Kyrgyz Republic: Power Sector Rehabilitation Project

Sovereign Project | 44198-012 Status: Closed

Summary

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Power Sector Rehabilitation Project
Project Number 44198-012
Country Kyrgyz Republic
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 7704-KGZ: Power Sector Rehabilitation
Technical Assistance Special Fund US$ 1.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change
Sector / Subsector

Energy - Electricity transmission and distribution - Energy efficiency and conservation - Energy sector development and institutional reform

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome

Concept paper was approved on 15 Dec 2010 to prepare the detailed feasibility study for the Power Rehabilitation Project as well as conduct the necessary due diligence in accordance with ADB requirements.

A Financial and Risk Management Consultant (individual) has been recruited to assess the (i) suitability of the effectiveness of financial management systems and controls, and (ii) financial reporting standards and policies relating to management and control of project funds in four distribution companies (DISCOs). In addition, the Consultant will prepare a risk assessment (RA) and risk management plan (RMP) for the Kyrgyz energy/power sector.

A consulting firm has been likewise recruited to prepare the the feasibility study for the rehabilitation of hydropower plant (HPP) of the Naryn River cascade and installation of a modern billing and collection system for Severelectro. The consulting firm is expected to provide inputs on the preparation for the ensuing Project which includes among others: (i) EA and IA capacity assessment, (ii) proposed procurement plan, and (iii) indicative implementation schedule. The Project Inception Meeting is tentatively scheduled by end-July 2011.

Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location National

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design The Ministry of Energy (MOE), Electric Power Plant Company (EPP), and Severelectro were consulted during the project design. Activities being undertaken by other development partners (e.g., Kredtanstalt fur Wiederaufbau) in the sector are also considered.
During Project Implementation

Public consultations were held to identify and assess the potential poverty reduction, social, and environmental impacts of the ensuing Project. The results of such consultations are shared to the relevant government agencies and disseminated to the public. These documents are available at the ADB website (http://www.adb.org/projects/44198-013/main).

Close coordination are likewise made with the implementing agencies namely, EPP and Severelectro, all throughout the project implementation.

Business Opportunities

Consulting Services

The PPTA consultant will be a firm. There are seven positions each for international (27 person-months [p-m]) and national consultants (30 p-m) comprising of: (i) hydropower expert/team leader, (ii) electrical engineers, (iii) electro-mechanical engineer, (iv) billing and collection system experts, (v) procurement experts, (vi) economic and financial analysis experts, and (vii) environmental and social safeguard experts. Quality- and cost-based selection (QCBS [80:20]) will be used for the selection method with simplified technical proposal.

The consultant, among other tasks, needs to adequately address the following aspects relating to the ensuing loan project: (i) detailed loan executing agency /implementing agency capacity assessment, and suggested remedial action plan to build executing agency and implementing agency capacity to minimize procurement and financial management risks; (ii) proposed or indicative loan related procurement plan with suggested level of priority or, if applicable, post review based on executing agency and implementing agency capacity assessment; and (iii) indicative implementation schedule with proposed sequencing of consultant recruitment and procurement bidding and awarding.

Expressions of Interest (EOIs) were submitted and short-listing was made on 21 January 2011. Request for Government concurrence was sent on 2 February 2011, and on a no-objection basis a Request for Proposal (RFP) was issued on 9 February 2011. The Consultant Selection Committee (CSC) evaluated the technical proposals on 25 March 2011, and subsequently COSO evaluated the financial proposals on 4 April 2011. Contract negotiations were held on 4-5 May 2011. Engagement commenced on 9 May 2011 and will be completed by 23 Dec 2011.

In August 2011, the Consultant's ToR was expanded to include tests and analysis to determine the status of the 500kV low pressure oil-filled cable of the Toktogul Hydropower Plant. The said cable was cross-linked to a polyethylene cable which is said to have exhausted its economic life.

In May 2012, the Consultant's ToR was further expanded to assist the EA in the (i) preparation of a full set of bidding documents (commercial and technical) for Toktogul HPP rehabilitation; (ii) conduct a rapid dam safety assessment; and (iii) preparation of ToR for Project Implementation Consultant to implement Dam Safety Monitoring.

Responsible Staff

Responsible ADB Officer Jim Liston
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Energy Division, CWRD
Executing Agencies
Ministry of Energy and Industry
119 Ahunbaev Street
Bishkek, 7200
Kyrgyz Republic

Timetable

Concept Clearance 10 Dec 2010
Fact Finding 19 Mar 2013 to 26 Mar 2013
MRM -
Approval -
Last Review Mission -
Last PDS Update 16 Nov 2012

TA 7704-KGZ

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
15 Dec 2010 28 Jan 2011 28 Jan 2011 30 Nov 2011 30 Nov 2012 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
1,000,000.00 0.00 100,000.00 0.00 0.00 0.00 1,100,000.00 15 Dec 2010 776,111.13

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.