44482-024: Transport Network Development Investment Program - Tranche 3 | Asian Development Bank

Afghanistan: Transport Network Development Investment Program - Tranche 3

Sovereign (Public) Project | 44482-024 Status: Active

ADB is helping Afghanistan upgrade its transport network. The third tranche of the program will rebuild 178 kilometers of a national road from Dar-i-Suf to Yakawlang, which will provide an alternative north-south transit route from from Mazar-e-Sharif to Kabul. It will also improve sanitation facilities and practices in Bamyan and Samangan provinces, which particularly benefit women and children.

 
Project Name Transport Network Development Investment Program - Tranche 3
Project Number 44482-024
Country Afghanistan
Project Status Active
Project Type / Modality of Assistance Grant
Source of Funding / Amount
Grant 0355-AFG: Transport Network Development Investment Program - Tranche 3
concessional ordinary capital resources lending / Asian Development Fund US$ 220.00 million
Strategic Agendas Inclusive economic growth
Regional integration
Drivers of Change Gender Equity and Mainstreaming
Governance and capacity development
Sector / Subsector

Transport / Road transport (non-urban)

Gender Equity and Mainstreaming Effective gender mainstreaming
Description Physical interventions under Tranche 3 include 178 km of reconstructed national road from Dar-i-Suf to Yakawlang linking the roads already completed under the ADB financed North South Corridor Project. Completion of this national road provides an alternative north south transit route from Mazar-e-Sharif to Kabul from the currently overloaded Salang Tunnel, a facility which has exceeded its engineering design life and is in need of major rehabilitation if it is going to continue to function. Additionally, Tranche 3 will provide community infrastructure specifically designed to improve the lives of women and children in some of Afghanistan's poorest provinces, Bamyan and Samangan, through betterment of sanitation facilities and practices.
Project Rationale and Linkage to Country/Regional Strategy As planned in the approved facility and linked documents, Tranche 3 of the investment program builds upon the lessons learned and progress from Tranches 1 and 2, and the complementary efforts of other development partners in the sector to further improve domestic and regional connectivity while widening access to social and economic opportunities. The proposed road subproject involves the reconstruction and upgrading of approximately 178 kilometers (km) of the road section from Dar-i-Suf to Yakawlang, which has been previously identified as a priority in the Afghanistan National Development Strategy (ANDS) and subsequent national planning and implementation frameworks. The rationale for the proposed subproject include: (i) completing the North South Corridor, which is an alternative route to using the Salang Tunnel; (ii) supporting completion of CAREC Corridor 5; and (iii) completing the first stage in cross country north south road from Mazar-e-Sharif to Kandahar. After years of use and lack of periodic maintenance, the subproject road in poor condition beyond repair, thus requiring major rehabilitation. Indeed, in its current condition, the road is impassable by motorized vehicles for many months throughout the year. This state of this road is hindering economic development in the central provinces, impeding regional trade and the opening of alternative trade routes, and imposing efficiency losses as traffic volumes continue to rise. In addition to supporting the ANDS, justification of Tranche 3 stems from Afghanistan's strategic geographic center of gravity in the Central Asian region and potential to serve as the nexus between north-south and east-west regional trade corridors. Afghanistan is traversed by three major CAREC corridors, to which the proposed Tranche 3 subproject supports Corridor 5 providing landlocked Central Asian access to populous commercial centers in South Asia, and major ports in the Persian Gulf and Arabian Sea. An efficient and sustained Afghanistan road network will improve regional connectivity, support increased domestic and international trade, and generate jobs and economic growth. The proposed tranche is consistent with the envisaged outputs, outcomes, and impacts of the investment program and additionally Strategy CAREC 2020 aimed at the development of priority transport routes, increasing trade through transport connectivity, and facilitating cross-border movement of goods.
Impact Better connectivity and efficiency through a fully complete North-South Corridor
Project Outcome
Description of Outcome Rehabilitated and reconstructed sections of national and regional highways
Progress Toward Outcome

Civil works contract for the reconstruction of Dara-i-Suf to Yakawlang (178 km) Road was signed on 31 December 2016. Contractor mobilized on 15 May 2017.

The contract for construction supervision consultant was signed on 15 May 2017.

Recruitment of construction supervision consultant and feasibility consultant for Kabul Ring Road is currently on hold.

Implementation Progress
Description of Project Outputs

178 km (Dar-i-Suf-Yakawlang section of the North-South Corridor) of reconstructed, rehabilitated, and appropriately maintained national and regional highways

Community development infrastructure

Status of Implementation Progress (Outputs, Activities, and Issues)

The civil work procurement has been delayed because of the high bid prices. The civil work contract (China Road & Bridge Corporation) was signed on 31 December 2016. The project was officially inaugurated on 15 May 2017 and the civil works contractor started moblization.

The contract for construction supervision consultant (Sheladia Associate Inc, USA) was signed on 15 May 2017.

Recruitment of feasibility consultant for Kabul Ring Road may be cancelled but the government has not provided an official request.

Construction of camp is ongoing. Working drawings for section K0-K43+300 is about 90% completed and for section K113-K186+240 is about 35% completed.

Assessment will be made at the physical completion of the project.

Not yet started.

Not yet started.

Not yet started.

Geographical Location Ahangaran, Baghalak, Bazar-e Yakawlang, Chaghcharan, Chaghcharan, Chahar Deh, Dara-I-Suf, Darah-ye Daymirdad, Deh-e Tarchi, Gardan Dewal, Gird Bayd, Hasani, Hisa-I-Awal Bihsud, Islamic Republic of Afghanistan, Kabul, Kotah, La`l wa Sar Jangal, Marghistan, Markazi Bihsud, Panjab, Qal`ah, Qal`ah Now, Rashak, Sadmardah, Safed Khak, Sar-e Bum, Surkh Joy, Yakawlang, Zayraki
Safeguard Categories
Environment B
Involuntary Resettlement A
Indigenous Peoples C
Summary of Environmental and Social Aspects
Environmental Aspects The road will not pass through any environmentally sensitive areas and rehabilitation activities will be confined with the existing ROW. The project is anticipated to have site specific environmental impacts. A further environmental assessment will re-confirm whether environment category B will be maintained.
Involuntary Resettlement Expected significant land acquisition and resettlement as defined by SPS (2009). Land acquisition process is ongoing.
Indigenous Peoples N/A
Stakeholder Communication, Participation, and Consultation
During Project Design Consultation sessions were conducted with the local residents in the project affected areas. The primary issues discussed were affected land, the process of land acquisition planning, compensation, and employment opportunities for the local residents, both skilled and unskilled. The benefits of constructing the projects roads were explained. The community development subcomponent will involve collaborative decision making and empowerment elements.
During Project Implementation Consultation sessions will continue during project implementation.
Business Opportunities
Consulting Services All consulting services financed under Tranche 3 will be procured in accordance with the Guidelines on The Use of Consultants by Asian Development Bank and Its Borrowers (2013, as amended from time to time).
Procurement Procurement of all civil works, equipment and goods will be undertaken in accordance with ADB's Procurement Guidelines (2015, as amended from time to time).
Responsible ADB Officer Mohibi, Neak Mohammad
Responsible ADB Department Central and West Asia Department
Responsible ADB Division Afghanistan Resident Mission
Executing Agencies
Ministry of Public Works
First Macrorayan
Kabul,
Islamic Republic of Afghanistan
Timetable
Concept Clearance -
Fact Finding -
MRM 16 Jul 2013
Approval 11 Sep 2013
Last Review Mission -
Last PDS Update 26 Sep 2017

Grant 0355-AFG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
11 Sep 2013 09 Nov 2013 03 Jan 2014 31 Dec 2017 31 Dec 2019 -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 230.00 Cumulative Contract Awards
ADB 220.00 11 Sep 2013 213.78 0.00 97%
Counterpart 10.00 Cumulative Disbursements
Cofinancing 0.00 11 Sep 2013 20.50 0.00 9%

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

Contract Title Approval Number Contract Date Contractor Contractor Address Executing Agency Contract Description Total Contract Amount (US$) Contract Amount Financed by ADB (US$)
Construction Supervision of the Reconstruction and Rehabilitation of North South Corridor Road Project Grant 0355 15 May 2017 Sheladia Associates Inc. 15825 Shady Grove Road Suite 100 Rockville Md United States Ministry of Public Works Construction Supervision of the Reconstruction and Rehabilitation of North South Corridor Road Project 8786627
Construction Supervision Of The Reconstruction And Rehabilitation Of North South Corridor Road Proj Grant 0355 15 May 2017 Sheladia Associates Inc. 15825 Shady Grove Road Suite 100 Rockville Md United States Ministry Of Public Works 8786627