Afghanistan: Energy Sector Development Investment Program - Tranche 5

Sovereign Project | 42094-075 Status: Active

Summary

ADB is helping Afghanistan improve power supply in the northern, eastern, and southern parts of the country. The project will build a 500-kV/220-kV substation at Dashte Alwan, which will connect to a 500-kV transmission line crossing the Hindukush mountains via the Salang Pass route. This will add 1,000 megawatts to the system and allow power imports from Tajikistan, Turkmenistan, and Uzbekistan.

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Energy Sector Development Investment Program - Tranche 5
Project Number 42094-075
Country Afghanistan
Project Status Active
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Grant 0377-AFG: Energy Sector Development Investment Program - Tranche 5
Asian Development Fund US$ 49.10 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change
Sector / Subsector

Energy - Electricity transmission and distribution

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome The EPC contract has been awarded to KEC International in January 2016. Advance payment will be made in early April 2016 and contractor will be mobilized by mid-April 2016. The contract of implementation supervision consultant is under negotiation with the first ranked firm.
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues) Physical work including project detailed design is expected to commence from mid April 2016. The project will be commissioned in 30 months.
Geographical Location Dashte Alwan

Safeguard Categories

Environment B
Involuntary Resettlement B
Indigenous Peoples C

Summary of Environmental and Social Aspects

Environmental Aspects Environmental categorization of the project is B in accordance with ADB's Safeguard Policy Statement (SPS 2009). An IEE was prepared and disclosed on ADB's website on 22 August 2013 in accordance with SPS. The current security situation makes it difficult to undertake wide-scale public consultation; however, representatives of affected people were consulted during preparation of the LARP. Additional public consultations will be conducted as part of the LARP updating during implementation. The draft LARP was disclosed on the ADB website on 22 August 2013. The IEE and environment monitoring plan will be updated prior to construction activity. The substation site has low environmental sensitivities with no significant environmental impacts expected during construction and operation phases. The environmental management plan has been prepared as part of the IEE to ensure that adequate resources are allocated to handle the environmental impacts. PMO staff is involved in similar projects financed by ADB and they have sufficient capacity to manage the environmental safeguards. Environmental specialists of the implementation consultants will also provide support to the PMO. The environmental assessment review framework was updated and disclosed on ADB's website on 3 September 2013.
Involuntary Resettlement The project is category B for involuntary resettlement safeguard. A LARP has been prepared based on project design, in close consultation with affected farming community, and disclosed on ADB's website on 22 August 2013. A socioeconomic survey was carried out in June 2013. DABS will update the LARP after finalizing the detailed design and submit it to ADB for approval before physical works can begin.
Indigenous Peoples The project is categorized C for indigenous peoples safeguard. The field social survey found no ethnic minority, as described in SPS 2009, involved or affected by the project.
Stakeholder Communication, Participation, and Consultation
During Project Design The project has limited scope for stakeholder engagement since it involves construction of upstream power sector infrastructure. Information sharing will relate to the siting of infrastructure in relation to land acquisition.
During Project Implementation Consultations with all stakeholders will be undertaken during implementation and construction works. A process and modality for such consultative process of dialogue is already institutionalized under the earlier 4 tranches of MFF. The land acquisition and resettlement plans and environment management plans will be updated in requisite intervals.

Business Opportunities

Consulting Services The PMO established in DABS under previous tranches will be responsible for project implementation. An implementation consultant will be recruited to assist the PMO. Consultants will be engaged in accordance with the Guidelines on the Use of Consultants by ADB and Its Borrowers (2013, as amended from time to time). Implementation consultant will be recruited using the quality- and cost-based selection method. Least-cost selection will be used for auditing services.
Procurement Procurement of works and goods to be financed under the project will be undertaken in accordance with ADB''s Procurement Guidelines (2013, as amended from time to time). International competitive bidding will be used for the turnkey contract 500-kV substations package.

Responsible Staff

Responsible ADB Officer Asad Aleem
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Energy Division, CWRD
Executing Agencies
Da Afghanistan Breshna Sherkat
Chaman Houzouri,
Kabul,
Islamic Republic of Afghanistan

Timetable

Concept Clearance -
Fact Finding -
MRM 11 Sep 2013
Approval -
Last Review Mission -
Last PDS Update 31 Mar 2016

Grant 0377-AFG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
04 Dec 2013 14 Dec 2013 10 Mar 2014 30 Jun 2017 28 Nov 2018 -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 53.00 Cumulative Contract Awards
ADB 49.10 04 Dec 2013 49.10 0.00 100%
Counterpart 3.90 Cumulative Disbursements
Cofinancing 0.00 04 Dec 2013 7.49 0.00 15%

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.