India: Uttar Pradesh Major District Road Investment Program

Sovereign Project | 43574-022 Status: Closed

Summary

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Uttar Pradesh Major District Road Investment Program
Project Number 43574-022
Country India
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 8427-IND: Uttar Pradesh Major District Road Investment Program
Technical Assistance Special Fund US$ 700,000.00
Strategic Agendas Inclusive economic growth
Drivers of Change Private sector development
Sector / Subsector

Transport - Road transport (non-urban)

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design Consultation with the Government of Uttar Pradesh (GOUP) and other stakeholders as well as with other donors particularly the World Bank to ensure coordination with regard to institutional matters.
During Project Implementation Consultations and discussions have been carried out with all stakeholders as described during project design. The technical work of the PPTA was substantially completed by November 2015, and the PPTA itself has been concluded in January 2016. Final closing actions are in progress.

Business Opportunities

Consulting Services A firm (or consortium of firms) will be engaged to undertake this PPTA. As estimated, this assignment will require 3 international experts for a total of 12 person-months, and 8 national experts of a total of 28 person-months. The consulting firm will be engaged following the quality- and cost-based selection method, with a quality:cost ratio of 80:20 using full technical proposal procedures. Procurement of all consultancy services used under the PPTA will be carried out in accordance with ADB's Guidelines on the Use of Consultants.

Responsible Staff

Responsible ADB Officer Ravi Peri
Responsible ADB Department South Asia Department
Responsible ADB Division Transport and Communications Division, SARD
Executing Agencies
Public Works Department, Uttar Pradesh
Lucknow
India

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
Last PDS Update 21 Mar 2016

TA 8427-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
13 Aug 2013 28 Mar 2014 28 Mar 2014 31 Jan 2015 31 Jan 2016 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
700,000.00 0.00 0.00 0.00 0.00 0.00 700,000.00 13 Aug 2013 633,068.30

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.