Philippines: Angat Water Transmission Improvement Project

Sovereign Project | 46362-001

Summary

The Project will secure raw water supply to the 13 million inhabitants of Metropolitan Waterworks and Sewerage System (MWSS) service area, through the rehabilitation of the Angat transmission line. It is estimated that currently each day about 800,000 m3 or 20% of the total potential capacity of raw water is lost , due to leakage of the aqueducts . The main components of the Angat transmission line are as old as 50 years, in poor condition, and not in compliance with structural and seismic requirements, risking the partial interruption of Metro Manila's water supply.

The impact of the Project is sustained and secured water supply from the Angat reservoir. The outcome is the sustained operation of the aqueducts, to be achieved by (i) retrofitting, rehabilitating and/or re-construction of the aqueducts; and (ii) operationalization of an integrated water safety, risk- and asset management plan.

Latest Project Documents

Consulting Notices

See also: CMS

No notices are currently available for this project.

Procurement Notices

See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents

No documents of this type are currently available for this project.


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Angat Water Transmission Improvement Project
Project Number 46362-001
Country Philippines
Project Status Approved
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 8169-PHI: Angat Water Transmission Improvement Project
Technical Assistance Special Fund US$ 800,000.00
TA: Angat Water Transmission Improvement Project (Supplementary)
Technical Assistance Special Fund US$ 140,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Private sector development
Sector / Subsector

Water and other urban infrastructure and services - Urban water supply

Gender Equity and Mainstreaming Some gender elements
Description

The Project will secure raw water supply to the 13 million inhabitants of Metropolitan Waterworks and Sewerage System (MWSS) service area, through the rehabilitation of the Angat transmission line. It is estimated that currently each day about 800,000 m3 or 20% of the total potential capacity of raw water is lost , due to leakage of the aqueducts . The main components of the Angat transmission line are as old as 50 years, in poor condition, and not in compliance with structural and seismic requirements, risking the partial interruption of Metro Manila's water supply.

The impact of the Project is sustained and secured water supply from the Angat reservoir. The outcome is the sustained operation of the aqueducts, to be achieved by (i) retrofitting, rehabilitating and/or re-construction of the aqueducts; and (ii) operationalization of an integrated water safety, risk- and asset management plan.

The Project will finance the (i) rehabilitation and/or reconstruction of the aqueducts, and (ii) technical assistance to (a) assess structural and seismic integrity of the transmission system; (b) prepare water safety, risk- and asset management plans, covering the optimization of the system; (c) prepare designs of structural and non-structural measures to support the implementation of these plans; and (d) prepare subsequent investments. These investments may include rehabilitation and retrofitting of intakes, stilling basins and the remaining aqueducts.

Project Rationale and Linkage to Country/Regional Strategy

Leakage reduction.

Provision of water supply and sanitation in Metro Manila (Manila) is the responsibility of MWSS, a government-owned corporation. In 1997, it awarded two concession contracts to private firms for water distribution. MWSS retained responsibility for bulk water supply. Manila's main water supply source is the Angat reservoir , which provides about 97% of Manila's water supply . Water from the reservoir is conveyed through a system of tunnels and aqueducts to water treatment plants in Manila. The treated water is then distributed to households, businesses, and industries in Manila, and parts of Cavite and Rizal.

The demand on the Angat water source is about 4.48 million m3/day, and is slightly decreasing from 2010 to 2015, as result from the very successful nonrevenue water (NRW) reduction programs of the concessionaires. However, following 2015, the demand will increase rapidly due to expected water supply area expansion and population growth. The demand is expected to increase by 38% in 2025, to 6.16 million m3/day

About 15 years ago, MWSS recognized the need to rehabilitate the aqueducts. At that time, the total potential transport capacity of the Angat transmission system, consisting of three parallel tunnels and five parallel aqueducts, was 4.76 million m3/day. However, the actual capacity was about 30% less, due to the high leakage rate especially of aqueduct number 5. To rehabilitate aqueduct number 5, MWSS built a new parallel aqueduct (number 6) in two phases: first bypassing the upstream part of aqueduct number 5, completed in 2003, followed by bypassing the downstream part, completed in July 2012. The current capacity of the system, without aqueduct number 5, is sufficient to match the projected 2015 demand.

In order to match 2025 demand, it is essential to rehabilitate to full capacity (i) aqueduct number 5, bringing potential transport capacity to 6.22 million m3/day; and (ii) the other four aqueducts, bringing potential transport capacity to 6.45 million m3/day. Besides restoring the transport capacity of the aqueducts, potential other bottlenecks will need to be identified and addressed, such as the limited capacity of the tunnels and the general configuration of the whole system.

Disaster risk management.

Besides rehabilitation to restore capacity, the aqueducts need to be reinforced to restore their structural integrity, reducing the risk of complete collapse, possibly due to earthquake damage. This is especially true for aqueducts number 1 and 2 which were commissioned in 1948. In addition, a proper risk assessment will be carried out, and risk management, asset management and water safety plans will be prepared.

Impact
Project Outcome
Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design MWSS and water concessionaires
During Project Implementation MWSS and water concessionaires
Business Opportunities
Consulting Services International consulting firm will be recruited to prepare the project
Responsible ADB Officer Paulus B. van Klaveren
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Urban Development and Water Division, SERD
Executing Agencies
Metropolitan Waterworks and Sewerage System4th Floor, Administration Bldg.,
MWSS Complex, Katipunan Road, Balara
Quezon City 1105, Philippines
Timetable
Concept Clearance -
Fact Finding -
MRM -
Approval 13 Sep 2012
Last Review Mission -
Last PDS Update 27 Jan 2014

TA 8169-PHI

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
13 Sep 2012 18 Oct 2012 18 Oct 2012 31 Jul 2013 31 May 2015 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
800,000.00 0.00 0.00 0.00 0.00 0.00 800,000.00 13 Sep 2012 816,125.54
Title Document Type Document Date
Angat Water Transmission Improvement Project Initial Poverty and Social Analysis Jun 2013
Angat Water Transmission Improvement Project Technical Assistance Reports Jun 2013

Safeguard Documents

See also: Safeguards

No documents found.

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.