Sri Lanka: Green Power Development and Energy Efficiency Improvement Investment Program

Sovereign Project | 47037-003

Summary

In recent years, Sri Lanka has improved its energy sector and achieved a national electrification ratio of 94% (2012) as compared with 29% in 1990. However, a longer-term challenge is to reduce its high dependence on expensive fossil fuel energy. The energy sector struggles to (a) meet growing demand for electricity at a low cost and acceptable reliability rates, and (b) attain long term sustainability. The share of thermal oil-fired energy in the power generation mix has increased from 6% in 1995 to 59% in 2012 that creates a high energy cost base. Demand growth has been mostly met by expensive oil-fired thermal plants. This is not a viable and sustainable solution to the country's energy security and environment protection in the long term. Diversification of the generation mix primarily to renewable energy sources, improved network efficiency, reduced technical losses and supply and demand side management is the only way to correct this situation.

Latest Project Documents

Consulting Notices

See also: CMS

No notices are currently available for this project.

Procurement Notices

See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Name Green Power Development and Energy Efficiency Improvement Investment Program
Project Number 47037-003
Country Sri Lanka
Project Status Approved
Project Type / Modality of Assistance Loan
Source of Funding / Amount
MFF Facility Concept 0084-SRI: Green Power Development and Energy Efficiency Improvement Investment Program
Asian Development Fund US$ 84.00 million
Ordinary capital resources US$ 216.00 million
Agence Francaise de Developpement US$ 60.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Knowledge solutions
Partnerships
Sector / Subsector Energy - Energy efficiency and conservation - Large hydropower generation
Gender Equity and Mainstreaming No gender elements
Description In recent years, Sri Lanka has improved its energy sector and achieved a national electrification ratio of 94% (2012) as compared with 29% in 1990. However, a longer-term challenge is to reduce its high dependence on expensive fossil fuel energy. The energy sector struggles to (a) meet growing demand for electricity at a low cost and acceptable reliability rates, and (b) attain long term sustainability. The share of thermal oil-fired energy in the power generation mix has increased from 6% in 1995 to 59% in 2012 that creates a high energy cost base. Demand growth has been mostly met by expensive oil-fired thermal plants. This is not a viable and sustainable solution to the country's energy security and environment protection in the long term. Diversification of the generation mix primarily to renewable energy sources, improved network efficiency, reduced technical losses and supply and demand side management is the only way to correct this situation. The transmission network needs expansion and modernization, particularly in the former conflict-affected areas in Northern and Eastern provinces. The 33 kilovolt medium voltage network needs to expand power supply into rural areas where many households have poor reliability and inadequate quality of electricity supply. For sustainable functioning of the power sector, the government pursues financial, managerial, and institutional reforms in line with the Sri Lanka Electricity Act, 2009.
Project Rationale and Linkage to Country/Regional Strategy Sri Lanka has a national investment program that is based on 10-Year Development Framework prepared in 2006 and updated in 2010. The framework includes a long-term energy sector investment program, sector roadmap, and appropriate policy and reform measures that are linked to a National Energy Policy and Strategies. The objective is to (i) increase power supply capacity to around 6,400 MW by 2020 and reduce the generation cost by adding aggregate base load capacity of around 2,000 MW from three coal-fired plants; (ii) increase the share in grid energy supply from nonconventional renewable energy sources to 20% by 2020; and (iii) reduce the total losses in the network to 10.0% by 2020. The government's intention to develop 2000 MW of coal-fired capacity aims to pursue cost recovery in expectation that with the introduction of low-cost coal-fired generation it will be possible to reduce the current high cost of thermal power generation and achieve cost recovery from 2017. It is complimentary to the development of renewable energy to achieve the energy security. As part of its cost recovery strategy, the government increased retail electricity tariffs by 35% on average in April 2013. While the government aims to increase supply capacity and replace expensive and inefficient oil-fired power plants by constructing the coal-fired plants, the remaining supply capacity will come from renewable sources (and conversion of the oil-fired plants to gas-fired plants in the future). The 20% increase in power generation from nonconventional renewable sources will be in addition to 28% (2012) of the conventional hydropower and will ensure that a substantial portion of electricity is generated by domestic clean energy sources in the future. This will address the critical issue of the energy security.
Impact increased access to clean and reliable power supply.
Project Outcome
Description of Outcome enhanced clean power generation, system efficiency and reliability.
Progress Toward Outcome
Implementation Progress
Description of Project Outputs

Hydropower generation developed and connected to the grid in the Central Province

Transmission infrastructure enhanced

Efficiency of medium voltage network improved

Demand-side management for energy efficiency improved

Capacity development support provided to Ceylon Electricity Board.

Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location
Summary of Environmental and Social Aspects
Environmental Aspects Category A
Involuntary Resettlement Category A
Indigenous Peoples Category C
Stakeholder Communication, Participation, and Consultation
During Project Design Consultations were carried out with various stakeholders, such as village community, local residents, women's group in the villages, representatives of government officials and executing and implementing agencies. Focus group discussions were conducted with 34 communities in various transmission and distribution subproject locations. Stakeholders were informed about the new project and program. Formal and informal consultations were carried out for the hydropower project including the host community. A village committee was formed in the hydropower project area to act as a key stakeholder during land acquisition and resettlement implementation.
During Project Implementation Consultation will continue with all stakeholders, including civil society, during investment program implementation. For the hydropower project in Moragolla, a housing committee and a resettlement committee, with representation from affected people, will work closely with Ceylon Electricity Board (CEB) on implementation of land acquisition and resettlement issues. Continuing consultations are and will be ongoing with wildlife stakeholder organizations, assessing reservoir safety, and developing an appropriate mechanism to guarantee downstream flows between CEB and the Mahaweli Authority to maintain the endangered fish in the tailrace of the Moragolla dam. Information dissemination will continue during program implementation.
Business Opportunities
Consulting Services A consulting firm will be recruited for the TA project with 17.5 person-months for international and 19.0 person-months for national consultants. Taking into consideration the complexity of the investment program, the firm will be recruited using quality and cost based selection methodology with an 90:10 technical-cost weighting based on simplified technical proposal. The consulting firm will conduct technical, economic, financial, and governance due diligence, prepare project cost estimates, procurement plan and implementation schedule. The international and national environmental and social development specialists will be recruited on an individual basis to ensure that that they start their field activities early in the process due to the expected environmental and involuntary resettlement categories A for the MFF. Consultants will be recruited following Guidelines on the Use of Consultants by ADB and Its Borrowers, April 2010.
Procurement Procurement of works, goods, and services will be carried out in accordance with ADB's Procurement Guidelines. ADB will allow advance contracting. ADB's Procurement Guidelines allow for the use of domestic preference to the goods and turnkey contracts. The Government has requested for the domestic preference for goods and turnkey contracts and a provision will be made in the loan agreement and further details of its application will be included in the bidding documents. It will be applicable to domestically manufactured goods in single responsibility turnkey contracts where the cost of the goods and supplies for permanent works is estimated prior to the bidding is equal or exceed 60% of such works. International competitive bidding (ICB) procedures will be used for procurement packages for the hydropower plant, 132 kV and 220 kV transmission lines, 220/132/33 kV grid substations, and 33 kV distribution lines and gantries and DSM pilot subprojects. CEB will recruit consultants to provide technical, supervision and monitoring support for implementation of hydropower power generation and other subprojects as well as capacity building for power sector development. The consultants will be recruited using ADB's Guidelines on Use of Consultants.
Responsible ADB Officer Mukhtor Khamudkhanov
Responsible ADB Department South Asia Department
Responsible ADB Division Energy Division, SARD
Executing Agencies
Ministry of Power and Energy (MOPE)72, Ananada Kumaraswamy Mawatha
Colombo 07, Sri Lanka
Timetable
Concept Clearance 25 Jun 2013
Fact Finding 17 Feb 2014 to 21 Feb 2014
MRM 07 Apr 2014
Approval 15 Jul 2014
Last Review Mission -
Last PDS Update 29 Sep 2014

MFF Facility Concept 0084-SRI

Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 440.00 Cumulative Contract Awards
ADB 300.00 - 0.00 0.00 %
Counterpart 80.00 Cumulative Disbursements
Cofinancing 60.00 - 0.00 0.00 %

Evaluation Documents

See also: Independent Evaluation

No documents found.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.