Viet Nam: Project Preparation and Startup Support Facility

Sovereign Project | 45098-001 Status: Active

Summary

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Project Preparation and Startup Support Facility
Project Number 45098-001
Country Viet Nam
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 2982-VIE: Project Preparation and Startup Support Facility
Asian Development Fund US$ 37.88 million
Strategic Agendas Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector

Public sector management - Economic affairs management

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome

First application of $13 million for Metro Line 5 approved by ADB and MPI for consulting service package for Frond End Engineering Design (QCBS).

The project team is discussing with MPI on potential candidates to use the remaining funds under PPSSF.

Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues) Sub-loan agreement of the engineering design for Metro Line 5 was signed between HCMC and MOF and Project agreement was signed between HCMC and MPI. Submission 0 is being finalized and also under DOT review. The PMU of Metro Line 5 project expects to advertise this package by end March 2016. Contract award is expected in Q1 of 2017.
Geographical Location

Summary of Environmental and Social Aspects

Environmental Aspects There is no impact
Involuntary Resettlement There is no impact
Indigenous Peoples There is no impact
Stakeholder Communication, Participation, and Consultation
During Project Design Facility is used to finance project preparation and start-up activities
During Project Implementation Facility is used to finance project preparation and start-up activities

Business Opportunities

Consulting Services

1- Consulting Services for Capacity Development:

ICS (intenational) - 40 person-months

Amount: $1,040,000

ICS (national) - 740 person months

Amount: $2,260,000

Consultation Qualification Selection or Least Cost Selection - 1 contract for audit services

Amount: $100,000

2- Consulting Services for Preparation of Subprojects

Firm and/or individual consultant selection - to be determined during implementation

Amount: to be determined during implementation

Procurement

Shopping

2 Contracts for information technology equipment and office furniture

Amount: $20,000

Responsible Staff

Responsible ADB Officer Hoang Do
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Viet Nam Resident Mission
Executing Agencies
Ministry of Planning and Investment
6 B Hoang Dieu street, Ba Dinh district, Hanoi, Viet Nam

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
Last PDS Update 30 Mar 2016

Loan 2982-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
13 Dec 2012 07 Mar 2013 19 Jun 2013 30 Jun 2020 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 40.38 Cumulative Contract Awards
ADB 37.88 13 Dec 2012 1.35 0.00 4%
Counterpart 2.50 Cumulative Disbursements
Cofinancing 0.00 13 Dec 2012 2.00 0.00 6%

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.