45200-002: Sustainable Urban Transport for Ho Chi Minh Mass Rapid Transit Line 2

Project Data Sheet (PDS): Financing


Type/Modality of Assistance Approval Number Source of Funding Approved Amount (thousand)
Loan3113Asian Development Fund10,000
Loan8279ADB Clean Technology Fund48,950
Counterpart 6,050
TOTAL US$ 65,000

Milestones

Approval No. Approval Signing Effectivity Closing
Original Revised Actual
Loan 3113 20 Feb 2014 18 Jul 2014 30 Jun 2020
Loan 8279 20 Feb 2014 18 Jul 2014 30 Jun 2020

Utilization

Date Approval Number ADB (US$ thousand) Others (US$ thousand) Net Percentage
Cumulative Contract Awards
01 Oct 2014 Loan 3113 0 0 0.00%
01 Oct 2014 Loan 8279 0 0 0.00%
Cumulative Disbursements
01 Oct 2014 Loan 3113 0 0 0.00%
01 Oct 2014 Loan 8279 0 0 0.00%



Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.