmission Line Initial Environmental Examination Nov 2011
Power Transmission Investment Program (MFF): Resettlement and Ethnic Minority Development Framework (as of Board aproval) Combined Resettlement Framework and Indigenous Peoples Planning Frameworks Nov 2011
Power Transmission Investment Program (MFF): Initial Environmental Examination for 220 kV Phu My 2 Industrial Zones and Connection Lines Initial Environmental Examination Nov 2011
Power Transmission Investment Program (MFF): Resettlement Plans (as of Board approval) Resettlement Plans Nov 2011
Power Transmission Investment Program (MFF): Initial Environmental Examination for 500 kV/220 kV Bac Ninh2-Pho Noi Transmission Line Initial Environmental Examination Nov 2011
Power Transmission Investment Program (MFF) Combined Resettlement Framework and Indigenous Peoples Planning Frameworks Nov 2011
Power Transmission Investment Program (MFF): Resettlement Plan for Bac Ninh 2 - Pho Noi 500/220kV T/L Project Resettlement Plans Oct 2011
Power Transmission Investment Program (MFF): Resettlement Plan for 220kV Phu My 2 Industrial Zone Sub-station and Connections Subproject Resettlement Plans Oct 2011
Power Transmission Investment Program (MFF): Resettlement Plan for Song May-Uyen Hung Transmission Line Subproject Resettlement Plans Oct 2011
Power Transmission Investment Program (MFF): Resettlement Plan for 500kV Pho Noi Substation and Connections Resettlement Plans Oct 2011
Power Transmission Investment Program (MFF) Environmental Assessment and Review Framework Sep 2011

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.