India: MFF-Himachal Pradesh Clean Energy Transmission Investment Program - Tranche 1

Sovereign Project | 43464-023

Summary

The Project proposed for financing under the requested PFR consists of:

1. New Transmission System Assets

A. Transmission Line Construction

i. An approximately 28 km, 220 kV double circuit transmission line from Hatkoti to Pragati Nagar, District Shimla.

B. Construction of SubStations

i. 66/220/400 kV gas insulated switchgear (GIS) substation at Wangtoo, District Kinnaur, and connecting 400 kV double circuit transmission line, (i.e. loop-in loop-out or LILO ) from Wangtoo to Abdullahpur

ii. 220/400 kV GIS substation near Pragati Nagar, District Shimla, plus connection line by LILO of 400 kV D/C line from Jhakri to Addullahpur

iii. 66/220 kV GIS substation at Bhoktoo, District Kinnaur plus connection line (LILO) of 220 kV D/C line from Kashang to Bhaba

2. Capacity Development

i. Computerized enterprise resource planning solution design and installation

ii. Additional computer and engineering design equipment

Latest Project Documents

Consulting Notices

See also: CMS

No notices are currently available for this project.

Procurement Notices

See also: Operational Procurement

Procurement Documents

No documents of this type are currently available for this project.


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name MFF-Himachal Pradesh Clean Energy Transmission Investment Program - Tranche 1
Project Number 43464-023
Country India
Project Status Approved
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2794-IND: Himachal Pradesh Clean Energy Transmission - Tranche 1
Ordinary capital resources US$ 113.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector Energy - Electricity transmission and distribution
Gender Equity and Mainstreaming No gender elements
Description

The Project proposed for financing under the requested PFR consists of:

1. New Transmission System Assets

A. Transmission Line Construction

i. An approximately 28 km, 220 kV double circuit transmission line from Hatkoti to Pragati Nagar, District Shimla.

B. Construction of SubStations

i. 66/220/400 kV gas insulated switchgear (GIS) substation at Wangtoo, District Kinnaur, and connecting 400 kV double circuit transmission line, (i.e. loop-in loop-out or LILO ) from Wangtoo to Abdullahpur

ii. 220/400 kV GIS substation near Pragati Nagar, District Shimla, plus connection line by LILO of 400 kV D/C line from Jhakri to Addullahpur

iii. 66/220 kV GIS substation at Bhoktoo, District Kinnaur plus connection line (LILO) of 220 kV D/C line from Kashang to Bhaba

2. Capacity Development

i. Computerized enterprise resource planning solution design and installation

ii. Additional computer and engineering design equipment

iii. Training program.

Project Rationale and Linkage to Country/Regional Strategy
Impact HPPTL has sufficient assets and capacity to support its mandate as the state transmission utility company
Project Outcome
Description of Outcome HPPTL has increased its asset base and its capacity.
Progress Toward Outcome

Implementation is ongoing.

A review mission was conducted last 22-25 September 2014.

Implementation Progress
Description of Project Outputs

New Transmission system assets are operational

HPPTCL's management capacity enhanced

Status of Implementation Progress (Outputs, Activities, and Issues)

All the four civil contracts have been awarded.

The following contracts for HPPTCL's capacity development have been awarded:

1. ERP consultant;

2. Project Resettlement and Rehabilitation Consultant;

3. Financial Management Specialist; and

4. Project Environment Consultant.

Geographical Location
Safeguard Categories
Environment B
Involuntary Resettlement B
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects The tranche 1 project is environment category B. The civil construction work is limited to building foundations for the transmission towers, and substations, and the tranche 1 project does not come within any environmentally sensitive area. Based on the environmental assessment and surveys, associated potential adverse environmental impacts are minimal and can be mitigated through implementation of the EMP. An adequate budgetary provision in the tranche 1 project covers the environmental mitigation and monitoring requirements, and the EMP is part of the construction contracts. The EA will supervise the construction contracts and EMP implementation, and quarterly progress reports of its implementation will be submitted to ADB. Overall, the major social and environmental impacts associated with the tranche 1 project are limited to the construction period and can be mitigated to an acceptable level by implementation of recommended engineering measures and environmental practices. A similar result is expected for future tranches based on investigations conducted to date.
Involuntary Resettlement The tranche 1 project is involuntary resettlement category B. Census surveys and consultations were undertaken in accordance with ADB's Safeguard Policy Statement. The tranche 1 project will entail minimum private land acquisition. Of the three proposed substations, two are to be built on government land, and the third requires 2.67 hectares of private land. The transmission line will have 76 towers out of which 63 will be located on privately owned land, 10 towers will be placed on government land and the remaining three towers will be placed on community land. There are no structures or buildings to be affected and no physical displacement is foreseen. In total, the tranche 1 project includes the acquisition of 4.09 hectares of private land. Regarding gender issues, the loan agreements include a standard assurance related to core labor standards for contractors (including equal pay for equal type of work), and an awareness program on HIV and sexually transmitted diseases and human trafficking.
Indigenous Peoples The tranche 1 project is indigenous peoples category C.
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Takeshi Shiihara
Responsible ADB Department South Asia Department
Responsible ADB Division Energy Division, SARD
Executing Agencies
Himachal Pradesh Power Transmission Corp. Ltd.MD.HPPTCL@GMAIL.COMBarowalia House, Khalini, Shimla 171002
Himachal Pradesh, India
Timetable
Concept Clearance 11 Jan 2011
Fact Finding 04 May 2011 to 13 May 2011
MRM 17 Jun 2011
Approval 18 Oct 2011
Last Review Mission -
Last PDS Update 27 Mar 2015

Loan 2794-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
18 Oct 2011 15 Dec 2011 19 Jan 2012 30 Jun 2018 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 113.00 Cumulative Contract Awards
ADB 113.00 18 Oct 2011 85.58 0.00 76%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 18 Oct 2011 32.87 0.00 29%

Safeguard Documents

See also: Safeguards

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.