Afghanistan: Energy Sector Development Investment Program - Tranche 4

Sovereign Project | 42094-052 Status: Active

Summary

ADB is helping Afghanistan upgrade its energy infrastructure to improve supply and increase regional power trade. The project will install transmission lines to expand the network in North-West Afghanistan and to connect to the Turkmenistan system. It will also extend the distribution network southeast of Kabul, the capital.

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Energy Sector Development Investment Program - Tranche 4
Project Number 42094-052
Country Afghanistan
Project Status Active
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Grant 0332-AFG: MFF - Energy Sector Development Investment Program Project 4 (formerly MFF - Energy Development Project Tranche 4)
Asian Development Fund US$ 200.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change
Sector / Subsector

Energy - Renewable energy generation - small hydro

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome Target achievable as various import and indigenous generation projects are under implementation.
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues) Project Implementation Consultant has been mobilized. Two turnkey contracts have been awarded for the (i) 500 kV transmission line Aqina to Sheberghan and Sheberghan to Mazar-e-Sharif; and (ii) 220kV substations at Andkhoy and Sheberghan and an upgradation of an existing 220kV substation at Mazar-e-Sharif. Bid evaluation for the distribution subprojects is on-going.
Geographical Location Andkhoy, Sheberghan, Mazar-e-Sharif, Pul-e-Alam, and Gardez

Summary of Environmental and Social Aspects

Environmental Aspects An IEE report for the Project has been prepared and posted in accordance with ADB Guidelines and ADB Safeguard Policy Statement, June 2009, Laws on the protection of nature of the Government of Afghanistan, discussions with the MEW and National Environmental Protection Agency (NEPA). The IEE will be updated during Project implementation based on contractor's detailed designs.
Involuntary Resettlement The Project may have some involuntary resettlement impacts that are not significant. A draft LARP for the transmission line (Andkhoy to Mazar-i-Sharif) was prepared in October 2012.
Indigenous Peoples Impacts on indigenous peoples are not envisaged.
Stakeholder Communication, Participation, and Consultation
During Project Design The current security situation makes it difficult to undertake effective community consultation without compromising the safety of staff and consultants. No public consultation has been carried out at this stage.
During Project Implementation Necessary public consultation will be conducted on-site by the Program Management Office of DABS with assistance from the implementation consultant prior to commencement of construction and will be reported to ADB in due course. The project impacts are not considered significant. As the project develops and if particular risks or impacts to the local community are identified; then a community relation plan and grievance mechanism will be developed.

Business Opportunities

Consulting Services

1. Program Management and Implementation Consultants - Quality-Based Selection using Full Technical Proposal

2. External Auditor - Single Source Selection

Procurement

1. 500 kV Transmission Line (100 kms approx) from AFG/TKM border to Sheberghan and 220 kV Transmission Line (142 kms approx) between Sheberghan and Mazar Sharif - ICB Turnkey

2. 220/20 kV substations at Andkhoy and Sheberghan and expansion of 220kv substation at Mazar Sharif - ICB Turnkey

3. 220/20 kv Distribution Networks 20 kV Distribution Networks:

Lot 1: Pul-e-Alam(13,000 connections), Lot 2: Gardez (13,000 connections) and Wazay Zadran (5,000

connections); Lot 3:Khost (13,000 connections)- ICB Turnkey

Responsible Staff

Responsible ADB Officer Asad Aleem
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Energy Division, CWRD
Executing Agencies
Da Afghanistan Breshna Sherkat
RAZIQUE.SAMADI@DABS.AF
Chaman Houzouri,
Kabul,
Islamic Republic of Afghanistan

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
Last PDS Update 31 Mar 2016

Grant 0332-AFG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
18 Dec 2012 07 Mar 2013 05 Jun 2013 30 Jun 2017 28 Nov 2018 -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 203.00 Cumulative Contract Awards
ADB 200.00 18 Dec 2012 97.70 0.00 49%
Counterpart 3.00 Cumulative Disbursements
Cofinancing 0.00 18 Dec 2012 13.85 0.00 7%
Status of Covenants
Category Sector Safeguards Social Financial Economic Others
Rating - - - Satisfactory - -

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.