China, People's Republic of: Chemical Industry Energy Efficiency and Emission Reduction Project

Sovereign Project | 47051-001 Status: Active

Summary

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents

None currently available.


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Chemical Industry Energy Efficiency and Emission Reduction Project
Project Number 47051-001
Country China, People's Republic of
Project Status Active
Project Type / Modality of Assistance Technical Assistance
Source of Funding / Amount
TA 8383-PRC: Chemical Industry Energy Efficiency and Emission Reduction Project
Technical Assistance Special Fund US$ 700,000.00
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Private sector development
Sector / Subsector

Energy - Energy efficiency and conservation

Gender Equity and Mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues)
Geographical Location

Summary of Environmental and Social Aspects

Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation Consultant services have been completed and loan negotiations for the proposed loan project was completed on 7-8 September 2015. A legal expert will be recruited to assist in drafting the subloan and onlending agreements.

Business Opportunities

Consulting Services

The PPTA will be implemented in two parts. Part 1 will focus on the (i) development of an innovative ESCO financing mechanism, and (ii) energy audit and environmental impact assessment (EIA). A review of ChemChina and chemical industry energy efficiency and emission reduction market assessment and barrier analysis will also be undertaken during part 1. Since these activities are independent activities, four individual consultants (2 international for a total of 6.5 person-months and 2 national for a total of 7 person-months) will be recruited in accordance with ADB's Guidelines on the Use of Consultants (2010, as amended from time to time). The energy efficiency finance experts will work closely with ChemChina, NDRC, and ADB to develop the financing mechanism. The international environment expert will be supported by a national technical expert to prepare the energy audit and the EIA.

Part 2 will be undertaken by a consulting firm, which will prepare the technical, economic, and financial due diligence of the subprojects to be undertaken. It will also provide capacity strengthening and project implementation support and capacity development measures to the project management office and other stakeholders, if needed. The detailed tasks to be undertaken by the consulting firm will be firmed up towards the end of the part 1. The consulting firm will be recruited in accordance with ADB's Guidelines on the Use of Consultants (2010, as amended from time to time) through quality- and cost-based selection method (with a quality-cost ratio of 80:20) following the simplified technical proposal.

Responsible Staff

Responsible ADB Officer Annika Seiler
Responsible ADB Department East Asia Department
Responsible ADB Division Energy Division, EARD
Executing Agencies
China National Chemical Corporation Group
Cai Ting, Director, Department of Planning & Development
caiting@chemchina.com
62, Beisihuan Xilu, Haidian District, Beijing 100080 PRC

Timetable

Concept Clearance -
Fact Finding -
MRM -
Approval -
Last Review Mission -
Last PDS Update 23 Sep 2015

TA 8383-PRC

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
17 Jun 2013 17 Jul 2013 17 Jul 2013 15 Sep 2014 31 Jan 2016 -
Financing Plan/TA Utilization Cumulative Disbursements
ADB Cofinancing Counterpart Total Date Amount
Gov Beneficiaries Project Sponsor Others
700,000.00 0.00 150,000.00 0.00 0.00 0.00 850,000.00 17 Jun 2013 629,770.28

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.