Viet Nam: Ha Noi and Ho Chi Minh City Power Grid Development Sector Project

Sovereign Project | 46391-001 Status: Active

Summary

ADB is supporting Viet Nam’s drive for more efficient, sustainable power supply from the country’s key electricity networks in its largest cities, Ha Noi and Ho Chi Minh. The project, which is cofinanced with a loan from the ASEAN Infrastructure Fund, will upgrade substations, increase transformer capacity, and expand 110 kilovolt and 220 kilovolt transmission lines.

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Ha Noi and Ho Chi Minh City Power Grid Development Sector Project
Project Number 46391-001
Country Viet Nam
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3161-VIE: Ha Noi and Ho Chi Minh City Power Transmission Development Sector Project
Ordinary capital resources US$ 172.70 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Partnerships
Sector / Subsector

Energy - Electricity transmission and distribution

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome Several procurement packages under: a) four core subprojects (1 for EVN Hanoi and 3 for EVN HCMC) and b) ten non-core subprojects (7 from EVN Hanoi and 3 from EVN HCMC) have been approved with various works and goods contracts awarded.
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)

1. Bidding documents for two core subprojects in Ha Noi have been initiated and issued beginning in 2014 with seven procurement packages awarded. Bidding documents for the two other core subprojects will be issued shortly after completion of the detailed technical designs.

2. Bidding documents for all four core subprojects in HCMC have been initiated in 2015 with three procurement contracts awarded under two subprojects.

3. Seven non-core subprojects in Ha Noi have been approved and are at various stages of implementation.

4. Three non-core subprojects in HCMC have been approved and are at various stages of implementation.

Geographical Location

Summary of Environmental and Social Aspects

Environmental Aspects Environmental impacts and mitigation/monitoring measures have been assessed under the PPTA.
Involuntary Resettlement Involuntary resettlement impacts and mitigation/monitoring measures have been assessed under the PPTA.
Indigenous Peoples Indigenous peoples are not involved.
Stakeholder Communication, Participation, and Consultation
During Project Design Project stakeholders were consulted during project design.
During Project Implementation Throughout the implementation of all subprojects, consultation with local governments, local communities, non-governmental organizations and other stakeholders will be done.

Business Opportunities

Consulting Services Individual Consultant Selection (ICS) was adopted in contracting consulting services.
Procurement

All procurement of goods and services under the ADB financing will be undertaken in accordance with ADB's Procurement Guidelines and the procurement plan for the project.

To ensure competitive bidding, international competitive bidding contract packages will be adopted. International competitive bidding will be used for Goods over $3 million and for Works over $5 million. ADB's prior review procedures will be followed. The Borrower agreed to include the relevant sections of ADB's Anticorruption Policy (1998) in all bidding and contractual documents. Installation and commissioning works will be undertaken by contractors through national competitive bidding (NCB).

Responsible Staff

Responsible ADB Officer Tuan Au
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Viet Nam Resident Mission
Executing Agencies
Hanoi Power Corporation
DAOQUANGMINHDLHT@YAHOO.COM.VN
69 Dinh Tien Hoang Street, Hoan Kiem District
Ha Noi, Viet Nam
Ho Chi Minh City Power Corporation
BAOPQ@HCMPC.COM.VN
35 Ton Duc Thang Street, Ben Nghe Ward District 1

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
Last PDS Update 28 Mar 2016

Loan 3161-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
23 Sep 2014 07 Nov 2014 06 Feb 2015 31 Dec 2020 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 294.27 Cumulative Contract Awards
ADB 172.70 23 Sep 2014 18.86 0.00 11%
Counterpart 121.57 Cumulative Disbursements
Cofinancing 0.00 23 Sep 2014 11.09 0.00 6%

Loan 8286-VIE

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
23 Sep 2014 07 Nov 2014 06 Feb 2015 31 Dec 2020 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 0.00 Cumulative Contract Awards
ADB 0.00 23 Sep 2014 0.00 10.90 11%
Counterpart 0.00 Cumulative Disbursements
Cofinancing 0.00 23 Sep 2014 0.00 6.35 6%

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
HN and HCMC PGDSP - 110 kV HCMC Thu Duc Water Plant Substation and Connection Line: Initial Environmental Examination Initial Environmental Examination Jun 2016
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project - 110 kV Thuong Tin-Thanh Oai Transmission Line: Initial Environmental Examination Initial Environmental Examination Apr 2016
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project - EVN HCMC Thu Duc Subproject: Resettlement Due Diligence Report Safeguards Due Diligence Reports Apr 2016
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: 110 kV Thuong Tin-Thanh Oai Transmission Line Resettlement Plan Resettlement Plans Mar 2016
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project - 110 kV Phu Nghia Substation and Transmission Line: Initial Environmental Examination Initial Environmental Examination Mar 2016
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: 110 kV Phu Nghia Substation and Connection Line Subproject Resettlement Plan Resettlement Plans Mar 2016
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project - EVN HCMC-Tham Luong Substation Subprojects: Resettlement Due Diligence Report Safeguards Due Diligence Reports Feb 2016
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project - 110 kV Phước Long Substation and Connecting Line: Initial Environmental Examination Initial Environmental Examination Jan 2016
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project - 110 kV Tân Hưng Substation and Connecting Line, Stage 2: Initial Environmental Examination Initial Environmental Examination Jan 2016
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Second Stage 110kV Tân Hưng Substation and Connecting Line - Resettlement Due Diligence Report Safeguards Due Diligence Reports Jan 2016
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: 220-110kV Cau Bong - Binh Tan Transmission Line - Resettlement Plan Resettlement Plans Dec 2015
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: 220-110kV Cau Bong-Binh Tan Transmission Line - Initial Environmental Examination Initial Environmental Examination Nov 2015
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Resettlement Framework Resettlement Frameworks Oct 2015
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Third Transformer Bank at 110 kV Thanh Xuan Substation - Resettlement Due Diligence Report Safeguards Due Diligence Reports Jun 2015
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Thanh Xuan 110kV Substation Initial Environmental Examination Initial Environmental Examination Jun 2015
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Thuong Dinh 110kV Substation Initial Environmental Examination Initial Environmental Examination Jun 2015
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: 110kV Phước Long Substation and Connecting Line - Resettlement Due Diligence Report Safeguards Due Diligence Reports May 2015
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Resettlement Due Diligence Report - Expansion of Thuong Dinh Substation Safeguards Due Diligence Reports Apr 2015
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project - Chem-Tay Ho 220kV Transmission Line: Resettlement Plan (March 2015) Resettlement Plans Mar 2015
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Resettlement Due Diligence Report Safeguards Due Diligence Reports Mar 2015
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Chem-Tay Ho 220kV Transmission Line Resettlement Plan Resettlement Plans Jun 2014
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Mo Lao 110kV Substation and Transmission Line Initial Environmental Examination Initial Environmental Examination Jun 2014
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project - 110 kV Noi Bai Airport Substation and Associated 110 kV Transmission Line (June 2014): Resettlement Plan Resettlement Plans Jun 2014
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Transmission line 220/110kV Chem-Tay Ho Initial Environmental Examination Initial Environmental Examination Jun 2014
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Mo Lao 110kV Substation and 110kV Connection Resettlement Plan Resettlement Plans Jun 2014
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project Resettlement Frameworks Feb 2014
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Rehabilitation and Renovation of Son Tay, Phuong Liet, and Tran Hung Dao 110 kV Substations Initial Environmental Examination Jan 2014
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: District 8 220 kV Substation and Upgraded Transmission Line Initial Environmental Examination Jan 2014
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Tham Luong 110 kV Substation and Underground Transmission Line Initial Environmental Examination Jan 2014
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Environmental Assessment and Measures, Environmental Assessment and Review Framework Environmental Assessment and Review Framework Dec 2013
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: Noi Bai Airport 110 kV Substation and Transmission Line Initial Environmental Examination Dec 2013
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: 110 kV Tran Hung Dao, Phuong Liet and Son Tay Substations Resettlement Plans Dec 2013
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: 110 kV Noi Bai Airport Substation and Associated 110 kV Transmission Line Resettlement Plans Dec 2013
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: 110 kV Underground Cable Connecting To Tham Luong Substation and Tham Luong 110 kV Substation Resettlement Plans Dec 2013
Ha Noi and Ho Chi Minh City Power Grid Development Sector Project: District 8 220 kV Substation and Nam Sai Gon - District 8 220 kV Transmission Line Resettlement Plans Nov 2013

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.