Georgia: Regional Power Transmission Enhancement Project

Sovereign Project | 44183-013 Status: Active

Summary

ADB is helping Georgia upgrade its power substations to boost its ability to export electricity in the Caucasus. The project will rehabilitate several substations by installing modern digital control and relay protection systems designed to improve energy management and power dispatch. It will also build a 220 kilovolt substation at Khorga and support a study on potential hydropower projects.

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Regional Power Transmission Enhancement Project
Project Number 44183-013
Country Georgia
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2974-GEO: Regional Power Transmission Enhancement Project
Asian Development Fund US$ 48.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Regional integration
Drivers of Change
Sector / Subsector

Energy - Electricity transmission and distribution

Gender Equity and Mainstreaming Some gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome All works are ongoing.
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)

1a. Menji Substation: Designs were completed and approved. Manufacturing of auto transformer is completed. Construction activities have yet to start.

1b. Ksani Substation: Design is under review. Time schedule and sequences for 220 kV switchyard submitted for approval.

1c. Marnueli Substation: Designs are under review.

2. Engineering activities are mostly completed; Installation of 220 kV and 110 kV equipment completed; Energizing of power supply in protection and control containers has been performed; Internal pre-commissioning of contractor has started; Installation of power transformer is planned in Feb 2016. Due to initial delays and difficulties in road works, contract completion is extended to April 2016.

3. Consulting services are proceeding according to schedule and within the budget.

Geographical Location

Ksani to border with Armenia

Gardabani to border with Azerbaijan

Khorga

Paliastomi

Batumi

Safeguard Categories

Environment B
Involuntary Resettlement B
Indigenous Peoples C

Summary of Environmental and Social Aspects

Environmental Aspects The project does not seem to involve major environmental issues that cannot be mitigated. Necessary due diligence was undertaken during PPTA.
Involuntary Resettlement The project does not seem to involve major social issues that cannot be mitigated. Necessary due diligence was undertaken during PPTA.
Indigenous Peoples No impacts on indigenous peoples are envisaged so far.
Stakeholder Communication, Participation, and Consultation
During Project Design Stakeholders' consultations through community meetings, discussions, and interviews were conducted during the PPTA. Potential initial stakeholders are general households, business community, and public and social institutions.
During Project Implementation Consultation meetings with affected people and project stakeholders are being done.

Business Opportunities

Consulting Services Implementation consultants through QCBS
Procurement Construction and installation of facilities through ICB

Responsible Staff

Responsible ADB Officer Tianhua Luo
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Energy Division, CWRD
Executing Agencies
Ministry of Energy and Natural Resources (MOENR)
Mr. ILIA ELOSHVILI
MARIKA.VALISHVILI@MINENERGY.GOV.GE
Gulua 6, Tbilisi 0105, Georgia
Georgian State Electrosystem
Mr. Sulkhan Zumburidze
MAYA_EMSP@GSE.COM.GE
2, Baratashvili str., Tbilisi 0105, Georgia

Timetable

Concept Clearance 06 Jul 2010
Fact Finding 25 Apr 2011 to 06 May 2011
MRM 21 Jun 2011
Approval -
Last Review Mission -
Last PDS Update 30 Mar 2016

Loan 2974-GEO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
17 Dec 2012 21 Mar 2013 23 Oct 2013 31 Dec 2016 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 67.00 Cumulative Contract Awards
ADB 48.00 17 Dec 2012 43.57 0.00 100%
Counterpart 19.00 Cumulative Disbursements
Cofinancing 0.00 17 Dec 2012 35.00 0.00 80%

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.