India: Madhya Pradesh Power Transmission and Distribution System Improvement Project

Sovereign Project | 47100-004 Status: Active

Summary

ADB is helping upgrade and expand the transmission and distribution of electricity in India’s Madhya Pradesh to meet growing demand for energy in the state. The project will fund about 1,800 circuit kilometers of transmission lines and more than 3,100 circuit kilometers of distribution lines, and construct or upgrade substations. It will also build institutional capacity.

Latest Project Documents

Consulting Notices See also: CMS

No notices are currently available for this project.

Procurement Notices See also: Operational Procurement

No notices are currently available for this project.

Procurement Documents


Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Public Communications Policy (PCP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

 
Project Name Madhya Pradesh Power Transmission and Distribution System Improvement Project
Project Number 47100-004
Country India
Project Status Active
Project Type / Modality of Assistance Loan
Source of Funding / Amount
Loan 3066-IND: Madhya Pradesh Power Transmission and Distribution System Improvement Project
Ordinary capital resources US$ 350.00 million
Strategic Agendas Environmentally sustainable growth
Inclusive economic growth
Drivers of Change Governance and capacity development
Sector / Subsector

Energy - Electricity transmission and distribution

Gender Equity and Mainstreaming No gender elements
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Project Outcome

Description of Outcome
Progress Toward Outcome Implementation is ongoing.
Implementation Progress
Description of Project Outputs
Status of Implementation Progress (Outputs, Activities, and Issues) All contracts have been awarded, implementation is ongoing.
Geographical Location

Safeguard Categories

Environment B
Involuntary Resettlement B
Indigenous Peoples C

Summary of Environmental and Social Aspects

Environmental Aspects The initial environmental examination was disclosed on the ADB website. Consultants for preparing updated Social and Environmental Monitoring Report are being recruited by executing agencies.
Involuntary Resettlement The resettlement plan was disclosed on the ADB website.
Indigenous Peoples Social assessments conducted during project preparation found no indigenous peoples who would be impacted by project activities. If any project impact on indigenous peoples is found during implementation, project authorities will either formulate an indigenous peoples plan or revise the approved resettlement plan, incorporating additional entitlements to address them. The revised resettlement plan or the new indigenous peoples plan will be submitted to ADB for review and approval.
Stakeholder Communication, Participation, and Consultation
During Project Design During Project preparation, consultations were held with the concerned Government officials. Additionally, consultations were also carried out with the affected persons in the project area and with the local community.
During Project Implementation Public consultation with all stakeholders will continue throughout implementation of the project.

Business Opportunities

Consulting Services Consultant requirements are covered under the PPTA for Madhya Pradesh Transmission and Distribution System Improvement Project with a total cost of $750,000. Total consultant requirement is 39 months of which 21 person-months are international.
Procurement All procurement of goods and works shall be undertaken in accordance with ADB's Procurement Guidelines. International competitive bidding procedures shall be followed for all the packages.

Responsible Staff

Responsible ADB Officer Jyotirmoy Banerjee
Responsible ADB Department South Asia Department
Responsible ADB Division India Resident Mission
Executing Agencies
Controller of Aid Accounts and Audit
CAAA@NIC.IN.
5th Floor, B Wing, Janpath Bhawan
Janpath, New Delhi 110 001
India
Madhya Pradesh Poorv Kshetra Vidyut Vitaran Co Ltd
CMDEAST@HOTMAIL.COM
Block No. 7, Shakti Bhawan, Vidyut Nagar
Jabalpur, Madhya Pradesh 482 008 India
M Pradesh Madhya Kshetra Vidyut Vitaran Co.Ltd.
CMD@MPMKVVC.COM
Nishtha Parisar, Govindpura, Bhopal
Madhya Pradesh, 461 023, India
M Pradesh Paschim Kshetra Vidyut Vitaran Co. Ltd.
CMDWZ.INDORE@GMAIL.COM
Indore, Madhya Pradesh
India
Madhya Pradesh Power Transmission Company Limited
Madhya Pradesh

Timetable

Concept Clearance 29 May 2013
Fact Finding 05 Aug 2013 to 16 Aug 2013
MRM 05 Sep 2013
Approval -
Last Review Mission -
Last PDS Update 04 Mar 2016

Loan 3066-IND

Milestones
Approval Signing Date Effectivity Date Closing
Original Revised Actual
27 Nov 2013 17 Feb 2014 21 Mar 2014 31 Dec 2018 - -
Financing Plan Loan Utilization
Total (Amount in US$ million) Date ADB Others Net Percentage
Project Cost 500.00 Cumulative Contract Awards
ADB 350.00 27 Nov 2013 334.87 0.00 96%
Counterpart 150.00 Cumulative Disbursements
Cofinancing 0.00 27 Nov 2013 82.28 0.00 24%

Safeguard Documents See also: Safeguards

Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

Title Document Type Document Date
Madhya Pradesh Power Transmission and Distribution System Improvement Project: Environmental Monitoring Report (August 2015-January 2016) Environmental Monitoring Reports Mar 2016
Madhya Pradesh Power Transmission and Distribution System Improvement Project: Environmental Monitoring Report by DISCOM-C (February-July 2015) Environmental Monitoring Reports Sep 2015
Madhya Pradesh Power Transmission and Distribution System Improvement Project: Environmental Monitoring Report by DISCOM-W (January-June 2015) Environmental Monitoring Reports Sep 2015
Madhya Pradesh Power Transmission and Distribution System Improvement Project: Environmental Monitoring Report (DISCOM-E) (January-June 2015) Environmental Monitoring Reports Aug 2015
Madhya Pradesh Power Transmission and Distribution System Improvement Project: Environmental Monitoring Report (DISCOM-W) (July-December 2014) Environmental Monitoring Reports May 2015
Madhya Pradesh Power Transmission and Distribution System Improvement Project: Environmental Monitoring Report (DISCOM-E) (July-December 2014) Environmental Monitoring Reports Mar 2015
Madhya Pradesh Power Transmission and Distribution System Improvement Project: Environmental Monitoring Report (February-July 2014) Environmental Monitoring Reports Mar 2015
Madhya Pradesh Power Transmission and Distribution System Improvement Project: Environmental Monitoring Report (January-June 2014) Environmental Monitoring Reports Jan 2015
Madhya Pradesh Power Transmission and Distribution System Improvement Project Initial Environmental Examination Sep 2013
Madhya Pradesh Power Transmission and Distribution System Improvement Project Resettlement Plans Sep 2013

Evaluation Documents See also: Independent Evaluation

None currently available.

Related Publications

None currently available.


The Public Communications Policy (PCP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.