India: Green Energy Corridor and Grid Strengthening Project

Sovereign Project | 44426-016 Status: Approved

Summary

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Green Energy Corridor and Grid Strengthening Project
Project Number 44426-016
Country India
Project Status Approved
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3365-IND: Green Energy Corridor and Grid Strengthening Project
Ordinary capital resources US$ 500.00 million
Loan: Green Energy Corridor and Grid Strengthening Project
KfW Bankengruppe US$ 625.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Partnerships
Private sector development
Sector / Subsector

Energy - Electricity transmission and distribution

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location

Safeguard Categories

Environment B
Involuntary Resettlement B
Indigenous Peoples C

Summary of Environmental and Social Aspects

Environmental Aspects Effective measures to avoid, minimize, mitigate, and compensate for the adverse environmental impacts are incorporated in the initial environmental examination, which includes the environmental management plan. Environmental impacts of transmission lines are mostly localized to the right-of-way and can be minimized by careful route selection.
Involuntary Resettlement For the transmission towers and lines, impacts are temporary and will occur during construction in terms of loss of crops and trees which will be compensated. Effective measures to avoid, minimize, mitigate, and compensate for the adverse impacts are incorporated in the relevant documents.
Indigenous Peoples Category C
Stakeholder Communication, Participation, and Consultation
During Project Design Project was cleared by Government of India for Asian Development Bank to undertake due diligence after inter-ministry consultations in 2014. Powergrid has conducted public consultations in applicable project areas and consulted with other stakeholders.
During Project Implementation Stakeholder consultation is an ongoing process and will continue during project implementation.

Business Opportunities

Consulting Services Project implementation consultants are not envisaged.
Procurement Powergrid is the executing and implementing agency. A project management unit is in place, headed by a project director. Goods, equipment and civil works to be financed by the ADB loan will be procured in accordance with ADB Procurement Guidelines (2015, as amended from time to time). International competitive bidding (ICB) will be used for civil works and turnkey contracts. Advanced contracting and/or retroactive financing are envisaged.

Responsible Staff

Responsible ADB Officer Kazuhiro Enomoto
Responsible ADB Department South Asia Department
Responsible ADB Division Energy Division, SARD
Executing Agencies
Power Grid Corporation of India Limited
PGCIL@VSNL.COM.
SAUDAMANI
Plot No. 2, Sector - 29
Gurgaon - 122 001 Haryana, India

Timetable

Concept Clearance 25 Jun 2014
Fact Finding 01 Jun 2015 to 11 Jun 2015
MRM 22 Sep 2015
Approval 09 Dec 2015
Last Review Mission -
Last PDS Update 10 Mar 2016

Loan 3365-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
09 Dec 2015 - - 30 Jun 2021 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 2,581.30 Cumulative Contract Awards
ADB 500.00 09 Dec 2015 0.00 0.00 0%
Counterpart 2,081.30 Cumulative Disbursements
Cofinancing 0.00 09 Dec 2015 0.00 0.00 0%

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.