The CDTA will contribute to the impact of sustainable use of forest resources in HOB Indonesai by strengthening the mahgment capacity of GOI on natural resources managment. This impact will be measured by the following indicators: (i) expansion of forest cover; (ii) improvement in the proportion of timber produced from sustainable tree plantations relative to the volume sourced from wild stock; and (iii) reduction in carbon dioxide emission.

The outcome of the Project is improved management of natural resources in the HOB Indonesia. Improvements in management will be reflected by the following indicators: (i) additional one million hectares of protected area established; (ii) strengthened capacity for sustainable forest and biodiversity management at the national, provincial, and district HOB Working Groups as reflected by greater coordination and cooperation among levels; and (iii) completed protection forest plans in four districts.

Latest Project Documents

Consulting Notices

See also: CMS

No notices are currently available for this project.

Procurement Notices

See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents

None currently available.


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Sustainable Forest and Biodiversity Management in Borneo
Project Number 44413-012
Country Indonesia
Project Status Approved
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 8331-INO: Sustainable Forest and Biodiversity Management in Borneo
Climate Change Fund US$ 1.25 million
Regional Cooperation and Integration Fund US$ 700,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Partnerships
Sector / Subsector

Agriculture, natural resources and rural development - Land-based natural resources management

Gender Equity and Mainstreaming No gender elements
Description

The CDTA will contribute to the impact of sustainable use of forest resources in HOB Indonesai by strengthening the mahgment capacity of GOI on natural resources managment. This impact will be measured by the following indicators: (i) expansion of forest cover; (ii) improvement in the proportion of timber produced from sustainable tree plantations relative to the volume sourced from wild stock; and (iii) reduction in carbon dioxide emission.

The outcome of the Project is improved management of natural resources in the HOB Indonesia. Improvements in management will be reflected by the following indicators: (i) additional one million hectares of protected area established; (ii) strengthened capacity for sustainable forest and biodiversity management at the national, provincial, and district HOB Working Groups as reflected by greater coordination and cooperation among levels; and (iii) completed protection forest plans in four districts.

Project Rationale and Linkage to Country/Regional Strategy The CDTA is part of ADB's support to the BIMP-EAGA. This support is key to the implementation of ADB's regional cooperation and integration strategy. In particular, the CDTA will assist the GOI in implementing its NSPA for the HOB and in carrying out the HOB Tri-Country Plan of Action as part of its cooperative arrangement with Brunei Darussalam and Malaysia. The project responds to the call of the ASEAN to protect the HOB in recognition of its role as the depository of the region's biodiversity and carbon sink and as a platform for honoring regional (e.g., ASEAN resolutions and agreements on sustainable development, wildlife trade, and transborder environmental pollution) and international commitments (e.g., Convention of Biological Diversity and Millennium Development Goals). Since 1997, ADB has been supporting efforts of the ASEAN to improve environmental quality at the regional level. At the national level, the CDTA supports ADB's strategy for strengthening environmental and natural resources management in Indonesia. Specifically, the CDTA is closely linked to ADB's strategy for improved environmental governance through institutional restructuring, policy strengthening, and legal development as well as support for building enhanced capability and transparency.
Impact Sustainable use of forest resources in the HOB Indonesia
Project Outcome
Description of Outcome Improved management of forest resources and biodiversity in four districts in HOB Indonesia
Progress Toward Outcome --
Implementation Progress
Description of Project Outputs

1. Strengthen capacity and institutions for sustainable forest and biodiversity management

2. Exercise the REDD+ implementation at local level

3. Pilot area for PES and sustainable financing schemes for forest and biodiversity management

4. Effective project management delivered

Status of Implementation Progress (Outputs, Activities, and Issues) The project implementation will start on mobilization of the Project Management Consultant expected to commence in third week of September 2015.
Geographical Location
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design ADB consulted with GOI; the Indonesian HOB Technical Working Group, provincial, district and local governments; and development partners.
During Project Implementation Stakeholder consultations in West and North Kalimantan have been carried out in May and June 2015 to orient national and local governments on project activities and confirm priority interventions.
Business Opportunities
Consulting Services

The Project will require 39 person-months of international and 130 personmonths

of national consulting services or a total of about 169 person-months. The consultants (through

an international consulting firm that will serve as PMC) will be engaged by ADB in accordance with the

Guidelines on the Use of Consultants (2010, as amended from time to time). The PMC will be chosen

using quality- and cost-based selection method (80:20), following the Guidelines on the Use of

Consultants and Its Borrowers (2010, as amended from time to time). It will provide technical and

management services over the duration of the Project. It will be headed by a team leader, who will

oversee the overall implementation of the Project, including field operations that are coordinated and

managed by the project implementation units. The PMC, with ADB and executing agency concurrence,

will select qualified local nongovernment organizations, academic and research institutions, or other

specialized institutions to undertake specific project activities, such as the conduct of pilot PES

mechanisms, REDD+ demonstrations, etc.

Responsible ADB Officer Pantja Putih Wardani
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Indonesia Resident Mission
Executing Agencies
Directorate of Env'mental Srvs &Conservation_Areas
Jl. Ir. Ir. H. H. Juanda No. No. Juanda,
15 Bogor, Bogor, Indonesia
Timetable
Concept Clearance 30 Sep 2010
Fact Finding 28 Feb 2011 to 13 Mar 2011
MRM -
Approval 26 Feb 2013
Last Review Mission -
Last PDS Update 14 Sep 2015

TA 8331-INO

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
26 Feb 2013 26 Mar 2014 26 Mar 2014 31 Aug 2016 28 Feb 2018 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
1,950,000.00 0.00 0.00 0.00 0.00 0.00 1,950,000.00 26 Feb 2013 113,075.50
Title Document Type Document Date
Sustainable Forest and Biodiversity Management in Borneo Technical Assistance Reports Feb 2013

Safeguard Documents

See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents

See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

  • 27 Feb 2013 | Article

    Heart of Borneo: Saving Forests in Southeast Asia

    ADB is partnering with WWF and the governments of Brunei Darussalam, Indonesia and Malaysia to conserve the lush forests of Borneo, providing sustainable livelihood for local populations and a safe haven for thousands of animals and plant species. The Heart of Borneo (HoB), which straddles Indonesia, Malaysia, and parts of Brunei, contains the largest contiguous forest area remaining in Southeast Asia and is one of the most biologically diverse habitats on Earth.
  • 27 Feb 2013 | Infographic

    Protecting Borneo's Heart

    The lush forests of the world’s third largest non-continental island - among the fast-shrinking band of forests functioning as the earth’s lungs - are being conserved to provide sustainable livelihood for local populations and a safe haven for thousands of animal and plant species.