Sri Lanka: Green Power Development and Energy Efficiency Improvement Investment Program

Sovereign Project | 47037-002 Status: Closed

Summary

Latest Project Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Green Power Development and Energy Efficiency Improvement Investment Program
Project Number 47037-002
Country Sri Lanka
Project Status Closed
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 8393-SRI: Green Power Development and Energy Efficiency Improvement Investment Program
Technical Assistance Special Fund US$ 700,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector

Energy - Electricity transmission and distribution - Energy efficiency and conservation - Renewable energy generation - wind

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design Stakeholder participation and consultation were conducted during PPTA project design.
During Project Implementation Regular communication via fax and/or email is conducted with the representatives of the Ministry of Power and Energy (the Executing Agency) and the Ceylon Electricity Board and the Sustainable Energy Authority (the Implementing Agencies). Stakeholder consultations are being conducted during PPTA implementation.

Business Opportunities

Consulting Services A consulting firm will be recruited for the TA project with 17.5 person-months for international and 19.0 person-months for national consultants. Taking into consideration the complexity of the investment program, the firm will be recruited using quality and cost based selection methodology with an 90:10 technical-cost weighting based on simplified technical proposal. The consulting firm will conduct technical, economic, financial, and governance due diligence, prepare project cost estimates, procurement plan and implementation schedule. The international and national environmental and social development specialists will be recruited on an individual basis to ensure that that they start their field activities early in the process due to the expected environmental and involuntary resettlement categories A for the MFF. Consultants will be recruited following Guidelines on the Use of Consultants by ADB and Its Borrowers, April 2010.

Responsible Staff

Responsible ADB Officer Mukhtor Khamudkhanov
Responsible ADB Department South Asia Department
Responsible ADB Division Energy Division, SARD
Executing Agencies
Ministry of Power and Renewable Energy
72 Ananada Kumaraswamy Mawatha
Colombo 07, Sri Lanka

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
Last PDS Update 29 Sep 2014

TA 8393-SRI

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
25 Jun 2013 06 Aug 2013 06 Aug 2013 31 May 2014 31 Jul 2015 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
700,000.00 0.00 0.00 0.00 0.00 0.00 700,000.00 25 Jun 2013 670,387.20

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.