Dili Water Supply Performance Improvement: Final Report

Date: December 2010
Country:
Subject:
Document Type: Technical Assistance Consultant's Reports
Project Number: 39152-012

Download Document



Description

This final report for the technical assistance project Dili Water Supply Performance Improvement in Timor-Leste provides information on technical assistance activities conducted during the project, specific issues and observations, lessons learned, and recommendations.  This report was prepared at the conclusion of the Dili Water Supply Performance Improvement (DWSPI) Technical Assistance (TA) after 30 months of implementation.