Philippines: KALAHI-CIDSS National Community-Driven Development Project

Sovereign Project | 46420-002 Status: Active

Summary

ADB is helping the Philippines restore basic social services and rebuild communities devastated by Typhoon Yolanda, known internationally as Haiyan. The emergency assistance loan will support the government's KALAHI-CIDSS National Community-Driven Development Project. It will help build the capacity of communities to identify, prioritize, budget, and implement needed projects.

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name KALAHI-CIDSS National Community-Driven Development Project
Project Number 46420-002
Country Philippines
Project Status Active
Project Type / Modality of Assistance Grant
Loan
Source of Funding / Amount
Loan 3100-PHI: KALAHI CIDSS National Community-Driven Development Project
Ordinary capital resources US$ 372.10 million
Loan: KALAHI-CIDSS National Community-Driven Development Project
World Bank (IBRD) US$ 479.00 million
Grant 0472-PHI: KALAHI CIDSS National Community-Driven Development Project - Additional Financing
Typhoon Yolanda Multi-Donor Trust Fund US$ 5.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector

Education - Pre-primary and primary

Public sector management - Decentralization - Social protection initiatives

Gender Equity and Mainstreaming Gender equity
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome

Access will be measured once the subprojects are completed.

The participation rate of households in KC-NCDDP barangay assemblies (BA) is relatively high at an average of 78% (59% women). These BAs were attended by 66% of Pantawid Pamilyang Pilipino Program (4Ps) household beneficiaries in the covered areas.

Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)

As of 6 January 2016, 3221 subprojects out of 9,709 approved subprojects were completed.

20% of paid jobs held by women

This target has been incorporated in the CEAC process being adopted by the project.

As of March 2016, 57% of the 504,272 trained community volunteers are women.

During the MTR in March 2016, the EA reported that 99,714 community volunteers hold leadership positions in committees and 55% of them are women.

Achieved. Use of E-RFR system began in December 2014

Achieved 100%. EA's information system has been designed to generate sex-disaggregated data.

Gender targets have been incorporated in the CEAC process

Geographical Location Nationwide

Safeguard Categories

Environment B
Involuntary Resettlement B
Indigenous Peoples A

Summary of Environmental and Social Aspects

Environmental Aspects

During the inception mission, it was recommended to incorporate ADB safeguards requirements consistently in the Operations Manual, DROM, and the Environmental and Social Management Framework (ESMF). DSWD made the necessary revisions in the said documents.

From June to August 2015, a joint ADB-World Bank safeguards mission was conducted in Regions 4B, 5, 8, and 13 and looked into the safeguards compliance during subproject implementation. The findings and lessons learnt will be incorporated in the implementation of Cycle 2 and enhancement of the ESMF and related tools.

Involuntary Resettlement

During the inception mission, it was recommended to incorporate ADB safeguards requirements consistently in the Operations Manual, DROM, and the ESMF. DSWD made the necessary revisions in the said documents.

During the safeguards mission in January 2015, ADB and the EA agreed on additional social safeguards missions to project areas where IPs may be more vulnerable due to problems in access and decision-making systems, and for monitoring progress and discussions with program staff and stakeholders. External monitoring would be conducted on a sample of subprojects with positive and negative IP and IR impacts on a regular basis and reports would be disclosed in the ADB website. The mission also recommended the following: (i) provision of the projects Resettlement Framework and IP Planning Framework to ACTs, (ii) translation of ESMP to Tagalog, and (iii) creation of a discussion forum on safeguards and gender issues for ACTs.

From June to August 2015, a joint ADB-World Bank safeguards mission was conducted in Regions 4B, 5, 8, and 13 and looked into the safeguards compliance during subproject implementation. The findings and lessons learnt will be incorporated in the implementation of Cycle 2 and enhancement of the ESMF and related tools.

Indigenous Peoples

During the inception mission, it was recommended to incorporate ADB safeguards requirements consistently in the Operations Manual, DROM, and the Environmental and Social Management Framework. DSWD made the necessary revisions in the said documents.

During the safeguards mission in January 2015, ADB and the EA agreed on additional social safeguards missions to project areas where IPs may be more vulnerable due to problems in access and decision-making systems, and for monitoring progress and discussions with program staff and stakeholders. External monitoring would be conducted on a sample of subprojects with positive and negative IP and IR impacts on a regular basis and reports would be disclosed in the ADB website. The mission also recommended the following: (i) provision of the projects Resettlement Framework and IP Planning Framework to ACTs, (ii) translation of ESMP to Tagalog, and (iii) creation of a discussion forum on safeguards and gender issues for ACTs.

From June to August 2015, a joint ADB-World Bank safeguards mission was conducted in Regions 4B, 5, 8, and 13 and looked into the safeguards compliance during subproject implementation. The findings and lessons learnt will be incorporated in the implementation of Cycle 2 and enhancement of the ESMF and related tools.

Stakeholder Communication, Participation, and Consultation
During Project Design Conducted consultations with different stakeholders and coordination with development partners.
During Project Implementation Participation of communities, local government units, and civil society organizations is a key feature of project implementation.

Responsible Staff

Responsible ADB Officer Joel Mangahas
Responsible ADB Department Southeast Asia Department
Responsible ADB Division Human and Social Development Division, SERD
Executing Agencies
Department of Social Welfare and Development
NPMO@ECD.GOV.PH
Batasan Pambansa Complex
Constitution Hills, Quezon City
Philippines

Timetable

Concept Clearance 17 Dec 2012
Fact Finding 11 Feb 2013 to 22 Feb 2013
MRM 18 Apr 2013
Approval -
Last Review Mission -
Last PDS Update 30 Mar 2016

Grant 0472-PHI

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
04 Mar 2016 21 Mar 2016 11 May 2016 30 Jun 2018 - -
Financing Plan Grant Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 5.47 Cumulative Contract Awards
ADB 0.00 04 Mar 2016 0.00 0.00 0%
Counterpart 0.47 Cumulative Disbursements
Cofinancing 5.00 04 Mar 2016 0.00 0.50 10%

Loan 3100-PHI

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
16 Dec 2013 26 Mar 2014 10 Jun 2014 30 Jun 2018 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 663.66 Cumulative Contract Awards
ADB 372.10 16 Dec 2013 195.20 0.00 52%
Counterpart 291.56 Cumulative Disbursements
Cofinancing 0.00 16 Dec 2013 224.17 0.00 60%

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Emergency Assistance for the KALAHI CIDSS National Community-Driven Development Project Resettlement Frameworks Dec 2013
Emergency Assistance for the KALAHI CIDSS National Community-Driven Development Project Indigenous Peoples Planning Frameworks/Indigenous Peoples Development Frameworks Dec 2013
Emergency Assistance for the KALAHI CIDSS National Community-Driven Development Project Environmental Assessment and Review Framework Dec 2013
Community-Driven Development Support Project (Draft) Environmental Assessment and Review Framework Apr 2013
Community-Driven Development Support Project Indigenous Peoples Planning Frameworks/Indigenous Peoples Development Frameworks Apr 2013
Community-Driven Development Support Project (Draft) Resettlement Frameworks Apr 2013

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.