Regional: Strengthening Public Procurement Management and Portfolio Performance

Sovereign Project | 44502-001

Summary

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Strengthening Public Procurement Management and Portfolio Performance
Project Number 44502-001
Country Regional
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 7752-REG: Strengthening Public Procurement Management and Portfolio Performance
Technical Assistance Special Fund US$ 225,000.00
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector Public sector management - Public expenditure and fiscal management
Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact Improved portfolio performance in public procurement operation and practice
Project Outcome
Description of Outcome Strengthened institutional capacity in public procurement
Progress Toward Outcome
Implementation Progress
Description of Project Outputs

E-government procurement system developed.

Annual action plan developed for public procurement reform and policy at the national level.

Technical issues in public procurement and necessary actions identified at the regional or national level.

Harmonization and knowledge sharing done with other development partners

PEs and private sectors trained on e-GP.

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design Consultation with government agencies held.
During Project Implementation Consultaion with Public Procurement Monitoring Office is underway to recruit the consulting firm.
Business Opportunities
Consulting Services

Consultants for a total of 25 person-months will be recruited through a firm using the single source section method.

International e-Government Procurement Specialist (1 for 2 person-months)

Ntional Consultants (23 person-months) will be as follows:

(i) e-GP System Analyst and Team Leader,

(ii) IT Expert in Web-based Application,

(iii) IT Expert in relational database management system/database administration (RDBMS/BDA),

(iv) Web Developers (two), and

(v) System Integration Specialist.

Responsible ADB Officer Raju Tuladhar
Responsible ADB Department South Asia Department
Responsible ADB Division Nepal Resident Mission
Executing Agencies
Asian Development Bank6 ADB Avenue, Mandaluyong
Metro Manila, Philippines
P.O. Box 789, 1099 Manila,
Philippines
Timetable
Concept Clearance 31 Mar 2011
Fact Finding 31 Mar 2011 to 13 Apr 2011
MRM -
Approval 16 Dec 2010
Last Review Mission -
Last PDS Update 28 Feb 2011

TA 7752-REG

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
16 Dec 2010 - 16 Dec 2010 31 Dec 2011 31 Dec 2012 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
225,000.00 0.00 0.00 0.00 0.00 0.00 225,000.00 16 Dec 2010 200,878.95

Safeguard Documents

See also: Safeguards

No documents found.

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.