44946-014: NONG SAENG NATURAL GAS POWER PROJECT

Project Data Sheet (PDS): Overview


Description

The Project entails the construction of a 1,600-megawatt combined cycle power plant in Nong Saeng district, Saraburi Province, 120 km north of Bangkok. The Project will be developed and implemented under a 25-year power purchase agreement (PPA) with the Electricity Generation Authority of Thailand (EGAT), and a 25-year gas supply agreement (GSA) with PTT Public Company Limited (PTT). Project costs and fuel are passed through the ofttake agreement. The Project is a public-private partnership (PPP) under the Independent Power Producers (IPP) program, that utilizes commercial energy from power plants with capacities greater than 90 MW. An interconnecting pipeline from the plant will connect to PTT's existing Wangnoi-Kaengkoi transmission pipeline 20 kilometers away. A new transmission line will also be constructed to connect to EGAT's system 1.5 kilometers away. Read More

Country Thailand
Borrower/Equity Investment Name GULF JP NS COMPANY LIMITED
Project Number 44946-014
Project Type or Modality of Assistance PS
Financing Private sector (Nonsovereign)
Status Approved
Approval Number 7335
Approval Date 07 Jul 2011
Closing Date 27 May 2015
Geographical Location Saraburi Province, Thailand
Sector / Subsector Classification Energy
/ Conventional Energy
Thematic Classification Economic growth
Not yet classified
Private sector development
Safeguard Categories Environment: A
Resettlement: C
Indigenous People: C

 

 

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Data Sheets (PDS)

Responsible ADB Officer
Daniel Wiedmer
Email contact

Responsible ADB Department
Private Sector Operations Department

Responsible ADB Divisions
Infrastructure Finance Division 2

PDS Creation Date
07 Jan 2011

Last PDS Update
16 Sep 2013