Viet Nam: Power Transmission Investment Program - Tranche 2

Sovereign Project | 42039-035

Summary

The investment program will contribute to meeting electricity demand growth of industrial, commercial, and residential consumers in an economically and environmentally sustainable manner. The outcome of the investment program is enhanced capacity of the transmission network to balance power load. The investment program also supports partial implementation of National Power Sector Development Master Plan VII (PDMP VII) to meet growing electricity demand of industrial, commercial and residential consumers throughout Viet Nam, and improve the operational effectiveness and efficiency of the National Power Transmission Corporation (NPT) the entity responsible for financing, managing, and operating the transmission network to ensure reliable electricity supply.

Tranche 2 will finance part of each of the three output components:

Component 1: Expanded Transmission Network (Physical investment)

Component 2: Improved Operational Effectiveness and Efficiency (Non-physical investment)

Latest Project Documents

Consulting Notices

See also: CMS

No notices are currently available for this project.

Procurement Notices

See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Power Transmission Investment Program - Tranche 2
Project Number 42039-035
Country Viet Nam
Project Status Approved
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2959-VIE: Power Transmission Investment Program, Tranche 2
Ordinary capital resources US$ 110.19 million
Loan: Power Transmission Investment Program - Tranche 2
Agence Francaise de Developpement US$ 100.00 million
Strategic Agendas Inclusive economic growth
Drivers of Change Partnerships
Sector / Subsector Energy - Electricity transmission and distribution - Energy sector development and institutional reform
Gender Equity and Mainstreaming No gender elements
Description

The investment program will contribute to meeting electricity demand growth of industrial, commercial, and residential consumers in an economically and environmentally sustainable manner. The outcome of the investment program is enhanced capacity of the transmission network to balance power load. The investment program also supports partial implementation of National Power Sector Development Master Plan VII (PDMP VII) to meet growing electricity demand of industrial, commercial and residential consumers throughout Viet Nam, and improve the operational effectiveness and efficiency of the National Power Transmission Corporation (NPT) the entity responsible for financing, managing, and operating the transmission network to ensure reliable electricity supply.

Tranche 2 will finance part of each of the three output components:

Component 1: Expanded Transmission Network (Physical investment)

Component 2: Improved Operational Effectiveness and Efficiency (Non-physical investment)

Component 3: Project Implementation Support (Non-physical investment)

Project Rationale and Linkage to Country/Regional Strategy

Recognizing the need to overcome current constraints in the power sector to ensure that rapidly growing electricity demand can be met in an economically and environmentally sustainable manner to sustain economic growth, the government of Viet Nam approved in 2011 the PDMP VII . With PDMP VII, the government approved multiple power generation and transmission projects to be implemented during 2011 -2020 and laid out a detailed road map and reform framework for (i) strengthening financial capacity, (ii) improving the operational performance of power sector entities, (iii) enhancing human resource capacity and development, (iv) improving the technological optimization and modernization of power sector infrastructure, and (v) enhancing energy efficiency in generation and consumption to sustainably develop and modernize Viet Nam's power sector.

To improve the financial sustainability of power sector entities, the Prime Minister approved in July 2012 EVN's 2011- 2015 Operation and Business Plan. The plan includes a provision for revaluation of NPT's assets of D15,000 billion to raise NPT's equity to D22,000 billion by the end of 2012. The asset revaluation will contribute to progressively improve NPT's financial performance in line with the objectives under the power transmission investment program of achieving a (i) debt-service coverage ratio of 1.5, (ii) self-financing ratio of 25%, and (iii) debt-to-equity ratio of 75:25 by 2015. Financial and implementation details of the asset revaluation are currently under approval by the Ministry of Finance. The asset revaluation is scheduled to take place end of 2012.

Impact Enhanced capacity to balance power load in southern Viet Nam
Project Outcome
Description of Outcome Strengthened financial and operational capacity of NPT
Progress Toward Outcome Tranche 2 activities are on scheduled. All procurement packages have been awarded. Most of the safeguard consulting services have been engaged. The remaining consulting services have been advertised and selection process to be finalized in Q2 2015.
Implementation Progress
Description of Project Outputs

Component 1: Expanded Transmission Network

Energized transmission lines

Component 2:

Improved Operational Effectiveness and Efficiency of NPT

Strengthened investment planning and management capacity of NPT

Component 3:

Project Implementation Support

Enhanced streamlined project implementation

Strengthened safeguard compliance management

Effective support in design and construction

Status of Implementation Progress (Outputs, Activities, and Issues) All activities are being closely monitored.
Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement A
Indigenous Peoples B
Summary of Environmental and Social Aspects
Environmental Aspects Subprojects of tranche 2 are category B under ADB's environment guidelines. No component of any of the three subprojects is located in an environmentally sensitive or protected area, and potential impacts during construction will be mitigated by using good international construction practices. The main identified impact will be the clearing of 40 hectares of degraded forest within the right of way of the 500kV Pleiku-My Phuoc-Cau Bong transmission line. The impact will be offset through tree planting in equivalent areas. An initial environmental examination (IEE) report with an environmental management plan and implementation budget was prepared for each of the subprojects under tranche 2. The IEEs were disclosed on ADB's website in August 2012.Environmental units supported by individual national and international consultants have been formed within each PPMB to supervise implementation and assure occupational and community health and operation until operation of the transmission lines.
Involuntary Resettlement Tranche 2 will build transmission lines that require land acquisition but no need to relocate houses is expected. A total of 4,023 household, 56 plantations owned by local communes will be affected and 64 households will be severely affected. The following plans/measures are in place to address this - combined resettlement framework and ethnic minority planning framework, resettlement plan and combined resettlement and ethnic minority development plan.
Indigenous Peoples A total of 1,039 ethnic minority households will be affected. Where ethnic minorities will be affected by the construction of the 500kV Pleiku-My Phuoc-Cau Bong transmission line, combined resettlement and ethnic minority development plans were prepared. Implementation will be closely monitored.
Stakeholder Communication, Participation, and Consultation
During Project Design Consultations regarding land acquisition were undertaken with key government officials and the affected people for subprojects included in Tranche 2.
During Project Implementation
Business Opportunities
Consulting Services The procurement plan has been uploaded on ADB's website.
Procurement The procurement plan has been uploaded in ADB's website.
Responsible ADB Officer Jim Liston
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Energy Division, SERD
Executing Agencies
National Power Transmission CorporationTUONGDP@NPT.EVN.VN885 Hong Ha Street
Hoan Kiem District
Ha Noi
Timetable
Concept Clearance -
Fact Finding -
MRM 24 Aug 2012
Approval 05 Dec 2012
Last Review Mission -
Last PDS Update 27 Mar 2015

Loan

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 100.00 Cumulative Contract Awards
ADB 0.00 - 0.00 0.00 %
Counterpart 0.00 Cumulative Disbursements
Cofinancing 100.00 - 0.00 0.00 %

Loan 2959-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
05 Dec 2012 21 Dec 2012 31 May 2013 30 Nov 2016 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 360.97 Cumulative Contract Awards
ADB 110.19 05 Dec 2012 60.93 0.00 89%
Counterpart 250.78 Cumulative Disbursements
Cofinancing 0.00 05 Dec 2012 54.88 0.00 80%

Safeguard Documents

See also: Safeguards
Title Document Type Document Date
Power Transmission Investment Program - Tranche 2: 500kV Pleiku-My Phuoc-Cau Bong Transmission Line - Second Semiannual Environmental Monitoring Report (July-December 2014) Environmental Monitoring Reports Mar 2015
Power Transmission Investment Program - Tranche 2: 220kV Cau Bong-Duc Hoa Transmission Line Subproject Semiannual Environmental Monitoring Report (June-December 2014) Environmental Monitoring Reports Jan 2015
Power Transmission Investment Program - Tranche 2: 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Subproject Semiannual Environmental Monitoring Report (June-December 2014) Environmental Monitoring Reports Jan 2015
Power Transmission Investment Program - Tranche 2: 220kV Cau Bong-Hoc Mon-Binh Tan Transmission Line Social Monitoring Report (June-December 2014) Social Monitoring Reports Jan 2015
Power Transmission Investment Program - Tranche 2: 220kV Cau Bong-Duc Hoa Transmission Line Social Monitoring Report (June-December 2014) Social Monitoring Reports Jan 2015
Power Transmission Investment Program - Tranche 2: 220kV Cau Bong-Cu Chi Transmission Line Project Resettlement Plan Due Diligence Report Safeguards Due Diligence Reports Aug 2014
Power Transmission Investment Program - Tranche 2: 500kV Pleiku‐My Phuoc‐Cau Bong Transmission Line Semiannual Environmental Monitoring Report (January-June 2014) Environmental Monitoring Reports Aug 2014
Power Transmission Investment Program - Tranche 2: 500kV Pleiku-My Phuoc-Cau Bong Transmission Line - First Semiannual Environmental Monitoring Report (January-June 2014) Environmental Monitoring Reports Aug 2014
Power Transmission Investment Program - Tranche 2: 500kV Pleiku-My Phuoc-Cau Bong Transmission Line Independent Monitoring Report on Resettlement and Ethnic Minority in Dak Nong Province (July 2014) Social Monitoring Reports Jul 2014
Power Transmission Investment Program - Tranche 2: 500kV Pleiku-My Phuoc-Cau Bong Transmission Line Independent Monitoring Report on Resettlement and Ethnic Minority in Gia Lai Province (July 2014) Social Monitoring Reports Jul 2014
Power Transmission Investment Program - Tranche 2: 500kV Pleiku-My Phuoc-Cau Bong Transmission Line Independent Monitoring Report on Resettlement and Ethnic Minority in Binh Duong Province (July 2014) Social Monitoring Reports Jul 2014
Power Transmission Investment Program - Tranche 2: 500kV Pleiku-My Phuoc-Cau Bong Transmission Line Independent Monitoring Report on Resettlement and Ethnic Minority in Ho Chi Minh City (July 2014) Social Monitoring Reports Jul 2014
Power Transmission Investment Program - Tranche 2: 500kV Pleiku-My Phuoc-Cau Bong Transmission Line Independent Monitoring Report on Resettlement and Ethnic Minority in Binh Phuoc Province (July 2014) Social Monitoring Reports Jul 2014
Power Transmission Investment Program: 220kV Cau Bong-Hoc Mon-Branches to Binh Tan Transmission Line Resettlement Plan Resettlement Plans Jul 2014
Power Transmission Investment Program - Tranche 2: 500kV Pleiku-My Phuoc-Cau Bong Transmission Line Independent Monitoring Report on Resettlement and Ethnic Minority in Dak Lak Province (July 2014) Social Monitoring Reports Jul 2014
Power Transmission Investment Program: Pleiku-My Phuoc-Cau Bong 500 kV Transmission Line Due Diligence and Corrective Action Plan Resettlement Plans Aug 2012
Power Transmission Investment Program - Tranche 2: Cau Bong - Hoc Mon 220 kV Transmission Line Initial Environmental Examination Jul 2012
Power Transmission Investment Program - Tranche 2: Cau Bong - Duc Hoa 220 kV Transmission Line Initial Environmental Examination Jul 2012
Power Transmission Investment Program - Tranche 2: Pleiku-My Phuoc-Cau Bong 500 kV Transmission Line Initial Environmental Examination Jul 2012
Power Transmission Investment Program: Cau Bong-Hoc Mon 220 kV Transmission Line (Ho Chi Minh Province Transmission Line Component) Resettlement Plans Jun 2012
Power Transmission Investment Program: Cau Bong-Duc Hoa 220 kV Transmission Line Resettlement Plans May 2012
Power Transmission Investment Program: Pleiku-My Phuoc-Cau Bong 500 Kv Transmission Line (Hồ Chί Minh City Transmission Line Component) Resettlement Plans Apr 2012
Power Transmission Investment Program: Pleiku-My Phuoc-Cau Bong 500 kV Transmission Line (Binh Dương Province Transmission Line Component) Resettlement Plans Mar 2012
Power Transmission Investment Program: Cau Bong - Duc Hoa 220 Kv Transmission Line (Ho Chi Minh Province Transmission Line Component) Resettlement Plans Mar 2012
Power Transmission Investment Program (Pleiku-My Phuoc-Cau Bong 500 kV Transmission Line): Binh Dương Province Combined Resettlement Plan and Indigenous Peoples Plans Mar 2012
Power Transmission Investment Program (Pleiku-My Phuoc-Cau Bong 500 kV Transmission Line): Ðấk Nông Province Combined Resettlement Plan and Indigenous Peoples Plans Mar 2012
Power Transmission Investment Program (Pleiku-My Phuoc-Cau Bong 500 kV Transmission Line): Ðấk Lấk Province Combined Resettlement Plan and Indigenous Peoples Plans Feb 2012
Power Transmission Investment Program (Pleiku-My Phuoc-Cau Bong 500 kV Transmission Line): Gia Lai Province Combined Resettlement Plan and Indigenous Peoples Plans Jan 2012

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.