Afghanistan: Energy Sector Development Investment Program - Tranche 4

Sovereign Project | 42094-052

Summary

The sub-projects, collectively the Project, under this Tranche 4 include (i) an electricity transmission sub-project in the North West Afghanistan to extend the network and connect to the Turkmenistan (TKM) system, and (ii) an electricity distribution sub-project to extend the distribution network south east of Kabul.

The transmission sub-project will include a 500kV transmission line from the TKM border to Andkhoy and from Andkhoy to Sheberghan and a 220kV transmission line from Sheberghan to Mazar-e-Sharif. The 220kV substations will be constructed at Andkhoy and Sheberghan and the existing 220kV substation at Mazar-e-Sharif will be expanded.

The distribution sub-project will include 20kV lines and 220/20 kV substations and low voltage network at Pul-e-Alam (Logar) and Gardez (Paktia).

Latest Project Documents

Consulting Notices

See also: CMS

No notices are currently available for this project.

Procurement Notices

See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Energy Sector Development Investment Program - Tranche 4
Project Number 42094-052
Country Afghanistan
Project Status Approved
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Grant 0332-AFG: MFF - Energy Sector Development Investment Program Project 4 (formerly MFF - Energy Development Project Tranche 4)
Asian Development Fund US$ 200.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change
Sector / Subsector Energy - Renewable energy generation - small hydro
Gender Equity and Mainstreaming No gender elements
Description

The sub-projects, collectively the Project, under this Tranche 4 include (i) an electricity transmission sub-project in the North West Afghanistan to extend the network and connect to the Turkmenistan (TKM) system, and (ii) an electricity distribution sub-project to extend the distribution network south east of Kabul.

The transmission sub-project will include a 500kV transmission line from the TKM border to Andkhoy and from Andkhoy to Sheberghan and a 220kV transmission line from Sheberghan to Mazar-e-Sharif. The 220kV substations will be constructed at Andkhoy and Sheberghan and the existing 220kV substation at Mazar-e-Sharif will be expanded.

The distribution sub-project will include 20kV lines and 220/20 kV substations and low voltage network at Pul-e-Alam (Logar) and Gardez (Paktia).

Project Rationale and Linkage to Country/Regional Strategy

The transmission subproject will allow TKM to supply electricity to North-West AFG where demand is estimated at 210 megawatts (MW) requiring 1,000 megawatt-hour (MWh) by 2020 to supply 120,000 households, and at 330 MW requiring 1,750 gigawatt-hour (GWh) by 2030 to supply 145,000 households. It will also allow Uzbekistan (UZB) imports, to be used to supply the Kabul region, which is currently facing a supply shortfall.

While electrification rate has increased from 5% in 2002 to 25% in 2012, AFG continues to place high priority on further increasing electrification. The distribution subproject meets this aim and is coordinated with related projects financed by the United States Government. The related project will extend the 220 kV network to Pul-e-Alam and Gardez where 220/20 kV substations will be constructed. The distribution subproject proposed under Tranche 4 will construct 20 kV and low voltage networks to be supplied from Pul-e-Alam and Gardez substation and bring electricity supply to 20,000 new households.

Impact Increased regional power trade and energy supplies in Afghanistan
Project Outcome
Description of Outcome Reliable power supplies to all grid connected customers
Progress Toward Outcome Financial bid evaluation for two turnkey packages (i) 220/110/20kV Substations and (ii) 500 kV S/C OHL are in progress. The bidding documents for distribution component in south-east Afghanistan is under preparation and contract is expected to be awarded in Q4 2015.
Implementation Progress
Description of Project Outputs

Commissioning of 108 kms 500 kV transmission line from AFG/TKM border to Andkhoy to Sheberghan

Commissioning of 142 kms 220 line from Sheberghan to Mazar-e-Sharif

Commissioning of 220/20 kV substations at Andkhoy and Sheberghan and expansion of 220 kV substation at Mazar-e- Sharif

Commissioning of 220/20 kV substations at Pul-e-Alam and Gardez

Commissioning of 10,000 new power connections at Pul-e-Alam and 10,000 new power connections in Gardez city

Status of Implementation Progress (Outputs, Activities, and Issues) Financial bid evaluation is in progress and contract is expected to be awarded in Q2 2015.
Geographical Location Andkhoy, Sheberghan, Mazar-e-Sharif, Pul-e-Alam, and Gardez
Safeguard Categories
Environment B
Involuntary Resettlement B
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects An IEE report for the Project has been prepared and posted in accordance with ADB Guidelines and ADB Safeguard Policy Statement, June 2009, Laws on the protection of nature of the Government of Afghanistan, discussions with the MEW and National Environmental Protection Agency (NEPA). The IEE will be updated during Project implementation based on contractor's detailed designs.
Involuntary Resettlement The Project may have some involuntary resettlement impacts that are not significant. A draft LARP for the transmission line (Andkhoy to Mazar-i-Sharif) was prepared in October 2012.
Indigenous Peoples Impacts on indigenous peoples are not envisaged.
Stakeholder Communication, Participation, and Consultation
During Project Design The current security situation makes it difficult to undertake effective community consultation without compromising the safety of staff and consultants. No public consultation has been carried out at this stage.
During Project Implementation Necessary public consultation will be conducted on-site by the Program Management Office of DABS with assistance from the implementation consultant prior to commencement of construction and will be reported to ADB in due course. The project impacts are not considered significant. As the project develops and if particular risks or impacts to the local community are identified; then a community relation plan and grievance mechanism will be developed.
Business Opportunities
Consulting Services

1. Program Management and Implementation Consultants - Quality-Based Selection using Full Technical Proposal

2. External Auditor - Single Source Selection

Procurement

1. 500 kV Transmission Line (100 kms approx) from AFG/TKM border to Sheberghan and 220 kV Transmission Line (142 kms approx) between Sheberghan and Mazar Sharif - ICB Turnkey

2. 220/20 kV substations at Andkhoy and Sheberghan and expansion of 220kv substation at Mazar Sharif - ICB Turnkey

3. 220/20 kv Distribution Networks 20 kV Distribution Networks:

Lot 1: Pul-e-Alam(13,000 connections), Lot 2: Gardez (13,000 connections) and Wazay Zadran (5,000

connections); Lot 3:Khost (13,000 connections)- ICB Turnkey

Responsible ADB Officer Sohail Hasnie
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Energy Division, CWRD
Executing Agencies
Da Afghanistan Breshna SherkatRAZIQUE.SAMADI@DABS.AFChaman Houzouri,Kabul,Islamic Republic
of Afghanistan
Timetable
Concept Clearance -
Fact Finding -
MRM 23 Nov 2012
Approval 18 Dec 2012
Last Review Mission -
Last PDS Update 30 Mar 2015

Grant 0332-AFG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
18 Dec 2012 07 Mar 2013 05 Jun 2013 30 Jun 2017 - -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 203.00 Cumulative Contract Awards
ADB 200.00 18 Dec 2012 0.00 0.00 0%
Counterpart 3.00 Cumulative Disbursements
Cofinancing 0.00 18 Dec 2012 0.00 0.00 0%

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.