Nepal: Preparing Hydropower Development for Energy Crisis

Sovereign Project | 43281-012 Status: Closed

Summary

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Preparing Hydropower Development for Energy Crisis
Project Number 43281-012
Country Nepal
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 7590-NEP: Preparing Hydropower Development for Energy Crisis
Japan Fund for Poverty Reduction US$ 2.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Private sector development
Sector / Subsector

Energy - Large hydropower generation

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation

Business Opportunities

Consulting Services The TA will require 83 person-months of consulting services (48 international and 35 national) comprising Power Sector Management Specialist (international, 6.5 person-months), Financial Specialist (international, 4.0 person-months; national, 2.0 person-months), Economist (international, 1.0 person-months; national, 2.0 person-months), Environment Specialist (international, 3.5 person-months; national, 4.0 person-months), Social Development Specialist (international, 4.5 person-months; national, 6.0 person-months), Legal and Contractual Specialist (international, 1.5 person-months), Communication Development Specialist (international, 3.0 person-months; national, 5.0 person-months), Community Development Specialist (national, 4.0 person-months), Hydropower Planning Engineer (international, 6.5 person-months; national, 6.0 person-months), Hydrological Engineer (international, 4.5 person-months), Construction Planning Engineer (international, 4.5 person-months; national, 6.0 person-months), Electrical Enginner (international, 4.5 person-months), and Mechanical Engineer (international, 4.0 person-months).

Responsible Staff

Responsible ADB Officer Kaoru Ogino
Responsible ADB Department South Asia Department
Responsible ADB Division Energy Division, SARD
Executing Agencies
Nepal Electricity Authority
Sanepa, Lalitpur
Nepal

Timetable

Concept Clearance 15 Mar 2010
Fact Finding 23 Feb 2010 to 04 Mar 2010
MRM -
Approval -
Last Review Mission -
PDS Creation Date 18 Oct 2010
Last PDS Update 26 Mar 2015

TA 7590-NEP

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
02 Sep 2010 28 Sep 2010 28 Sep 2010 30 Sep 2012 31 Dec 2014 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
0.00 2,000,000.00 360,000.00 0.00 0.00 0.00 2,360,000.00 02 Sep 2010 1,992,552.56

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.